Click here to close now.




















Welcome!

Microsoft Cloud Authors: Eric Aarrestad, Greg O'Connor, Liz McMillan, Aleksei Gavrilenko, Elizabeth White

News Feed Item

Avala Announces Positive Preliminary Economic Assessment and Updated Mineral Resource for Timok Gold Project, Serbia

LONGUEUIL, QUEBEC -- (Marketwired) -- 06/20/14 -- Avala Resources Ltd. (TSX VENTURE: AVZ) (the "Company" or "Avala") is pleased to announce the results of an independent preliminary economic assessment ("PEA") and an updated mineral resource estimate for its 100% owned Timok Gold Project located in Eastern Serbia.

Highlights of the Timok Gold Project PEA


--  Open pit gold mine with an initial life of mine ("LOM") of 8.4 years.

--  Average annual gold production LOM of approximately 81,000 ounces at
    US$788 cash cost per ounce.

--  Average annual gold production of approximately 92,000 ounces for the
    first three years of production.

--  LOM gold production of 680,000 ounces.

--  Average LOM operating costs (including royalties, selling costs,
    closure/environmental costs and sustaining capital) of U$843 per ounce
    of gold.

--  Annual processing rate of 1.68 million tonnes per year.

--  Average LOM gold recovery of 75% from milling and flotation to produce a
    gold-rich concentrate.

--  Estimated pre-production capital cost of US$177 million, including
    working capital.

--  LOM net cash flow of US$127.6 million at a gold price of US$1300 per
    ounce.

--  Net present value ("NPV") of US$65 million at a 5% discount rate and a
    gold price of US$1300 per ounce generating an internal rate of return
    ("IRR") of 14.3%.

--  Project payback of 4.0 years.

--  All economic outcomes presented in the PEA are the same on a pre- and
    after-tax basis as it is expected that the proposed level of investment
    and employment associated with the implementation of the proposed mine
    would qualify for a 10 year tax holiday under current Serbian tax
    legislation.

--  Over 99.5% of the resources within the PEA pit designs are categorized
    as indicated resources.

Purpose of the Study

The purpose of the PEA was to (a) provide a preliminary concept for the scale and type of mining project that the Timok Gold Project could support, (b) identify areas where additional work is required before a pre-feasibility study can be completed and (c) demonstrate potential for positive economic returns that would justify continued investment in the Timok Gold Project.

The PEA is preliminary in nature, based on mineral resources, and provides an indication of potential viability of the Timok Gold Project. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. The PEA includes inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted to the measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

Additional details will be provided in a NI 43-101 technical report to be filed on SEDAR within 45 days.

Project Throughput Trade-Off Study

Prior to initiating the PEA, Avala carried out an internal, preliminary trade-off study to determine the optimum throughput rate for the Timok Gold Project. Throughput rates of 5,000 tonnes per day (1.68 million tonnes per annum) to 10,000 tonnes per day (3.36 million tonnes per annum) were evaluated at gold prices from US$1250 per ounce to US$1500 per ounce. The results of the study indicated that 5,000 tonnes per day provides the best project economics relative to other operating and financial parameters.

Summary of Base Case Results

The base case assumptions included revenues using a gold price of US$1300 per ounce and current prices for fuel, reagents, labor, power and other consumables in Serbia. The key results are as follows:


----------------------------------------------------------------------------
               Preliminary Economic Analysis Base Case Summary
----------------------------------------------------------------------------
Item                                                                   Value
----------------------------------------------------------------------------
LOM average gold recovery (%)                                             75
----------------------------------------------------------------------------
Gold ounces produced (koz)                                               680
----------------------------------------------------------------------------
Average annual gold production (koz)                                      81
----------------------------------------------------------------------------
Ore mined (Mt)                                                          14.1
----------------------------------------------------------------------------
LOM head grade (g/t Au)                                                  2.0
----------------------------------------------------------------------------
Waste material mined (Mt) (including capitalized pre-strip)             63.6
----------------------------------------------------------------------------
Waste to ore strip ratio                                                 4.5
----------------------------------------------------------------------------
Construction capital, including working capital (US$M)                 177.0
----------------------------------------------------------------------------
Sustaining capital (US$M)                                               10.6
----------------------------------------------------------------------------
Gross gold revenue (US$M)                                              839.5
----------------------------------------------------------------------------
Net income (US$M) (1)                                                  127.6
----------------------------------------------------------------------------
Net present value at 5% discount rate (US$M) (1)                        64.9
----------------------------------------------------------------------------
IRR (%) (1)                                                             14.3
----------------------------------------------------------------------------
Mine life (years)                                                        8.4
----------------------------------------------------------------------------
Payback (years) (1)                                                      4.0
----------------------------------------------------------------------------
LOM direct cost (mining, processing and G&A) (US$/oz)                    567
----------------------------------------------------------------------------
LOM cash cost (direct cost + royalties and selling costs) (US$/oz)       788
----------------------------------------------------------------------------
LOM operating cost (cash cost + closure/environmental costs &
 sustaining capital) (US$/oz)                                            843
----------------------------------------------------------------------------
LOM total cost (operating cost + implementation capital) (US$/oz)       1104
----------------------------------------------------------------------------
Average LOM mining cost (US$/t mined)                                  14.92
----------------------------------------------------------------------------
Average LOM processing cost (US$/t processed)                          11.69
----------------------------------------------------------------------------
Average LOM cost of sales (US$/t processed)                             7.96
----------------------------------------------------------------------------
Annual G&A costs (US$M)                                                 1.24
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
qualification to a 10-year tax holiday under current tax legislation in
Serbia.

The PEA is subject to a number of assumptions, including amongst others, that an environmental impact assessment will be completed within the required timeline, that all required permits will be obtained in a timely manner, that the Timok Gold Project will have the support of the local government and community, that the regulatory environment will remain consistent and that estimated costs will not increase materially. The table below summarizes key assumptions in the PEA.



----------------------------------------------------------------------------
               Preliminary Economic Analysis Key Assumptions
----------------------------------------------------------------------------
Costs and Recoveries                    Capital Estimate
----------------------------------------------------------------------------
Fuel cost (US$/liter)          1.22     Mining (US$M)                 27.24
----------------------------------------------------------------------------
Electricity cost
(US$/kWh)                      0.07     Process plant (US$M)          66.64
----------------------------------------------------------------------------
Mill power usage                        Plant infrastructure
(kWh/t)                          35     (US$M)                        16.72
----------------------------------------------------------------------------
Mining (US$/t) - unit                   Area infrastructure
cost (ore)                2.36-2.55     (US$M)                         7.29
----------------------------------------------------------------------------
Mining (US$/t) -
overall cost                            Regional
(waste+ore)                   14.92     infrastructure (US$M)          1.86
----------------------------------------------------------------------------
Grade control (US$/t)          0.45     Miscellaneous                  7.62
----------------------------------------------------------------------------
                                        Sub-Total Direct Cost
Rehabilitation (US$/t)         0.09     (US$M)                       127.37
----------------------------------------------------------------------------
Stockpile re-handling
(US$/t)                        1.50     Indirect cost (US$M)          19.14
----------------------------------------------------------------------------
Plant feed at ROM pad                   Accuracy provision
(US$/t)                        0.25     (US$M)                        22.22
----------------------------------------------------------------------------
Ore haulage (US$/t)                     Sub-Total Initial
(Kraku Pester)                 3.50     Capital (US$M)               168.73
----------------------------------------------------------------------------
Processing (US$/t) -
full production year          11.55     Owner's costs (US$M)           8.29
----------------------------------------------------------------------------
Concentrate costs
(TC/RC, transport                       Total Initial Capital
etc.) (US$/dry t                        (US$M) - including
concentrate)            200.0-203.8     working capital              177.02
----------------------------------------------------------------------------
General services
(US$/t)                        0.74
----------------------------------------------------------------------------
CAT mining equipment
financing cost (US$/t)         1.15     State royalty                     5%
----------------------------------------------------------------------------
Total operating cost
(US$/t)                       37.99
----------------------------------------------------------------------------
Plant recoveries:                       Plant recoveries:
Bigar Hill                       80%    Kraku Pester                     56%
----------------------------------------------------------------------------
Plant recoveries:                       Overall plant
Korkan                           68%    recoveries: LOM                  75%
----------------------------------------------------------------------------

A full list of the assumptions will be set out in the NI 43-101 technical report for the PEA.

Project Sensitivities

The Timok Gold Project PEA is based on producing a gold-rich sulphide concentrate for sale to smelters. A small positive increase in gold price and/or gold recovery has a marked effect on the project economics, as illustrated in the table below (with the pit designs and schedules unchanged). The optimum pit shells, which form the basis of the PEA pit designs, are most sensitive to plant recovery and the gold price. The Company believes that the metallurgical testwork recommended in the PEA may result in higher overall plant recoveries, which would result in a higher conversion ratio. Independently, an increase in the gold price will also increase the conversion ratio, as larger pits are developed. As noted below, Avala also intends to assess the potential for underground extraction of gold mineralisation beneath the open pit designs.


----------------------------------------------------------------------------
            Preliminary Economic Analysis Sensitivity Summary (1)
----------------------------------------------------------------------------
                                    Gold Price    NPV@0%    NPV@5%       IRR
Sensitivity                           (US$/oz)    (US$M)    (US$M)       (%)
----------------------------------------------------------------------------
                           Gold Price Sensitivity
----------------------------------------------------------------------------
Gold price +US$150                        1450     219.2     132.1      22.4
----------------------------------------------------------------------------
Gold price +US$100                        1400     188.7     109.7      19.8
----------------------------------------------------------------------------
Gold price +US$50                         1350     158.1      87.3      17.2
----------------------------------------------------------------------------
Base case gold price                      1300     127.6      64.9      14.3
----------------------------------------------------------------------------
Gold price -US$50                         1250      97.0      42.6      11.4
----------------------------------------------------------------------------
Gold price -US$100                        1200      66.5      20.2       8.2
----------------------------------------------------------------------------
                            Recovery Sensitivity
----------------------------------------------------------------------------
Recovery +6%                              1300     191.0     111.0      19.9
----------------------------------------------------------------------------
Recovery +4%                              1300     169.9      96.6      18.1
----------------------------------------------------------------------------
Recovery +2%                              1300     148.7      80.3      16.3
----------------------------------------------------------------------------
Recovery -2%                              1300     106.4      49.6      12.3
----------------------------------------------------------------------------
Recovery -4%                              1300      85.2      34.3      10.2
----------------------------------------------------------------------------
                           Combined Sensitivities
----------------------------------------------------------------------------
Recovery +4% & gold price +US50           1350     202.1     119.2      20.8
----------------------------------------------------------------------------
Recovery +6% & gold price +US$100         1400     257.0     159.3      25.2
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
 qualification to a 10-year tax holiday under current tax legislation in
 Serbia.

Mineral Resources

In conjunction with the preparation of the PEA, the mineral resource estimates for the Bigar Hill and Korkan deposits (Oct 2013) and Kraku Pester deposit (Jan 2013) have been updated to constrain the deposits within pit shells for the purposes of the PEA, based on the assumptions, parameters and methodology that are summarised below. At this stage the Korkan East deposit has not been subject to preliminary economic assessment. The Bigar Hill, Korkan and Kraku Pester estimates are supported by 271,420.2 metres of drilling. The average drill spacing is 40 meters by 40 meters for indicated resources and 80 meters by 80 meters for inferred resources. The mineral resources for Bigar Hill, Korkan and Kraku Pester, which were used in the PEA, are listed in the table below.


----------------------------------------------------------------------------
                             TIMOK GOLD PROJECT
              INDICATED AND INFERRED RESOURCES USED IN THE PEA
----------------------------------------------------------------------------
                                 Indicated                 Inferred
                         ---------------------------------------------------
                 Cut Off                  Million                    Million
                  Grade   Million     Au   Ounces  Million     Au     Ounces
Deposit        (Au g/t)    Tonnes  (g/t)     (Au)   Tonnes  (g/t)       (Au)


----------------------------------------------------------------------------
Bigar Hill           0.3    38.62   1.19     1.48      1.3    1.3        0.1
----------------------------------------------------------------------------
Korkan               0.3    22.35   1.07     0.77      2.7    0.9        0.1
----------------------------------------------------------------------------
Kraku Pester         0.3     6.45   1.05     0.22      0.3    0.8        0.0
----------------------------------------------------------------------------
Total                       67.42   1.14     2.48      4.3    1.0        0.2
----------------------------------------------------------------------------
Notes: (1) The effective date of the updated mineral resource estimate is
           May 1, 2014.
       (2) The resource estimation was prepared by Chris Arnold MAusIMM
           CP(Geo) of AMC Consultants Limited using the Canadian Institute
           of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
           Mineral Resources and Reserves, Definitions and Guidelines
           prepared by the CIM Standing Committee on Reserve Definitions and
           adopted by the CIM Council.
       (3) The resources are constrained within pit shells returning the
           maximum undiscounted values, based on the following assumptions:
           NSR gold price of $1500/oz ($1700/oz spot price less $200/oz for
           off-site concentrate costs), 85% gold recovery for Bigar Hill and
           Korkan, 80% recovery for Kraku Pester, 55 degree pit slopes,
           US$2.00/t ore and waste mining costs (including rehabilitation
           costs) andUS$12.70/t processing and other costs, resulting in cut
           off grades of 0.32g/t for Bigar Hill and Korkan and 0.34g/t for
           Kraku Pester. Both cut off grades have been rounded to 0.3g/t for
           the reporting of resources within the designated pit shells.
       (4) Mineral resources, which are not mineral reserves, do not have
           demonstrated economic viability. The estimate of mineral
           resources may be materially affected by environmental,
           permitting, legal, title, taxation, sociopolitical, marketing, or
           other relevant issues.
       (5) The quantity and grade of reported inferred resources in this
           estimation are uncertain in nature and there has been
           insufficient exploration to define these inferred resources as
           indicated or measured mineral resources.
       (6) Totals and average grades are subject to rounding to the
           appropriate precision.
       (7) The key changes between the previous mineral resource estimate
           for the Bigar Hill, Korkan and Kraku Pester deposits (news
           release of October 16, 2013) and this updated mineral resource
           are that the updated resource estimate is constrained within a
           pit shell and has been reported at a lower cut-off, commensurate
           with the gold price and costs parameters used to defined the
           constrained pit.

The NI 43-101 technical report to be filed for the PEA will include the technical and scientific data to support the updated mineral resource estimate.

Next Steps

Subject to the availability of funds, Avala plans to do the following work to advance the Timok Gold Project.

Several metallurgical testwork programs have been undertaken since 2011 on samples selected from the Timok Gold Project deposits. Initial work investigated the potential for gold recovery from several processing options, including cyanidation techniques. During 2012 and 2013, the metallurgical testwork focus changed to the assessment of ultra-fine grinding and flotation to produce a gold-rich sulphide concentrate for treatment by others. In addition, the potential for upgrading via attritioning/scrubbing (pre-concentration) was evaluated, which showed promise but was not taken further in the PEA design. Testwork was successful in using primary grinding, ultra-fine grinding and flotation to produce a gold bearing pyritic concentrate. Metallurgical recoveries adopted for the design were 80%, 68% and 56% for Bigar Hill, Korkan and Kraku Pester deposits respectively; into a design concentrate mass pull of 4%. Testwork to support pre-feasibility study activities would include:


--  Detailed mineralogical evaluation to improve understanding of gold
    associations with gangue and sulphide minerals;

--  SAG milling characterization;

--  Further evaluation of scrubbing/attritioning (pre-concentration)
    potential;

--  Evaluation of finer grind sizes to improve flotation recovery;

--  Larger scale ultra-fine grinding testwork to confirm specific energy
    requirements and to prepare flotation feed;

--  Staged Flotation Reactor circuit testing;

--  Production of concentrate for marketing purposes; and

--  Liquid-solid separation testwork (concentrate and tailings).

Avala has developed an extensive geo-metallurgical database for the Timok Gold Project and plans to produce detailed three dimensional geometallurgical models of the deposits to assist with effective targeting of further metallurgical testwork.

Review of the Bigar Hill and Korkan resource models suggests there may be potential for underground extraction of gold mineralization beneath the current open pit designs. Avala plans to assess this potential, along with preliminary assessment of the recently announced Korkan East deposit.

During Q1 2014 Avala was granted the right to explore on the Bigar Istok license (15 square kilometers) which is located immediately due east of the Potoj Cuka Tisnica exploration license, which hosts the currently defined deposits. Previous exploration in this area has highlighted various gold-in-soil anomalies together with evidence of historic gold and base metal mineralization as defined by previous Serbian State exploration drilling. Avala believes that the exploration potential of the Bigar Istok license area, together with the various prospects located proximal to the currently defined deposits, remains high.

Qualified Persons

The PEA was completed by AMEC Australia Pty Ltd. under the supervision of Peter Nofal, FAusIMM, with participation of AMEC Growth Regions Mining Services Group UK and Gary Jobson, MAusIMM, of Macromet Pty Ltd. (metallurgy), Nick Journet, ARSM, FAusIMM, of Dumpsolver Pty Ltd.(mining), Chris Arnold MAusIMM CP(Geo), AMC UK, (geology and resource modeling), Fergus Anckorn, FAusIMM CP(Environmental), of AMEC Earth and Environmental (UK) Ltd (Environmental, Social and Permitting), Ciaran Molloy, MIMMM ICE QP of AMEC Growth Regions Specialty Mining Services Group (Geotechnical & Civil Engineering), and Rod Cameron, F.Geol.Soc.London Chartered Geologist, of AMEC Growth Regions Speciality Mining Services Group (Tailings and Water Management). The Bigar Hill, Korkan and Kraku Pester updated mineral resource estimate was undertaken by independent qualified person Chris Arnold MAusIMM CP(Geo) of AMC. Mr. Arnold has reviewed and approved the contents of this press release insofar as mineral resource estimates are concerned. Dr. Julian F. H. Barnes, FAusIMM, MAIG, a director of the Company and special consultant, is the Company's designated qualified person for purposes of the PEA. All qualified persons have reviewed and approved the disclosure in this press release related to their respective areas of expertise.

About Avala Resources Ltd.: Avala Resources is a mineral exploration company focused on the exploration and development of the Timok Gold Project in Eastern Serbia. The Timok Gold Project comprises several targets, including the Korkan, Bigar Hill, Kraku Pester, and Korkan East deposits. Avala controls 100% of this recently identified sediment-hosted gold belt which totals approximately 250 square kilometers. The common shares of Avala trade on the TSX Venture Exchange under the symbol AVZ.

Avala had approximately $1.1 million in its treasury at March 31, 2014. Avala's issued and outstanding share capital totals 254,492,223 common shares, of which approximately 53.1% is held by Dundee Precious Metals Inc. (TSX: DPM).

Additional information about the Company is available on Avala's website (www.avalaresources.com) and on SEDAR (www.sedar.com).

Cautionary Statement Regarding Forward-Looking Information

This press release contains 'forward-looking information' within the meaning of Canadian securities legislation. Forward looking information in this press release includes information about the results of a Preliminary Economic Assessment (PEA). This PEA is the first in a series of development studies for the project assessing the potential viability of a potential mining operation on the Timok Gold Project. The operating and capital costs estimated in the PEA were developed to be reasonable estimates within industry benchmarks. The PEA is intended to quantify the project's cost parameters which will, in turn, be used to guide ongoing exploration and engineering work and to define the optimal scale of the operation for a feasibility study. Forward looking information in this press release also includes information about planned metallurgical testwork and the ability to increase metal recoveries through additional work, completion of a pre-feasibility study, the potential to incorporate an underground operation into the open pit plans for the Timok Gold Project, and the exploration potential of the Bigar Istok license and the target areas nearby Bigar Hill, Korkan, Kraku Pester, and Korkan East. This press release also includes an updated mineral resource estimate. Mineral resources are not mineral reserves and do not have demonstrated economic viability. Inferred resources have a great amount of uncertainty as to their existence, and economic and legal feasibility. Since forward-looking information is based on assumptions and addresses future events and conditions, by its very nature it involves risks and uncertainties. Certain assumptions used in the PEA and the resource estimate are summarized in this press release. Actual results could differ materially from those anticipated in the forward looking information for many reasons including, but not limited to: changes in general economic conditions and conditions in the financial markets; changes in demand and prices for gold; changes in prices of inputs and other assumptions in the PEA and the resource estimate; unavailability of the 10-year tax holiday; legislative, environmental and other regulatory, political and competitive developments; operational difficulties encountered in connection with the activities of the Company; and the Company's financial condition and financial resources to execute its business plans. These and other factors referred to in public disclosures and filings by the Company should be considered carefully, and readers should not place undue reliance on the Company's forward-looking information. The Company does not undertake to update any forward-looking information, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
SYS-CON Events announced today that HPM Networks will exhibit at the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. For 20 years, HPM Networks has been integrating technology solutions that solve complex business challenges. HPM Networks has designed solutions for both SMB and enterprise customers throughout the San Francisco Bay Area.
For IoT to grow as quickly as analyst firms’ project, a lot is going to fall on developers to quickly bring applications to market. But the lack of a standard development platform threatens to slow growth and make application development more time consuming and costly, much like we’ve seen in the mobile space. In his session at @ThingsExpo, Mike Weiner, Product Manager of the Omega DevCloud with KORE Telematics Inc., discussed the evolving requirements for developers as IoT matures and conducted a live demonstration of how quickly application development can happen when the need to comply wit...
The Internet of Everything (IoE) brings together people, process, data and things to make networked connections more relevant and valuable than ever before – transforming information into knowledge and knowledge into wisdom. IoE creates new capabilities, richer experiences, and unprecedented opportunities to improve business and government operations, decision making and mission support capabilities.
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at @ThingsExpo, James Kirkland, Red Hat's Chief Architect for the Internet of Things and Intelligent Systems, described how to revolutionize your archit...
MuleSoft has announced the findings of its 2015 Connectivity Benchmark Report on the adoption and business impact of APIs. The findings suggest traditional businesses are quickly evolving into "composable enterprises" built out of hundreds of connected software services, applications and devices. Most are embracing the Internet of Things (IoT) and microservices technologies like Docker. A majority are integrating wearables, like smart watches, and more than half plan to generate revenue with APIs within the next year.
Growth hacking is common for startups to make unheard-of progress in building their business. Career Hacks can help Geek Girls and those who support them (yes, that's you too, Dad!) to excel in this typically male-dominated world. Get ready to learn the facts: Is there a bias against women in the tech / developer communities? Why are women 50% of the workforce, but hold only 24% of the STEM or IT positions? Some beginnings of what to do about it! In her Opening Keynote at 16th Cloud Expo, Sandy Carter, IBM General Manager Cloud Ecosystem and Developers, and a Social Business Evangelist, d...
In his keynote at 16th Cloud Expo, Rodney Rogers, CEO of Virtustream, discussed the evolution of the company from inception to its recent acquisition by EMC – including personal insights, lessons learned (and some WTF moments) along the way. Learn how Virtustream’s unique approach of combining the economics and elasticity of the consumer cloud model with proper performance, application automation and security into a platform became a breakout success with enterprise customers and a natural fit for the EMC Federation.
The Internet of Things is not only adding billions of sensors and billions of terabytes to the Internet. It is also forcing a fundamental change in the way we envision Information Technology. For the first time, more data is being created by devices at the edge of the Internet rather than from centralized systems. What does this mean for today's IT professional? In this Power Panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, panelists addressed this very serious issue of profound change in the industry.
Discussions about cloud computing are evolving into discussions about enterprise IT in general. As enterprises increasingly migrate toward their own unique clouds, new issues such as the use of containers and microservices emerge to keep things interesting. In this Power Panel at 16th Cloud Expo, moderated by Conference Chair Roger Strukhoff, panelists addressed the state of cloud computing today, and what enterprise IT professionals need to know about how the latest topics and trends affect their organization.
It is one thing to build single industrial IoT applications, but what will it take to build the Smart Cities and truly society-changing applications of the future? The technology won’t be the problem, it will be the number of parties that need to work together and be aligned in their motivation to succeed. In his session at @ThingsExpo, Jason Mondanaro, Director, Product Management at Metanga, discussed how you can plan to cooperate, partner, and form lasting all-star teams to change the world and it starts with business models and monetization strategies.
Converging digital disruptions is creating a major sea change - Cisco calls this the Internet of Everything (IoE). IoE is the network connection of People, Process, Data and Things, fueled by Cloud, Mobile, Social, Analytics and Security, and it represents a $19Trillion value-at-stake over the next 10 years. In her keynote at @ThingsExpo, Manjula Talreja, VP of Cisco Consulting Services, discussed IoE and the enormous opportunities it provides to public and private firms alike. She will share what businesses must do to thrive in the IoE economy, citing examples from several industry sectors.
There will be 150 billion connected devices by 2020. New digital businesses have already disrupted value chains across every industry. APIs are at the center of the digital business. You need to understand what assets you have that can be exposed digitally, what their digital value chain is, and how to create an effective business model around that value chain to compete in this economy. No enterprise can be complacent and not engage in the digital economy. Learn how to be the disruptor and not the disruptee.
Akana has released Envision, an enhanced API analytics platform that helps enterprises mine critical insights across their digital eco-systems, understand their customers and partners and offer value-added personalized services. “In today’s digital economy, data-driven insights are proving to be a key differentiator for businesses. Understanding the data that is being tunneled through their APIs and how it can be used to optimize their business and operations is of paramount importance,” said Alistair Farquharson, CTO of Akana.
Business as usual for IT is evolving into a "Make or Buy" decision on a service-by-service conversation with input from the LOBs. How does your organization move forward with cloud? In his general session at 16th Cloud Expo, Paul Maravei, Regional Sales Manager, Hybrid Cloud and Managed Services at Cisco, discusses how Cisco and its partners offer a market-leading portfolio and ecosystem of cloud infrastructure and application services that allow you to uniquely and securely combine cloud business applications and services across multiple cloud delivery models.
The enterprise market will drive IoT device adoption over the next five years. In his session at @ThingsExpo, John Greenough, an analyst at BI Intelligence, division of Business Insider, analyzed how companies will adopt IoT products and the associated cost of adopting those products. John Greenough is the lead analyst covering the Internet of Things for BI Intelligence- Business Insider’s paid research service. Numerous IoT companies have cited his analysis of the IoT. Prior to joining BI Intelligence, he worked analyzing bank technology for Corporate Insight and The Clearing House Payment...
"Optimal Design is a technology integration and product development firm that specializes in connecting devices to the cloud," stated Joe Wascow, Co-Founder & CMO of Optimal Design, in this SYS-CON.tv interview at @ThingsExpo, held June 9-11, 2015, at the Javits Center in New York City.
SYS-CON Events announced today that CommVault has been named “Bronze Sponsor” of SYS-CON's 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. A singular vision – a belief in a better way to address current and future data management needs – guides CommVault in the development of Singular Information Management® solutions for high-performance data protection, universal availability and simplified management of data on complex storage networks. CommVault's exclusive single-platform architecture gives companies unp...
Electric Cloud and Arynga have announced a product integration partnership that will bring Continuous Delivery solutions to the automotive Internet-of-Things (IoT) market. The joint solution will help automotive manufacturers, OEMs and system integrators adopt DevOps automation and Continuous Delivery practices that reduce software build and release cycle times within the complex and specific parameters of embedded and IoT software systems.
"ciqada is a combined platform of hardware modules and server products that lets people take their existing devices or new devices and lets them be accessible over the Internet for their users," noted Geoff Engelstein of ciqada, a division of Mars International, in this SYS-CON.tv interview at @ThingsExpo, held June 9-11, 2015, at the Javits Center in New York City.
Internet of Things is moving from being a hype to a reality. Experts estimate that internet connected cars will grow to 152 million, while over 100 million internet connected wireless light bulbs and lamps will be operational by 2020. These and many other intriguing statistics highlight the importance of Internet powered devices and how market penetration is going to multiply many times over in the next few years.