Welcome!

Microsoft Cloud Authors: Janakiram MSV, Pat Romanski, Steven Mandel, John Basso, Liz McMillan

News Feed Item

Avala Announces Positive Preliminary Economic Assessment and Updated Mineral Resource for Timok Gold Project, Serbia

LONGUEUIL, QUEBEC -- (Marketwired) -- 06/20/14 -- Avala Resources Ltd. (TSX VENTURE: AVZ) (the "Company" or "Avala") is pleased to announce the results of an independent preliminary economic assessment ("PEA") and an updated mineral resource estimate for its 100% owned Timok Gold Project located in Eastern Serbia.

Highlights of the Timok Gold Project PEA


--  Open pit gold mine with an initial life of mine ("LOM") of 8.4 years.

--  Average annual gold production LOM of approximately 81,000 ounces at
    US$788 cash cost per ounce.

--  Average annual gold production of approximately 92,000 ounces for the
    first three years of production.

--  LOM gold production of 680,000 ounces.

--  Average LOM operating costs (including royalties, selling costs,
    closure/environmental costs and sustaining capital) of U$843 per ounce
    of gold.

--  Annual processing rate of 1.68 million tonnes per year.

--  Average LOM gold recovery of 75% from milling and flotation to produce a
    gold-rich concentrate.

--  Estimated pre-production capital cost of US$177 million, including
    working capital.

--  LOM net cash flow of US$127.6 million at a gold price of US$1300 per
    ounce.

--  Net present value ("NPV") of US$65 million at a 5% discount rate and a
    gold price of US$1300 per ounce generating an internal rate of return
    ("IRR") of 14.3%.

--  Project payback of 4.0 years.

--  All economic outcomes presented in the PEA are the same on a pre- and
    after-tax basis as it is expected that the proposed level of investment
    and employment associated with the implementation of the proposed mine
    would qualify for a 10 year tax holiday under current Serbian tax
    legislation.

--  Over 99.5% of the resources within the PEA pit designs are categorized
    as indicated resources.

Purpose of the Study

The purpose of the PEA was to (a) provide a preliminary concept for the scale and type of mining project that the Timok Gold Project could support, (b) identify areas where additional work is required before a pre-feasibility study can be completed and (c) demonstrate potential for positive economic returns that would justify continued investment in the Timok Gold Project.

The PEA is preliminary in nature, based on mineral resources, and provides an indication of potential viability of the Timok Gold Project. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. The PEA includes inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted to the measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

Additional details will be provided in a NI 43-101 technical report to be filed on SEDAR within 45 days.

Project Throughput Trade-Off Study

Prior to initiating the PEA, Avala carried out an internal, preliminary trade-off study to determine the optimum throughput rate for the Timok Gold Project. Throughput rates of 5,000 tonnes per day (1.68 million tonnes per annum) to 10,000 tonnes per day (3.36 million tonnes per annum) were evaluated at gold prices from US$1250 per ounce to US$1500 per ounce. The results of the study indicated that 5,000 tonnes per day provides the best project economics relative to other operating and financial parameters.

Summary of Base Case Results

The base case assumptions included revenues using a gold price of US$1300 per ounce and current prices for fuel, reagents, labor, power and other consumables in Serbia. The key results are as follows:


----------------------------------------------------------------------------
               Preliminary Economic Analysis Base Case Summary
----------------------------------------------------------------------------
Item                                                                   Value
----------------------------------------------------------------------------
LOM average gold recovery (%)                                             75
----------------------------------------------------------------------------
Gold ounces produced (koz)                                               680
----------------------------------------------------------------------------
Average annual gold production (koz)                                      81
----------------------------------------------------------------------------
Ore mined (Mt)                                                          14.1
----------------------------------------------------------------------------
LOM head grade (g/t Au)                                                  2.0
----------------------------------------------------------------------------
Waste material mined (Mt) (including capitalized pre-strip)             63.6
----------------------------------------------------------------------------
Waste to ore strip ratio                                                 4.5
----------------------------------------------------------------------------
Construction capital, including working capital (US$M)                 177.0
----------------------------------------------------------------------------
Sustaining capital (US$M)                                               10.6
----------------------------------------------------------------------------
Gross gold revenue (US$M)                                              839.5
----------------------------------------------------------------------------
Net income (US$M) (1)                                                  127.6
----------------------------------------------------------------------------
Net present value at 5% discount rate (US$M) (1)                        64.9
----------------------------------------------------------------------------
IRR (%) (1)                                                             14.3
----------------------------------------------------------------------------
Mine life (years)                                                        8.4
----------------------------------------------------------------------------
Payback (years) (1)                                                      4.0
----------------------------------------------------------------------------
LOM direct cost (mining, processing and G&A) (US$/oz)                    567
----------------------------------------------------------------------------
LOM cash cost (direct cost + royalties and selling costs) (US$/oz)       788
----------------------------------------------------------------------------
LOM operating cost (cash cost + closure/environmental costs &
 sustaining capital) (US$/oz)                                            843
----------------------------------------------------------------------------
LOM total cost (operating cost + implementation capital) (US$/oz)       1104
----------------------------------------------------------------------------
Average LOM mining cost (US$/t mined)                                  14.92
----------------------------------------------------------------------------
Average LOM processing cost (US$/t processed)                          11.69
----------------------------------------------------------------------------
Average LOM cost of sales (US$/t processed)                             7.96
----------------------------------------------------------------------------
Annual G&A costs (US$M)                                                 1.24
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
qualification to a 10-year tax holiday under current tax legislation in
Serbia.

The PEA is subject to a number of assumptions, including amongst others, that an environmental impact assessment will be completed within the required timeline, that all required permits will be obtained in a timely manner, that the Timok Gold Project will have the support of the local government and community, that the regulatory environment will remain consistent and that estimated costs will not increase materially. The table below summarizes key assumptions in the PEA.



----------------------------------------------------------------------------
               Preliminary Economic Analysis Key Assumptions
----------------------------------------------------------------------------
Costs and Recoveries                    Capital Estimate
----------------------------------------------------------------------------
Fuel cost (US$/liter)          1.22     Mining (US$M)                 27.24
----------------------------------------------------------------------------
Electricity cost
(US$/kWh)                      0.07     Process plant (US$M)          66.64
----------------------------------------------------------------------------
Mill power usage                        Plant infrastructure
(kWh/t)                          35     (US$M)                        16.72
----------------------------------------------------------------------------
Mining (US$/t) - unit                   Area infrastructure
cost (ore)                2.36-2.55     (US$M)                         7.29
----------------------------------------------------------------------------
Mining (US$/t) -
overall cost                            Regional
(waste+ore)                   14.92     infrastructure (US$M)          1.86
----------------------------------------------------------------------------
Grade control (US$/t)          0.45     Miscellaneous                  7.62
----------------------------------------------------------------------------
                                        Sub-Total Direct Cost
Rehabilitation (US$/t)         0.09     (US$M)                       127.37
----------------------------------------------------------------------------
Stockpile re-handling
(US$/t)                        1.50     Indirect cost (US$M)          19.14
----------------------------------------------------------------------------
Plant feed at ROM pad                   Accuracy provision
(US$/t)                        0.25     (US$M)                        22.22
----------------------------------------------------------------------------
Ore haulage (US$/t)                     Sub-Total Initial
(Kraku Pester)                 3.50     Capital (US$M)               168.73
----------------------------------------------------------------------------
Processing (US$/t) -
full production year          11.55     Owner's costs (US$M)           8.29
----------------------------------------------------------------------------
Concentrate costs
(TC/RC, transport                       Total Initial Capital
etc.) (US$/dry t                        (US$M) - including
concentrate)            200.0-203.8     working capital              177.02
----------------------------------------------------------------------------
General services
(US$/t)                        0.74
----------------------------------------------------------------------------
CAT mining equipment
financing cost (US$/t)         1.15     State royalty                     5%
----------------------------------------------------------------------------
Total operating cost
(US$/t)                       37.99
----------------------------------------------------------------------------
Plant recoveries:                       Plant recoveries:
Bigar Hill                       80%    Kraku Pester                     56%
----------------------------------------------------------------------------
Plant recoveries:                       Overall plant
Korkan                           68%    recoveries: LOM                  75%
----------------------------------------------------------------------------

A full list of the assumptions will be set out in the NI 43-101 technical report for the PEA.

Project Sensitivities

The Timok Gold Project PEA is based on producing a gold-rich sulphide concentrate for sale to smelters. A small positive increase in gold price and/or gold recovery has a marked effect on the project economics, as illustrated in the table below (with the pit designs and schedules unchanged). The optimum pit shells, which form the basis of the PEA pit designs, are most sensitive to plant recovery and the gold price. The Company believes that the metallurgical testwork recommended in the PEA may result in higher overall plant recoveries, which would result in a higher conversion ratio. Independently, an increase in the gold price will also increase the conversion ratio, as larger pits are developed. As noted below, Avala also intends to assess the potential for underground extraction of gold mineralisation beneath the open pit designs.


----------------------------------------------------------------------------
            Preliminary Economic Analysis Sensitivity Summary (1)
----------------------------------------------------------------------------
                                    Gold Price    [email protected]%    [email protected]%       IRR
Sensitivity                           (US$/oz)    (US$M)    (US$M)       (%)
----------------------------------------------------------------------------
                           Gold Price Sensitivity
----------------------------------------------------------------------------
Gold price +US$150                        1450     219.2     132.1      22.4
----------------------------------------------------------------------------
Gold price +US$100                        1400     188.7     109.7      19.8
----------------------------------------------------------------------------
Gold price +US$50                         1350     158.1      87.3      17.2
----------------------------------------------------------------------------
Base case gold price                      1300     127.6      64.9      14.3
----------------------------------------------------------------------------
Gold price -US$50                         1250      97.0      42.6      11.4
----------------------------------------------------------------------------
Gold price -US$100                        1200      66.5      20.2       8.2
----------------------------------------------------------------------------
                            Recovery Sensitivity
----------------------------------------------------------------------------
Recovery +6%                              1300     191.0     111.0      19.9
----------------------------------------------------------------------------
Recovery +4%                              1300     169.9      96.6      18.1
----------------------------------------------------------------------------
Recovery +2%                              1300     148.7      80.3      16.3
----------------------------------------------------------------------------
Recovery -2%                              1300     106.4      49.6      12.3
----------------------------------------------------------------------------
Recovery -4%                              1300      85.2      34.3      10.2
----------------------------------------------------------------------------
                           Combined Sensitivities
----------------------------------------------------------------------------
Recovery +4% & gold price +US50           1350     202.1     119.2      20.8
----------------------------------------------------------------------------
Recovery +6% & gold price +US$100         1400     257.0     159.3      25.2
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
 qualification to a 10-year tax holiday under current tax legislation in
 Serbia.

Mineral Resources

In conjunction with the preparation of the PEA, the mineral resource estimates for the Bigar Hill and Korkan deposits (Oct 2013) and Kraku Pester deposit (Jan 2013) have been updated to constrain the deposits within pit shells for the purposes of the PEA, based on the assumptions, parameters and methodology that are summarised below. At this stage the Korkan East deposit has not been subject to preliminary economic assessment. The Bigar Hill, Korkan and Kraku Pester estimates are supported by 271,420.2 metres of drilling. The average drill spacing is 40 meters by 40 meters for indicated resources and 80 meters by 80 meters for inferred resources. The mineral resources for Bigar Hill, Korkan and Kraku Pester, which were used in the PEA, are listed in the table below.


----------------------------------------------------------------------------
                             TIMOK GOLD PROJECT
              INDICATED AND INFERRED RESOURCES USED IN THE PEA
----------------------------------------------------------------------------
                                 Indicated                 Inferred
                         ---------------------------------------------------
                 Cut Off                  Million                    Million
                  Grade   Million     Au   Ounces  Million     Au     Ounces
Deposit        (Au g/t)    Tonnes  (g/t)     (Au)   Tonnes  (g/t)       (Au)


----------------------------------------------------------------------------
Bigar Hill           0.3    38.62   1.19     1.48      1.3    1.3        0.1
----------------------------------------------------------------------------
Korkan               0.3    22.35   1.07     0.77      2.7    0.9        0.1
----------------------------------------------------------------------------
Kraku Pester         0.3     6.45   1.05     0.22      0.3    0.8        0.0
----------------------------------------------------------------------------
Total                       67.42   1.14     2.48      4.3    1.0        0.2
----------------------------------------------------------------------------
Notes: (1) The effective date of the updated mineral resource estimate is
           May 1, 2014.
       (2) The resource estimation was prepared by Chris Arnold MAusIMM
           CP(Geo) of AMC Consultants Limited using the Canadian Institute
           of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
           Mineral Resources and Reserves, Definitions and Guidelines
           prepared by the CIM Standing Committee on Reserve Definitions and
           adopted by the CIM Council.
       (3) The resources are constrained within pit shells returning the
           maximum undiscounted values, based on the following assumptions:
           NSR gold price of $1500/oz ($1700/oz spot price less $200/oz for
           off-site concentrate costs), 85% gold recovery for Bigar Hill and
           Korkan, 80% recovery for Kraku Pester, 55 degree pit slopes,
           US$2.00/t ore and waste mining costs (including rehabilitation
           costs) andUS$12.70/t processing and other costs, resulting in cut
           off grades of 0.32g/t for Bigar Hill and Korkan and 0.34g/t for
           Kraku Pester. Both cut off grades have been rounded to 0.3g/t for
           the reporting of resources within the designated pit shells.
       (4) Mineral resources, which are not mineral reserves, do not have
           demonstrated economic viability. The estimate of mineral
           resources may be materially affected by environmental,
           permitting, legal, title, taxation, sociopolitical, marketing, or
           other relevant issues.
       (5) The quantity and grade of reported inferred resources in this
           estimation are uncertain in nature and there has been
           insufficient exploration to define these inferred resources as
           indicated or measured mineral resources.
       (6) Totals and average grades are subject to rounding to the
           appropriate precision.
       (7) The key changes between the previous mineral resource estimate
           for the Bigar Hill, Korkan and Kraku Pester deposits (news
           release of October 16, 2013) and this updated mineral resource
           are that the updated resource estimate is constrained within a
           pit shell and has been reported at a lower cut-off, commensurate
           with the gold price and costs parameters used to defined the
           constrained pit.

The NI 43-101 technical report to be filed for the PEA will include the technical and scientific data to support the updated mineral resource estimate.

Next Steps

Subject to the availability of funds, Avala plans to do the following work to advance the Timok Gold Project.

Several metallurgical testwork programs have been undertaken since 2011 on samples selected from the Timok Gold Project deposits. Initial work investigated the potential for gold recovery from several processing options, including cyanidation techniques. During 2012 and 2013, the metallurgical testwork focus changed to the assessment of ultra-fine grinding and flotation to produce a gold-rich sulphide concentrate for treatment by others. In addition, the potential for upgrading via attritioning/scrubbing (pre-concentration) was evaluated, which showed promise but was not taken further in the PEA design. Testwork was successful in using primary grinding, ultra-fine grinding and flotation to produce a gold bearing pyritic concentrate. Metallurgical recoveries adopted for the design were 80%, 68% and 56% for Bigar Hill, Korkan and Kraku Pester deposits respectively; into a design concentrate mass pull of 4%. Testwork to support pre-feasibility study activities would include:


--  Detailed mineralogical evaluation to improve understanding of gold
    associations with gangue and sulphide minerals;

--  SAG milling characterization;

--  Further evaluation of scrubbing/attritioning (pre-concentration)
    potential;

--  Evaluation of finer grind sizes to improve flotation recovery;

--  Larger scale ultra-fine grinding testwork to confirm specific energy
    requirements and to prepare flotation feed;

--  Staged Flotation Reactor circuit testing;

--  Production of concentrate for marketing purposes; and

--  Liquid-solid separation testwork (concentrate and tailings).

Avala has developed an extensive geo-metallurgical database for the Timok Gold Project and plans to produce detailed three dimensional geometallurgical models of the deposits to assist with effective targeting of further metallurgical testwork.

Review of the Bigar Hill and Korkan resource models suggests there may be potential for underground extraction of gold mineralization beneath the current open pit designs. Avala plans to assess this potential, along with preliminary assessment of the recently announced Korkan East deposit.

During Q1 2014 Avala was granted the right to explore on the Bigar Istok license (15 square kilometers) which is located immediately due east of the Potoj Cuka Tisnica exploration license, which hosts the currently defined deposits. Previous exploration in this area has highlighted various gold-in-soil anomalies together with evidence of historic gold and base metal mineralization as defined by previous Serbian State exploration drilling. Avala believes that the exploration potential of the Bigar Istok license area, together with the various prospects located proximal to the currently defined deposits, remains high.

Qualified Persons

The PEA was completed by AMEC Australia Pty Ltd. under the supervision of Peter Nofal, FAusIMM, with participation of AMEC Growth Regions Mining Services Group UK and Gary Jobson, MAusIMM, of Macromet Pty Ltd. (metallurgy), Nick Journet, ARSM, FAusIMM, of Dumpsolver Pty Ltd.(mining), Chris Arnold MAusIMM CP(Geo), AMC UK, (geology and resource modeling), Fergus Anckorn, FAusIMM CP(Environmental), of AMEC Earth and Environmental (UK) Ltd (Environmental, Social and Permitting), Ciaran Molloy, MIMMM ICE QP of AMEC Growth Regions Specialty Mining Services Group (Geotechnical & Civil Engineering), and Rod Cameron, F.Geol.Soc.London Chartered Geologist, of AMEC Growth Regions Speciality Mining Services Group (Tailings and Water Management). The Bigar Hill, Korkan and Kraku Pester updated mineral resource estimate was undertaken by independent qualified person Chris Arnold MAusIMM CP(Geo) of AMC. Mr. Arnold has reviewed and approved the contents of this press release insofar as mineral resource estimates are concerned. Dr. Julian F. H. Barnes, FAusIMM, MAIG, a director of the Company and special consultant, is the Company's designated qualified person for purposes of the PEA. All qualified persons have reviewed and approved the disclosure in this press release related to their respective areas of expertise.

About Avala Resources Ltd.: Avala Resources is a mineral exploration company focused on the exploration and development of the Timok Gold Project in Eastern Serbia. The Timok Gold Project comprises several targets, including the Korkan, Bigar Hill, Kraku Pester, and Korkan East deposits. Avala controls 100% of this recently identified sediment-hosted gold belt which totals approximately 250 square kilometers. The common shares of Avala trade on the TSX Venture Exchange under the symbol AVZ.

Avala had approximately $1.1 million in its treasury at March 31, 2014. Avala's issued and outstanding share capital totals 254,492,223 common shares, of which approximately 53.1% is held by Dundee Precious Metals Inc. (TSX: DPM).

Additional information about the Company is available on Avala's website (www.avalaresources.com) and on SEDAR (www.sedar.com).

Cautionary Statement Regarding Forward-Looking Information

This press release contains 'forward-looking information' within the meaning of Canadian securities legislation. Forward looking information in this press release includes information about the results of a Preliminary Economic Assessment (PEA). This PEA is the first in a series of development studies for the project assessing the potential viability of a potential mining operation on the Timok Gold Project. The operating and capital costs estimated in the PEA were developed to be reasonable estimates within industry benchmarks. The PEA is intended to quantify the project's cost parameters which will, in turn, be used to guide ongoing exploration and engineering work and to define the optimal scale of the operation for a feasibility study. Forward looking information in this press release also includes information about planned metallurgical testwork and the ability to increase metal recoveries through additional work, completion of a pre-feasibility study, the potential to incorporate an underground operation into the open pit plans for the Timok Gold Project, and the exploration potential of the Bigar Istok license and the target areas nearby Bigar Hill, Korkan, Kraku Pester, and Korkan East. This press release also includes an updated mineral resource estimate. Mineral resources are not mineral reserves and do not have demonstrated economic viability. Inferred resources have a great amount of uncertainty as to their existence, and economic and legal feasibility. Since forward-looking information is based on assumptions and addresses future events and conditions, by its very nature it involves risks and uncertainties. Certain assumptions used in the PEA and the resource estimate are summarized in this press release. Actual results could differ materially from those anticipated in the forward looking information for many reasons including, but not limited to: changes in general economic conditions and conditions in the financial markets; changes in demand and prices for gold; changes in prices of inputs and other assumptions in the PEA and the resource estimate; unavailability of the 10-year tax holiday; legislative, environmental and other regulatory, political and competitive developments; operational difficulties encountered in connection with the activities of the Company; and the Company's financial condition and financial resources to execute its business plans. These and other factors referred to in public disclosures and filings by the Company should be considered carefully, and readers should not place undue reliance on the Company's forward-looking information. The Company does not undertake to update any forward-looking information, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
The 19th International Cloud Expo has announced that its Call for Papers is open. Cloud Expo, to be held November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, brings together Cloud Computing, Big Data, Internet of Things, DevOps, Digital Transformation, Microservices and WebRTC to one location. With cloud computing driving a higher percentage of enterprise IT budgets every year, it becomes increasingly important to plant your flag in this fast-expanding business opportuni...
Smart Cities are here to stay, but for their promise to be delivered, the data they produce must not be put in new siloes. In his session at @ThingsExpo, Mathias Herberts, Co-founder and CTO of Cityzen Data, will deep dive into best practices that will ensure a successful smart city journey.
SYS-CON Events announced today that 910Telecom will exhibit at the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Housed in the classic Denver Gas & Electric Building, 910 15th St., 910Telecom is a carrier-neutral telecom hotel located in the heart of Denver. Adjacent to CenturyLink, AT&T, and Denver Main, 910Telecom offers connectivity to all major carriers, Internet service providers, Internet backbones and ...
Pulzze Systems was happy to participate in such a premier event and thankful to be receiving the winning investment and global network support from G-Startup Worldwide. It is an exciting time for Pulzze to showcase the effectiveness of innovative technologies and enable them to make the world smarter and better. The reputable contest is held to identify promising startups around the globe that are assured to change the world through their innovative products and disruptive technologies. There w...
Internet of @ThingsExpo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 19th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The Internet of Things (IoT) is the most profound change in personal and enterprise IT since the creation of the Worldwide Web more than 20 years ago. All major researchers estimate there will be tens of billions devices - comp...
DevOps at Cloud Expo, taking place Nov 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, is co-located with 19th Cloud Expo and will feature technical sessions from a rock star conference faculty and the leading industry players in the world. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long dev...
Data is the fuel that drives the machine learning algorithmic engines and ultimately provides the business value. In his session at Cloud Expo, Ed Featherston, a director and senior enterprise architect at Collaborative Consulting, will discuss the key considerations around quality, volume, timeliness, and pedigree that must be dealt with in order to properly fuel that engine.
19th Cloud Expo, taking place November 1-3, 2016, at the Santa Clara Convention Center in Santa Clara, CA, will feature technical sessions from a rock star conference faculty and the leading industry players in the world. Cloud computing is now being embraced by a majority of enterprises of all sizes. Yesterday's debate about public vs. private has transformed into the reality of hybrid cloud: a recent survey shows that 74% of enterprises have a hybrid cloud strategy. Meanwhile, 94% of enterpri...
There is growing need for data-driven applications and the need for digital platforms to build these apps. In his session at 19th Cloud Expo, Muddu Sudhakar, VP and GM of Security & IoT at Splunk, will cover different PaaS solutions and Big Data platforms that are available to build applications. In addition, AI and machine learning are creating new requirements that developers need in the building of next-gen apps. The next-generation digital platforms have some of the past platform needs a...
SYS-CON Events announced today Telecom Reseller has been named “Media Sponsor” of SYS-CON's 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Telecom Reseller reports on Unified Communications, UCaaS, BPaaS for enterprise and SMBs. They report extensively on both customer premises based solutions such as IP-PBX as well as cloud based and hosted platforms.
With so much going on in this space you could be forgiven for thinking you were always working with yesterday’s technologies. So much change, so quickly. What do you do if you have to build a solution from the ground up that is expected to live in the field for at least 5-10 years? This is the challenge we faced when we looked to refresh our existing 10-year-old custom hardware stack to measure the fullness of trash cans and compactors.
The emerging Internet of Everything creates tremendous new opportunities for customer engagement and business model innovation. However, enterprises must overcome a number of critical challenges to bring these new solutions to market. In his session at @ThingsExpo, Michael Martin, CTO/CIO at nfrastructure, outlined these key challenges and recommended approaches for overcoming them to achieve speed and agility in the design, development and implementation of Internet of Everything solutions wi...
Cloud computing is being adopted in one form or another by 94% of enterprises today. Tens of billions of new devices are being connected to The Internet of Things. And Big Data is driving this bus. An exponential increase is expected in the amount of information being processed, managed, analyzed, and acted upon by enterprise IT. This amazing is not part of some distant future - it is happening today. One report shows a 650% increase in enterprise data by 2020. Other estimates are even higher....
Today we can collect lots and lots of performance data. We build beautiful dashboards and even have fancy query languages to access and transform the data. Still performance data is a secret language only a couple of people understand. The more business becomes digital the more stakeholders are interested in this data including how it relates to business. Some of these people have never used a monitoring tool before. They have a question on their mind like “How is my application doing” but no id...
Identity is in everything and customers are looking to their providers to ensure the security of their identities, transactions and data. With the increased reliance on cloud-based services, service providers must build security and trust into their offerings, adding value to customers and improving the user experience. Making identity, security and privacy easy for customers provides a unique advantage over the competition.
I wanted to gather all of my Internet of Things (IOT) blogs into a single blog (that I could later use with my University of San Francisco (USF) Big Data “MBA” course). However as I started to pull these blogs together, I realized that my IOT discussion lacked a vision; it lacked an end point towards which an organization could drive their IOT envisioning, proof of value, app dev, data engineering and data science efforts. And I think that the IOT end point is really quite simple…
Personalization has long been the holy grail of marketing. Simply stated, communicate the most relevant offer to the right person and you will increase sales. To achieve this, you must understand the individual. Consequently, digital marketers developed many ways to gather and leverage customer information to deliver targeted experiences. In his session at @ThingsExpo, Lou Casal, Founder and Principal Consultant at Practicala, discussed how the Internet of Things (IoT) has accelerated our abil...
Is the ongoing quest for agility in the data center forcing you to evaluate how to be a part of infrastructure automation efforts? As organizations evolve toward bimodal IT operations, they are embracing new service delivery models and leveraging virtualization to increase infrastructure agility. Therefore, the network must evolve in parallel to become equally agile. Read this essential piece of Gartner research for recommendations on achieving greater agility.
SYS-CON Events announced today that Venafi, the Immune System for the Internet™ and the leading provider of Next Generation Trust Protection, will exhibit at @DevOpsSummit at 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Venafi is the Immune System for the Internet™ that protects the foundation of all cybersecurity – cryptographic keys and digital certificates – so they can’t be misused by bad guys in attacks...
For basic one-to-one voice or video calling solutions, WebRTC has proven to be a very powerful technology. Although WebRTC’s core functionality is to provide secure, real-time p2p media streaming, leveraging native platform features and server-side components brings up new communication capabilities for web and native mobile applications, allowing for advanced multi-user use cases such as video broadcasting, conferencing, and media recording.