Welcome!

Microsoft Cloud Authors: Pat Romanski, Elizabeth White, Liz McMillan, Mihai Corbuleac, David Bermingham

News Feed Item

Avala Announces Positive Preliminary Economic Assessment and Updated Mineral Resource for Timok Gold Project, Serbia

LONGUEUIL, QUEBEC -- (Marketwired) -- 06/20/14 -- Avala Resources Ltd. (TSX VENTURE: AVZ) (the "Company" or "Avala") is pleased to announce the results of an independent preliminary economic assessment ("PEA") and an updated mineral resource estimate for its 100% owned Timok Gold Project located in Eastern Serbia.

Highlights of the Timok Gold Project PEA


--  Open pit gold mine with an initial life of mine ("LOM") of 8.4 years.

--  Average annual gold production LOM of approximately 81,000 ounces at
    US$788 cash cost per ounce.

--  Average annual gold production of approximately 92,000 ounces for the
    first three years of production.

--  LOM gold production of 680,000 ounces.

--  Average LOM operating costs (including royalties, selling costs,
    closure/environmental costs and sustaining capital) of U$843 per ounce
    of gold.

--  Annual processing rate of 1.68 million tonnes per year.

--  Average LOM gold recovery of 75% from milling and flotation to produce a
    gold-rich concentrate.

--  Estimated pre-production capital cost of US$177 million, including
    working capital.

--  LOM net cash flow of US$127.6 million at a gold price of US$1300 per
    ounce.

--  Net present value ("NPV") of US$65 million at a 5% discount rate and a
    gold price of US$1300 per ounce generating an internal rate of return
    ("IRR") of 14.3%.

--  Project payback of 4.0 years.

--  All economic outcomes presented in the PEA are the same on a pre- and
    after-tax basis as it is expected that the proposed level of investment
    and employment associated with the implementation of the proposed mine
    would qualify for a 10 year tax holiday under current Serbian tax
    legislation.

--  Over 99.5% of the resources within the PEA pit designs are categorized
    as indicated resources.

Purpose of the Study

The purpose of the PEA was to (a) provide a preliminary concept for the scale and type of mining project that the Timok Gold Project could support, (b) identify areas where additional work is required before a pre-feasibility study can be completed and (c) demonstrate potential for positive economic returns that would justify continued investment in the Timok Gold Project.

The PEA is preliminary in nature, based on mineral resources, and provides an indication of potential viability of the Timok Gold Project. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. The PEA includes inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted to the measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

Additional details will be provided in a NI 43-101 technical report to be filed on SEDAR within 45 days.

Project Throughput Trade-Off Study

Prior to initiating the PEA, Avala carried out an internal, preliminary trade-off study to determine the optimum throughput rate for the Timok Gold Project. Throughput rates of 5,000 tonnes per day (1.68 million tonnes per annum) to 10,000 tonnes per day (3.36 million tonnes per annum) were evaluated at gold prices from US$1250 per ounce to US$1500 per ounce. The results of the study indicated that 5,000 tonnes per day provides the best project economics relative to other operating and financial parameters.

Summary of Base Case Results

The base case assumptions included revenues using a gold price of US$1300 per ounce and current prices for fuel, reagents, labor, power and other consumables in Serbia. The key results are as follows:


----------------------------------------------------------------------------
               Preliminary Economic Analysis Base Case Summary
----------------------------------------------------------------------------
Item                                                                   Value
----------------------------------------------------------------------------
LOM average gold recovery (%)                                             75
----------------------------------------------------------------------------
Gold ounces produced (koz)                                               680
----------------------------------------------------------------------------
Average annual gold production (koz)                                      81
----------------------------------------------------------------------------
Ore mined (Mt)                                                          14.1
----------------------------------------------------------------------------
LOM head grade (g/t Au)                                                  2.0
----------------------------------------------------------------------------
Waste material mined (Mt) (including capitalized pre-strip)             63.6
----------------------------------------------------------------------------
Waste to ore strip ratio                                                 4.5
----------------------------------------------------------------------------
Construction capital, including working capital (US$M)                 177.0
----------------------------------------------------------------------------
Sustaining capital (US$M)                                               10.6
----------------------------------------------------------------------------
Gross gold revenue (US$M)                                              839.5
----------------------------------------------------------------------------
Net income (US$M) (1)                                                  127.6
----------------------------------------------------------------------------
Net present value at 5% discount rate (US$M) (1)                        64.9
----------------------------------------------------------------------------
IRR (%) (1)                                                             14.3
----------------------------------------------------------------------------
Mine life (years)                                                        8.4
----------------------------------------------------------------------------
Payback (years) (1)                                                      4.0
----------------------------------------------------------------------------
LOM direct cost (mining, processing and G&A) (US$/oz)                    567
----------------------------------------------------------------------------
LOM cash cost (direct cost + royalties and selling costs) (US$/oz)       788
----------------------------------------------------------------------------
LOM operating cost (cash cost + closure/environmental costs &
 sustaining capital) (US$/oz)                                            843
----------------------------------------------------------------------------
LOM total cost (operating cost + implementation capital) (US$/oz)       1104
----------------------------------------------------------------------------
Average LOM mining cost (US$/t mined)                                  14.92
----------------------------------------------------------------------------
Average LOM processing cost (US$/t processed)                          11.69
----------------------------------------------------------------------------
Average LOM cost of sales (US$/t processed)                             7.96
----------------------------------------------------------------------------
Annual G&A costs (US$M)                                                 1.24
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
qualification to a 10-year tax holiday under current tax legislation in
Serbia.

The PEA is subject to a number of assumptions, including amongst others, that an environmental impact assessment will be completed within the required timeline, that all required permits will be obtained in a timely manner, that the Timok Gold Project will have the support of the local government and community, that the regulatory environment will remain consistent and that estimated costs will not increase materially. The table below summarizes key assumptions in the PEA.



----------------------------------------------------------------------------
               Preliminary Economic Analysis Key Assumptions
----------------------------------------------------------------------------
Costs and Recoveries                    Capital Estimate
----------------------------------------------------------------------------
Fuel cost (US$/liter)          1.22     Mining (US$M)                 27.24
----------------------------------------------------------------------------
Electricity cost
(US$/kWh)                      0.07     Process plant (US$M)          66.64
----------------------------------------------------------------------------
Mill power usage                        Plant infrastructure
(kWh/t)                          35     (US$M)                        16.72
----------------------------------------------------------------------------
Mining (US$/t) - unit                   Area infrastructure
cost (ore)                2.36-2.55     (US$M)                         7.29
----------------------------------------------------------------------------
Mining (US$/t) -
overall cost                            Regional
(waste+ore)                   14.92     infrastructure (US$M)          1.86
----------------------------------------------------------------------------
Grade control (US$/t)          0.45     Miscellaneous                  7.62
----------------------------------------------------------------------------
                                        Sub-Total Direct Cost
Rehabilitation (US$/t)         0.09     (US$M)                       127.37
----------------------------------------------------------------------------
Stockpile re-handling
(US$/t)                        1.50     Indirect cost (US$M)          19.14
----------------------------------------------------------------------------
Plant feed at ROM pad                   Accuracy provision
(US$/t)                        0.25     (US$M)                        22.22
----------------------------------------------------------------------------
Ore haulage (US$/t)                     Sub-Total Initial
(Kraku Pester)                 3.50     Capital (US$M)               168.73
----------------------------------------------------------------------------
Processing (US$/t) -
full production year          11.55     Owner's costs (US$M)           8.29
----------------------------------------------------------------------------
Concentrate costs
(TC/RC, transport                       Total Initial Capital
etc.) (US$/dry t                        (US$M) - including
concentrate)            200.0-203.8     working capital              177.02
----------------------------------------------------------------------------
General services
(US$/t)                        0.74
----------------------------------------------------------------------------
CAT mining equipment
financing cost (US$/t)         1.15     State royalty                     5%
----------------------------------------------------------------------------
Total operating cost
(US$/t)                       37.99
----------------------------------------------------------------------------
Plant recoveries:                       Plant recoveries:
Bigar Hill                       80%    Kraku Pester                     56%
----------------------------------------------------------------------------
Plant recoveries:                       Overall plant
Korkan                           68%    recoveries: LOM                  75%
----------------------------------------------------------------------------

A full list of the assumptions will be set out in the NI 43-101 technical report for the PEA.

Project Sensitivities

The Timok Gold Project PEA is based on producing a gold-rich sulphide concentrate for sale to smelters. A small positive increase in gold price and/or gold recovery has a marked effect on the project economics, as illustrated in the table below (with the pit designs and schedules unchanged). The optimum pit shells, which form the basis of the PEA pit designs, are most sensitive to plant recovery and the gold price. The Company believes that the metallurgical testwork recommended in the PEA may result in higher overall plant recoveries, which would result in a higher conversion ratio. Independently, an increase in the gold price will also increase the conversion ratio, as larger pits are developed. As noted below, Avala also intends to assess the potential for underground extraction of gold mineralisation beneath the open pit designs.


----------------------------------------------------------------------------
            Preliminary Economic Analysis Sensitivity Summary (1)
----------------------------------------------------------------------------
                                    Gold Price    [email protected]%    [email protected]%       IRR
Sensitivity                           (US$/oz)    (US$M)    (US$M)       (%)
----------------------------------------------------------------------------
                           Gold Price Sensitivity
----------------------------------------------------------------------------
Gold price +US$150                        1450     219.2     132.1      22.4
----------------------------------------------------------------------------
Gold price +US$100                        1400     188.7     109.7      19.8
----------------------------------------------------------------------------
Gold price +US$50                         1350     158.1      87.3      17.2
----------------------------------------------------------------------------
Base case gold price                      1300     127.6      64.9      14.3
----------------------------------------------------------------------------
Gold price -US$50                         1250      97.0      42.6      11.4
----------------------------------------------------------------------------
Gold price -US$100                        1200      66.5      20.2       8.2
----------------------------------------------------------------------------
                            Recovery Sensitivity
----------------------------------------------------------------------------
Recovery +6%                              1300     191.0     111.0      19.9
----------------------------------------------------------------------------
Recovery +4%                              1300     169.9      96.6      18.1
----------------------------------------------------------------------------
Recovery +2%                              1300     148.7      80.3      16.3
----------------------------------------------------------------------------
Recovery -2%                              1300     106.4      49.6      12.3
----------------------------------------------------------------------------
Recovery -4%                              1300      85.2      34.3      10.2
----------------------------------------------------------------------------
                           Combined Sensitivities
----------------------------------------------------------------------------
Recovery +4% & gold price +US50           1350     202.1     119.2      20.8
----------------------------------------------------------------------------
Recovery +6% & gold price +US$100         1400     257.0     159.3      25.2
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
 qualification to a 10-year tax holiday under current tax legislation in
 Serbia.

Mineral Resources

In conjunction with the preparation of the PEA, the mineral resource estimates for the Bigar Hill and Korkan deposits (Oct 2013) and Kraku Pester deposit (Jan 2013) have been updated to constrain the deposits within pit shells for the purposes of the PEA, based on the assumptions, parameters and methodology that are summarised below. At this stage the Korkan East deposit has not been subject to preliminary economic assessment. The Bigar Hill, Korkan and Kraku Pester estimates are supported by 271,420.2 metres of drilling. The average drill spacing is 40 meters by 40 meters for indicated resources and 80 meters by 80 meters for inferred resources. The mineral resources for Bigar Hill, Korkan and Kraku Pester, which were used in the PEA, are listed in the table below.


----------------------------------------------------------------------------
                             TIMOK GOLD PROJECT
              INDICATED AND INFERRED RESOURCES USED IN THE PEA
----------------------------------------------------------------------------
                                 Indicated                 Inferred
                         ---------------------------------------------------
                 Cut Off                  Million                    Million
                  Grade   Million     Au   Ounces  Million     Au     Ounces
Deposit        (Au g/t)    Tonnes  (g/t)     (Au)   Tonnes  (g/t)       (Au)


----------------------------------------------------------------------------
Bigar Hill           0.3    38.62   1.19     1.48      1.3    1.3        0.1
----------------------------------------------------------------------------
Korkan               0.3    22.35   1.07     0.77      2.7    0.9        0.1
----------------------------------------------------------------------------
Kraku Pester         0.3     6.45   1.05     0.22      0.3    0.8        0.0
----------------------------------------------------------------------------
Total                       67.42   1.14     2.48      4.3    1.0        0.2
----------------------------------------------------------------------------
Notes: (1) The effective date of the updated mineral resource estimate is
           May 1, 2014.
       (2) The resource estimation was prepared by Chris Arnold MAusIMM
           CP(Geo) of AMC Consultants Limited using the Canadian Institute
           of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
           Mineral Resources and Reserves, Definitions and Guidelines
           prepared by the CIM Standing Committee on Reserve Definitions and
           adopted by the CIM Council.
       (3) The resources are constrained within pit shells returning the
           maximum undiscounted values, based on the following assumptions:
           NSR gold price of $1500/oz ($1700/oz spot price less $200/oz for
           off-site concentrate costs), 85% gold recovery for Bigar Hill and
           Korkan, 80% recovery for Kraku Pester, 55 degree pit slopes,
           US$2.00/t ore and waste mining costs (including rehabilitation
           costs) andUS$12.70/t processing and other costs, resulting in cut
           off grades of 0.32g/t for Bigar Hill and Korkan and 0.34g/t for
           Kraku Pester. Both cut off grades have been rounded to 0.3g/t for
           the reporting of resources within the designated pit shells.
       (4) Mineral resources, which are not mineral reserves, do not have
           demonstrated economic viability. The estimate of mineral
           resources may be materially affected by environmental,
           permitting, legal, title, taxation, sociopolitical, marketing, or
           other relevant issues.
       (5) The quantity and grade of reported inferred resources in this
           estimation are uncertain in nature and there has been
           insufficient exploration to define these inferred resources as
           indicated or measured mineral resources.
       (6) Totals and average grades are subject to rounding to the
           appropriate precision.
       (7) The key changes between the previous mineral resource estimate
           for the Bigar Hill, Korkan and Kraku Pester deposits (news
           release of October 16, 2013) and this updated mineral resource
           are that the updated resource estimate is constrained within a
           pit shell and has been reported at a lower cut-off, commensurate
           with the gold price and costs parameters used to defined the
           constrained pit.

The NI 43-101 technical report to be filed for the PEA will include the technical and scientific data to support the updated mineral resource estimate.

Next Steps

Subject to the availability of funds, Avala plans to do the following work to advance the Timok Gold Project.

Several metallurgical testwork programs have been undertaken since 2011 on samples selected from the Timok Gold Project deposits. Initial work investigated the potential for gold recovery from several processing options, including cyanidation techniques. During 2012 and 2013, the metallurgical testwork focus changed to the assessment of ultra-fine grinding and flotation to produce a gold-rich sulphide concentrate for treatment by others. In addition, the potential for upgrading via attritioning/scrubbing (pre-concentration) was evaluated, which showed promise but was not taken further in the PEA design. Testwork was successful in using primary grinding, ultra-fine grinding and flotation to produce a gold bearing pyritic concentrate. Metallurgical recoveries adopted for the design were 80%, 68% and 56% for Bigar Hill, Korkan and Kraku Pester deposits respectively; into a design concentrate mass pull of 4%. Testwork to support pre-feasibility study activities would include:


--  Detailed mineralogical evaluation to improve understanding of gold
    associations with gangue and sulphide minerals;

--  SAG milling characterization;

--  Further evaluation of scrubbing/attritioning (pre-concentration)
    potential;

--  Evaluation of finer grind sizes to improve flotation recovery;

--  Larger scale ultra-fine grinding testwork to confirm specific energy
    requirements and to prepare flotation feed;

--  Staged Flotation Reactor circuit testing;

--  Production of concentrate for marketing purposes; and

--  Liquid-solid separation testwork (concentrate and tailings).

Avala has developed an extensive geo-metallurgical database for the Timok Gold Project and plans to produce detailed three dimensional geometallurgical models of the deposits to assist with effective targeting of further metallurgical testwork.

Review of the Bigar Hill and Korkan resource models suggests there may be potential for underground extraction of gold mineralization beneath the current open pit designs. Avala plans to assess this potential, along with preliminary assessment of the recently announced Korkan East deposit.

During Q1 2014 Avala was granted the right to explore on the Bigar Istok license (15 square kilometers) which is located immediately due east of the Potoj Cuka Tisnica exploration license, which hosts the currently defined deposits. Previous exploration in this area has highlighted various gold-in-soil anomalies together with evidence of historic gold and base metal mineralization as defined by previous Serbian State exploration drilling. Avala believes that the exploration potential of the Bigar Istok license area, together with the various prospects located proximal to the currently defined deposits, remains high.

Qualified Persons

The PEA was completed by AMEC Australia Pty Ltd. under the supervision of Peter Nofal, FAusIMM, with participation of AMEC Growth Regions Mining Services Group UK and Gary Jobson, MAusIMM, of Macromet Pty Ltd. (metallurgy), Nick Journet, ARSM, FAusIMM, of Dumpsolver Pty Ltd.(mining), Chris Arnold MAusIMM CP(Geo), AMC UK, (geology and resource modeling), Fergus Anckorn, FAusIMM CP(Environmental), of AMEC Earth and Environmental (UK) Ltd (Environmental, Social and Permitting), Ciaran Molloy, MIMMM ICE QP of AMEC Growth Regions Specialty Mining Services Group (Geotechnical & Civil Engineering), and Rod Cameron, F.Geol.Soc.London Chartered Geologist, of AMEC Growth Regions Speciality Mining Services Group (Tailings and Water Management). The Bigar Hill, Korkan and Kraku Pester updated mineral resource estimate was undertaken by independent qualified person Chris Arnold MAusIMM CP(Geo) of AMC. Mr. Arnold has reviewed and approved the contents of this press release insofar as mineral resource estimates are concerned. Dr. Julian F. H. Barnes, FAusIMM, MAIG, a director of the Company and special consultant, is the Company's designated qualified person for purposes of the PEA. All qualified persons have reviewed and approved the disclosure in this press release related to their respective areas of expertise.

About Avala Resources Ltd.: Avala Resources is a mineral exploration company focused on the exploration and development of the Timok Gold Project in Eastern Serbia. The Timok Gold Project comprises several targets, including the Korkan, Bigar Hill, Kraku Pester, and Korkan East deposits. Avala controls 100% of this recently identified sediment-hosted gold belt which totals approximately 250 square kilometers. The common shares of Avala trade on the TSX Venture Exchange under the symbol AVZ.

Avala had approximately $1.1 million in its treasury at March 31, 2014. Avala's issued and outstanding share capital totals 254,492,223 common shares, of which approximately 53.1% is held by Dundee Precious Metals Inc. (TSX: DPM).

Additional information about the Company is available on Avala's website (www.avalaresources.com) and on SEDAR (www.sedar.com).

Cautionary Statement Regarding Forward-Looking Information

This press release contains 'forward-looking information' within the meaning of Canadian securities legislation. Forward looking information in this press release includes information about the results of a Preliminary Economic Assessment (PEA). This PEA is the first in a series of development studies for the project assessing the potential viability of a potential mining operation on the Timok Gold Project. The operating and capital costs estimated in the PEA were developed to be reasonable estimates within industry benchmarks. The PEA is intended to quantify the project's cost parameters which will, in turn, be used to guide ongoing exploration and engineering work and to define the optimal scale of the operation for a feasibility study. Forward looking information in this press release also includes information about planned metallurgical testwork and the ability to increase metal recoveries through additional work, completion of a pre-feasibility study, the potential to incorporate an underground operation into the open pit plans for the Timok Gold Project, and the exploration potential of the Bigar Istok license and the target areas nearby Bigar Hill, Korkan, Kraku Pester, and Korkan East. This press release also includes an updated mineral resource estimate. Mineral resources are not mineral reserves and do not have demonstrated economic viability. Inferred resources have a great amount of uncertainty as to their existence, and economic and legal feasibility. Since forward-looking information is based on assumptions and addresses future events and conditions, by its very nature it involves risks and uncertainties. Certain assumptions used in the PEA and the resource estimate are summarized in this press release. Actual results could differ materially from those anticipated in the forward looking information for many reasons including, but not limited to: changes in general economic conditions and conditions in the financial markets; changes in demand and prices for gold; changes in prices of inputs and other assumptions in the PEA and the resource estimate; unavailability of the 10-year tax holiday; legislative, environmental and other regulatory, political and competitive developments; operational difficulties encountered in connection with the activities of the Company; and the Company's financial condition and financial resources to execute its business plans. These and other factors referred to in public disclosures and filings by the Company should be considered carefully, and readers should not place undue reliance on the Company's forward-looking information. The Company does not undertake to update any forward-looking information, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
There are several IoTs: the Industrial Internet, Consumer Wearables, Wearables and Healthcare, Supply Chains, and the movement toward Smart Grids, Cities, Regions, and Nations. There are competing communications standards every step of the way, a bewildering array of sensors and devices, and an entire world of competing data analytics platforms. To some this appears to be chaos. In this power panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, Bradley Holt, Developer Advocate a...
In addition to all the benefits, IoT is also bringing new kind of customer experience challenges - cars that unlock themselves, thermostats turning houses into saunas and baby video monitors broadcasting over the internet. This list can only increase because while IoT services should be intuitive and simple to use, the delivery ecosystem is a myriad of potential problems as IoT explodes complexity. So finding a performance issue is like finding the proverbial needle in the haystack.
A strange thing is happening along the way to the Internet of Things, namely far too many devices to work with and manage. It has become clear that we'll need much higher efficiency user experiences that can allow us to more easily and scalably work with the thousands of devices that will soon be in each of our lives. Enter the conversational interface revolution, combining bots we can literally talk with, gesture to, and even direct with our thoughts, with embedded artificial intelligence, wh...
"delaPlex is a software development company. We do team-based outsourcing development," explained Mark Rivers, COO and Co-founder of delaPlex Software, in this SYS-CON.tv interview at 18th Cloud Expo, held June 7-9, 2016, at the Javits Center in New York City, NY.
IoT is rapidly changing the way enterprises are using data to improve business decision-making. In order to derive business value, organizations must unlock insights from the data gathered and then act on these. In their session at @ThingsExpo, Eric Hoffman, Vice President at EastBanc Technologies, and Peter Shashkin, Head of Development Department at EastBanc Technologies, discussed how one organization leveraged IoT, cloud technology and data analysis to improve customer experiences and effi...
The IoT is changing the way enterprises conduct business. In his session at @ThingsExpo, Eric Hoffman, Vice President at EastBanc Technologies, discussed how businesses can gain an edge over competitors by empowering consumers to take control through IoT. He cited examples such as a Washington, D.C.-based sports club that leveraged IoT and the cloud to develop a comprehensive booking system. He also highlighted how IoT can revitalize and restore outdated business models, making them profitable ...
Machine Learning helps make complex systems more efficient. By applying advanced Machine Learning techniques such as Cognitive Fingerprinting, wind project operators can utilize these tools to learn from collected data, detect regular patterns, and optimize their own operations. In his session at 18th Cloud Expo, Stuart Gillen, Director of Business Development at SparkCognition, discussed how research has demonstrated the value of Machine Learning in delivering next generation analytics to imp...
The cloud market growth today is largely in public clouds. While there is a lot of spend in IT departments in virtualization, these aren’t yet translating into a true “cloud” experience within the enterprise. What is stopping the growth of the “private cloud” market? In his general session at 18th Cloud Expo, Nara Rajagopalan, CEO of Accelerite, explored the challenges in deploying, managing, and getting adoption for a private cloud within an enterprise. What are the key differences between wh...
Connected devices and the industrial internet are growing exponentially every year with Cisco expecting 50 billion devices to be in operation by 2020. In this period of growth, location-based insights are becoming invaluable to many businesses as they adopt new connected technologies. Knowing when and where these devices connect from is critical for a number of scenarios in supply chain management, disaster management, emergency response, M2M, location marketing and more. In his session at @Th...
Basho Technologies has announced the latest release of Basho Riak TS, version 1.3. Riak TS is an enterprise-grade NoSQL database optimized for Internet of Things (IoT). The open source version enables developers to download the software for free and use it in production as well as make contributions to the code and develop applications around Riak TS. Enhancements to Riak TS make it quick, easy and cost-effective to spin up an instance to test new ideas and build IoT applications. In addition to...
When people aren’t talking about VMs and containers, they’re talking about serverless architecture. Serverless is about no maintenance. It means you are not worried about low-level infrastructural and operational details. An event-driven serverless platform is a great use case for IoT. In his session at @ThingsExpo, Animesh Singh, an STSM and Lead for IBM Cloud Platform and Infrastructure, will detail how to build a distributed serverless, polyglot, microservices framework using open source tec...
Apixio Inc. has raised $19.3 million in Series D venture capital funding led by SSM Partners with participation from First Analysis, Bain Capital Ventures and Apixio’s largest angel investor. Apixio will dedicate the proceeds toward advancing and scaling products powered by its cognitive computing platform, further enabling insights for optimal patient care. The Series D funding comes as Apixio experiences strong momentum and increasing demand for its HCC Profiler solution, which mines unstruc...
IoT offers a value of almost $4 trillion to the manufacturing industry through platforms that can improve margins, optimize operations & drive high performance work teams. By using IoT technologies as a foundation, manufacturing customers are integrating worker safety with manufacturing systems, driving deep collaboration and utilizing analytics to exponentially increased per-unit margins. However, as Benoit Lheureux, the VP for Research at Gartner points out, “IoT project implementers often ...
It is one thing to build single industrial IoT applications, but what will it take to build the Smart Cities and truly society changing applications of the future? The technology won’t be the problem, it will be the number of parties that need to work together and be aligned in their motivation to succeed. In his Day 2 Keynote at @ThingsExpo, Henrik Kenani Dahlgren, Portfolio Marketing Manager at Ericsson, discussed how to plan to cooperate, partner, and form lasting all-star teams to change t...
In his general session at 18th Cloud Expo, Lee Atchison, Principal Cloud Architect and Advocate at New Relic, discussed cloud as a ‘better data center’ and how it adds new capacity (faster) and improves application availability (redundancy). The cloud is a ‘Dynamic Tool for Dynamic Apps’ and resource allocation is an integral part of your application architecture, so use only the resources you need and allocate /de-allocate resources on the fly.
Presidio has received the 2015 EMC Partner Services Quality Award from EMC Corporation for achieving outstanding service excellence and customer satisfaction as measured by the EMC Partner Services Quality (PSQ) program. Presidio was also honored as the 2015 EMC Americas Marketing Excellence Partner of the Year and 2015 Mid-Market East Partner of the Year. The EMC PSQ program is a project-specific survey program designed for partners with Service Partner designations to solicit customer feedbac...
In his keynote at 18th Cloud Expo, Andrew Keys, Co-Founder of ConsenSys Enterprise, provided an overview of the evolution of the Internet and the Database and the future of their combination – the Blockchain. Andrew Keys is Co-Founder of ConsenSys Enterprise. He comes to ConsenSys Enterprise with capital markets, technology and entrepreneurial experience. Previously, he worked for UBS investment bank in equities analysis. Later, he was responsible for the creation and distribution of life sett...
Cloud computing is being adopted in one form or another by 94% of enterprises today. Tens of billions of new devices are being connected to The Internet of Things. And Big Data is driving this bus. An exponential increase is expected in the amount of information being processed, managed, analyzed, and acted upon by enterprise IT. This amazing is not part of some distant future - it is happening today. One report shows a 650% increase in enterprise data by 2020. Other estimates are even higher....
SYS-CON Events announced today that Bsquare has been named “Silver Sponsor” of SYS-CON's @ThingsExpo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. For more than two decades, Bsquare has helped its customers extract business value from a broad array of physical assets by making them intelligent, connecting them, and using the data they generate to optimize business processes.
Internet of @ThingsExpo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 19th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The Internet of Things (IoT) is the most profound change in personal and enterprise IT since the creation of the Worldwide Web more than 20 years ago. All major researchers estimate there will be tens of billions devices - comp...