Welcome!

.NET Authors: Srinivasan Sundara Rajan, Pat Romanski, ChandraShekar Dattatreya, Jayaram Krishnaswamy, Jim Kaskade

News Feed Item

Avala Announces Positive Preliminary Economic Assessment and Updated Mineral Resource for Timok Gold Project, Serbia

LONGUEUIL, QUEBEC -- (Marketwired) -- 06/20/14 -- Avala Resources Ltd. (TSX VENTURE: AVZ) (the "Company" or "Avala") is pleased to announce the results of an independent preliminary economic assessment ("PEA") and an updated mineral resource estimate for its 100% owned Timok Gold Project located in Eastern Serbia.

Highlights of the Timok Gold Project PEA


--  Open pit gold mine with an initial life of mine ("LOM") of 8.4 years.

--  Average annual gold production LOM of approximately 81,000 ounces at
    US$788 cash cost per ounce.

--  Average annual gold production of approximately 92,000 ounces for the
    first three years of production.

--  LOM gold production of 680,000 ounces.

--  Average LOM operating costs (including royalties, selling costs,
    closure/environmental costs and sustaining capital) of U$843 per ounce
    of gold.

--  Annual processing rate of 1.68 million tonnes per year.

--  Average LOM gold recovery of 75% from milling and flotation to produce a
    gold-rich concentrate.

--  Estimated pre-production capital cost of US$177 million, including
    working capital.

--  LOM net cash flow of US$127.6 million at a gold price of US$1300 per
    ounce.

--  Net present value ("NPV") of US$65 million at a 5% discount rate and a
    gold price of US$1300 per ounce generating an internal rate of return
    ("IRR") of 14.3%.

--  Project payback of 4.0 years.

--  All economic outcomes presented in the PEA are the same on a pre- and
    after-tax basis as it is expected that the proposed level of investment
    and employment associated with the implementation of the proposed mine
    would qualify for a 10 year tax holiday under current Serbian tax
    legislation.

--  Over 99.5% of the resources within the PEA pit designs are categorized
    as indicated resources.

Purpose of the Study

The purpose of the PEA was to (a) provide a preliminary concept for the scale and type of mining project that the Timok Gold Project could support, (b) identify areas where additional work is required before a pre-feasibility study can be completed and (c) demonstrate potential for positive economic returns that would justify continued investment in the Timok Gold Project.

The PEA is preliminary in nature, based on mineral resources, and provides an indication of potential viability of the Timok Gold Project. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral resource estimates do not account for mineability, selectivity, mining loss and dilution. The PEA includes inferred mineral resources that are considered too speculative geologically to have economic considerations applied to them that would enable them to be categorized as mineral reserves. There is also no certainty that these inferred mineral resources will be converted to the measured and indicated categories through further drilling, or into mineral reserves, once economic considerations are applied.

Additional details will be provided in a NI 43-101 technical report to be filed on SEDAR within 45 days.

Project Throughput Trade-Off Study

Prior to initiating the PEA, Avala carried out an internal, preliminary trade-off study to determine the optimum throughput rate for the Timok Gold Project. Throughput rates of 5,000 tonnes per day (1.68 million tonnes per annum) to 10,000 tonnes per day (3.36 million tonnes per annum) were evaluated at gold prices from US$1250 per ounce to US$1500 per ounce. The results of the study indicated that 5,000 tonnes per day provides the best project economics relative to other operating and financial parameters.

Summary of Base Case Results

The base case assumptions included revenues using a gold price of US$1300 per ounce and current prices for fuel, reagents, labor, power and other consumables in Serbia. The key results are as follows:


----------------------------------------------------------------------------
               Preliminary Economic Analysis Base Case Summary
----------------------------------------------------------------------------
Item                                                                   Value
----------------------------------------------------------------------------
LOM average gold recovery (%)                                             75
----------------------------------------------------------------------------
Gold ounces produced (koz)                                               680
----------------------------------------------------------------------------
Average annual gold production (koz)                                      81
----------------------------------------------------------------------------
Ore mined (Mt)                                                          14.1
----------------------------------------------------------------------------
LOM head grade (g/t Au)                                                  2.0
----------------------------------------------------------------------------
Waste material mined (Mt) (including capitalized pre-strip)             63.6
----------------------------------------------------------------------------
Waste to ore strip ratio                                                 4.5
----------------------------------------------------------------------------
Construction capital, including working capital (US$M)                 177.0
----------------------------------------------------------------------------
Sustaining capital (US$M)                                               10.6
----------------------------------------------------------------------------
Gross gold revenue (US$M)                                              839.5
----------------------------------------------------------------------------
Net income (US$M) (1)                                                  127.6
----------------------------------------------------------------------------
Net present value at 5% discount rate (US$M) (1)                        64.9
----------------------------------------------------------------------------
IRR (%) (1)                                                             14.3
----------------------------------------------------------------------------
Mine life (years)                                                        8.4
----------------------------------------------------------------------------
Payback (years) (1)                                                      4.0
----------------------------------------------------------------------------
LOM direct cost (mining, processing and G&A) (US$/oz)                    567
----------------------------------------------------------------------------
LOM cash cost (direct cost + royalties and selling costs) (US$/oz)       788
----------------------------------------------------------------------------
LOM operating cost (cash cost + closure/environmental costs &
 sustaining capital) (US$/oz)                                            843
----------------------------------------------------------------------------
LOM total cost (operating cost + implementation capital) (US$/oz)       1104
----------------------------------------------------------------------------
Average LOM mining cost (US$/t mined)                                  14.92
----------------------------------------------------------------------------
Average LOM processing cost (US$/t processed)                          11.69
----------------------------------------------------------------------------
Average LOM cost of sales (US$/t processed)                             7.96
----------------------------------------------------------------------------
Annual G&A costs (US$M)                                                 1.24
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
qualification to a 10-year tax holiday under current tax legislation in
Serbia.

The PEA is subject to a number of assumptions, including amongst others, that an environmental impact assessment will be completed within the required timeline, that all required permits will be obtained in a timely manner, that the Timok Gold Project will have the support of the local government and community, that the regulatory environment will remain consistent and that estimated costs will not increase materially. The table below summarizes key assumptions in the PEA.



----------------------------------------------------------------------------
               Preliminary Economic Analysis Key Assumptions
----------------------------------------------------------------------------
Costs and Recoveries                    Capital Estimate
----------------------------------------------------------------------------
Fuel cost (US$/liter)          1.22     Mining (US$M)                 27.24
----------------------------------------------------------------------------
Electricity cost
(US$/kWh)                      0.07     Process plant (US$M)          66.64
----------------------------------------------------------------------------
Mill power usage                        Plant infrastructure
(kWh/t)                          35     (US$M)                        16.72
----------------------------------------------------------------------------
Mining (US$/t) - unit                   Area infrastructure
cost (ore)                2.36-2.55     (US$M)                         7.29
----------------------------------------------------------------------------
Mining (US$/t) -
overall cost                            Regional
(waste+ore)                   14.92     infrastructure (US$M)          1.86
----------------------------------------------------------------------------
Grade control (US$/t)          0.45     Miscellaneous                  7.62
----------------------------------------------------------------------------
                                        Sub-Total Direct Cost
Rehabilitation (US$/t)         0.09     (US$M)                       127.37
----------------------------------------------------------------------------
Stockpile re-handling
(US$/t)                        1.50     Indirect cost (US$M)          19.14
----------------------------------------------------------------------------
Plant feed at ROM pad                   Accuracy provision
(US$/t)                        0.25     (US$M)                        22.22
----------------------------------------------------------------------------
Ore haulage (US$/t)                     Sub-Total Initial
(Kraku Pester)                 3.50     Capital (US$M)               168.73
----------------------------------------------------------------------------
Processing (US$/t) -
full production year          11.55     Owner's costs (US$M)           8.29
----------------------------------------------------------------------------
Concentrate costs
(TC/RC, transport                       Total Initial Capital
etc.) (US$/dry t                        (US$M) - including
concentrate)            200.0-203.8     working capital              177.02
----------------------------------------------------------------------------
General services
(US$/t)                        0.74
----------------------------------------------------------------------------
CAT mining equipment
financing cost (US$/t)         1.15     State royalty                     5%
----------------------------------------------------------------------------
Total operating cost
(US$/t)                       37.99
----------------------------------------------------------------------------
Plant recoveries:                       Plant recoveries:
Bigar Hill                       80%    Kraku Pester                     56%
----------------------------------------------------------------------------
Plant recoveries:                       Overall plant
Korkan                           68%    recoveries: LOM                  75%
----------------------------------------------------------------------------

A full list of the assumptions will be set out in the NI 43-101 technical report for the PEA.

Project Sensitivities

The Timok Gold Project PEA is based on producing a gold-rich sulphide concentrate for sale to smelters. A small positive increase in gold price and/or gold recovery has a marked effect on the project economics, as illustrated in the table below (with the pit designs and schedules unchanged). The optimum pit shells, which form the basis of the PEA pit designs, are most sensitive to plant recovery and the gold price. The Company believes that the metallurgical testwork recommended in the PEA may result in higher overall plant recoveries, which would result in a higher conversion ratio. Independently, an increase in the gold price will also increase the conversion ratio, as larger pits are developed. As noted below, Avala also intends to assess the potential for underground extraction of gold mineralisation beneath the open pit designs.


----------------------------------------------------------------------------
            Preliminary Economic Analysis Sensitivity Summary (1)
----------------------------------------------------------------------------
                                    Gold Price    NPV@0%    NPV@5%       IRR
Sensitivity                           (US$/oz)    (US$M)    (US$M)       (%)
----------------------------------------------------------------------------
                           Gold Price Sensitivity
----------------------------------------------------------------------------
Gold price +US$150                        1450     219.2     132.1      22.4
----------------------------------------------------------------------------
Gold price +US$100                        1400     188.7     109.7      19.8
----------------------------------------------------------------------------
Gold price +US$50                         1350     158.1      87.3      17.2
----------------------------------------------------------------------------
Base case gold price                      1300     127.6      64.9      14.3
----------------------------------------------------------------------------
Gold price -US$50                         1250      97.0      42.6      11.4
----------------------------------------------------------------------------
Gold price -US$100                        1200      66.5      20.2       8.2
----------------------------------------------------------------------------
                            Recovery Sensitivity
----------------------------------------------------------------------------
Recovery +6%                              1300     191.0     111.0      19.9
----------------------------------------------------------------------------
Recovery +4%                              1300     169.9      96.6      18.1
----------------------------------------------------------------------------
Recovery +2%                              1300     148.7      80.3      16.3
----------------------------------------------------------------------------
Recovery -2%                              1300     106.4      49.6      12.3
----------------------------------------------------------------------------
Recovery -4%                              1300      85.2      34.3      10.2
----------------------------------------------------------------------------
                           Combined Sensitivities
----------------------------------------------------------------------------
Recovery +4% & gold price +US50           1350     202.1     119.2      20.8
----------------------------------------------------------------------------
Recovery +6% & gold price +US$100         1400     257.0     159.3      25.2
----------------------------------------------------------------------------

(1) Same result on a pre- and after-tax basis due to the expected
 qualification to a 10-year tax holiday under current tax legislation in
 Serbia.

Mineral Resources

In conjunction with the preparation of the PEA, the mineral resource estimates for the Bigar Hill and Korkan deposits (Oct 2013) and Kraku Pester deposit (Jan 2013) have been updated to constrain the deposits within pit shells for the purposes of the PEA, based on the assumptions, parameters and methodology that are summarised below. At this stage the Korkan East deposit has not been subject to preliminary economic assessment. The Bigar Hill, Korkan and Kraku Pester estimates are supported by 271,420.2 metres of drilling. The average drill spacing is 40 meters by 40 meters for indicated resources and 80 meters by 80 meters for inferred resources. The mineral resources for Bigar Hill, Korkan and Kraku Pester, which were used in the PEA, are listed in the table below.


----------------------------------------------------------------------------
                             TIMOK GOLD PROJECT
              INDICATED AND INFERRED RESOURCES USED IN THE PEA
----------------------------------------------------------------------------
                                 Indicated                 Inferred
                         ---------------------------------------------------
                 Cut Off                  Million                    Million
                  Grade   Million     Au   Ounces  Million     Au     Ounces
Deposit        (Au g/t)    Tonnes  (g/t)     (Au)   Tonnes  (g/t)       (Au)


----------------------------------------------------------------------------
Bigar Hill           0.3    38.62   1.19     1.48      1.3    1.3        0.1
----------------------------------------------------------------------------
Korkan               0.3    22.35   1.07     0.77      2.7    0.9        0.1
----------------------------------------------------------------------------
Kraku Pester         0.3     6.45   1.05     0.22      0.3    0.8        0.0
----------------------------------------------------------------------------
Total                       67.42   1.14     2.48      4.3    1.0        0.2
----------------------------------------------------------------------------
Notes: (1) The effective date of the updated mineral resource estimate is
           May 1, 2014.
       (2) The resource estimation was prepared by Chris Arnold MAusIMM
           CP(Geo) of AMC Consultants Limited using the Canadian Institute
           of Mining, Metallurgy and Petroleum (CIM), CIM Standards on
           Mineral Resources and Reserves, Definitions and Guidelines
           prepared by the CIM Standing Committee on Reserve Definitions and
           adopted by the CIM Council.
       (3) The resources are constrained within pit shells returning the
           maximum undiscounted values, based on the following assumptions:
           NSR gold price of $1500/oz ($1700/oz spot price less $200/oz for
           off-site concentrate costs), 85% gold recovery for Bigar Hill and
           Korkan, 80% recovery for Kraku Pester, 55 degree pit slopes,
           US$2.00/t ore and waste mining costs (including rehabilitation
           costs) andUS$12.70/t processing and other costs, resulting in cut
           off grades of 0.32g/t for Bigar Hill and Korkan and 0.34g/t for
           Kraku Pester. Both cut off grades have been rounded to 0.3g/t for
           the reporting of resources within the designated pit shells.
       (4) Mineral resources, which are not mineral reserves, do not have
           demonstrated economic viability. The estimate of mineral
           resources may be materially affected by environmental,
           permitting, legal, title, taxation, sociopolitical, marketing, or
           other relevant issues.
       (5) The quantity and grade of reported inferred resources in this
           estimation are uncertain in nature and there has been
           insufficient exploration to define these inferred resources as
           indicated or measured mineral resources.
       (6) Totals and average grades are subject to rounding to the
           appropriate precision.
       (7) The key changes between the previous mineral resource estimate
           for the Bigar Hill, Korkan and Kraku Pester deposits (news
           release of October 16, 2013) and this updated mineral resource
           are that the updated resource estimate is constrained within a
           pit shell and has been reported at a lower cut-off, commensurate
           with the gold price and costs parameters used to defined the
           constrained pit.

The NI 43-101 technical report to be filed for the PEA will include the technical and scientific data to support the updated mineral resource estimate.

Next Steps

Subject to the availability of funds, Avala plans to do the following work to advance the Timok Gold Project.

Several metallurgical testwork programs have been undertaken since 2011 on samples selected from the Timok Gold Project deposits. Initial work investigated the potential for gold recovery from several processing options, including cyanidation techniques. During 2012 and 2013, the metallurgical testwork focus changed to the assessment of ultra-fine grinding and flotation to produce a gold-rich sulphide concentrate for treatment by others. In addition, the potential for upgrading via attritioning/scrubbing (pre-concentration) was evaluated, which showed promise but was not taken further in the PEA design. Testwork was successful in using primary grinding, ultra-fine grinding and flotation to produce a gold bearing pyritic concentrate. Metallurgical recoveries adopted for the design were 80%, 68% and 56% for Bigar Hill, Korkan and Kraku Pester deposits respectively; into a design concentrate mass pull of 4%. Testwork to support pre-feasibility study activities would include:


--  Detailed mineralogical evaluation to improve understanding of gold
    associations with gangue and sulphide minerals;

--  SAG milling characterization;

--  Further evaluation of scrubbing/attritioning (pre-concentration)
    potential;

--  Evaluation of finer grind sizes to improve flotation recovery;

--  Larger scale ultra-fine grinding testwork to confirm specific energy
    requirements and to prepare flotation feed;

--  Staged Flotation Reactor circuit testing;

--  Production of concentrate for marketing purposes; and

--  Liquid-solid separation testwork (concentrate and tailings).

Avala has developed an extensive geo-metallurgical database for the Timok Gold Project and plans to produce detailed three dimensional geometallurgical models of the deposits to assist with effective targeting of further metallurgical testwork.

Review of the Bigar Hill and Korkan resource models suggests there may be potential for underground extraction of gold mineralization beneath the current open pit designs. Avala plans to assess this potential, along with preliminary assessment of the recently announced Korkan East deposit.

During Q1 2014 Avala was granted the right to explore on the Bigar Istok license (15 square kilometers) which is located immediately due east of the Potoj Cuka Tisnica exploration license, which hosts the currently defined deposits. Previous exploration in this area has highlighted various gold-in-soil anomalies together with evidence of historic gold and base metal mineralization as defined by previous Serbian State exploration drilling. Avala believes that the exploration potential of the Bigar Istok license area, together with the various prospects located proximal to the currently defined deposits, remains high.

Qualified Persons

The PEA was completed by AMEC Australia Pty Ltd. under the supervision of Peter Nofal, FAusIMM, with participation of AMEC Growth Regions Mining Services Group UK and Gary Jobson, MAusIMM, of Macromet Pty Ltd. (metallurgy), Nick Journet, ARSM, FAusIMM, of Dumpsolver Pty Ltd.(mining), Chris Arnold MAusIMM CP(Geo), AMC UK, (geology and resource modeling), Fergus Anckorn, FAusIMM CP(Environmental), of AMEC Earth and Environmental (UK) Ltd (Environmental, Social and Permitting), Ciaran Molloy, MIMMM ICE QP of AMEC Growth Regions Specialty Mining Services Group (Geotechnical & Civil Engineering), and Rod Cameron, F.Geol.Soc.London Chartered Geologist, of AMEC Growth Regions Speciality Mining Services Group (Tailings and Water Management). The Bigar Hill, Korkan and Kraku Pester updated mineral resource estimate was undertaken by independent qualified person Chris Arnold MAusIMM CP(Geo) of AMC. Mr. Arnold has reviewed and approved the contents of this press release insofar as mineral resource estimates are concerned. Dr. Julian F. H. Barnes, FAusIMM, MAIG, a director of the Company and special consultant, is the Company's designated qualified person for purposes of the PEA. All qualified persons have reviewed and approved the disclosure in this press release related to their respective areas of expertise.

About Avala Resources Ltd.: Avala Resources is a mineral exploration company focused on the exploration and development of the Timok Gold Project in Eastern Serbia. The Timok Gold Project comprises several targets, including the Korkan, Bigar Hill, Kraku Pester, and Korkan East deposits. Avala controls 100% of this recently identified sediment-hosted gold belt which totals approximately 250 square kilometers. The common shares of Avala trade on the TSX Venture Exchange under the symbol AVZ.

Avala had approximately $1.1 million in its treasury at March 31, 2014. Avala's issued and outstanding share capital totals 254,492,223 common shares, of which approximately 53.1% is held by Dundee Precious Metals Inc. (TSX: DPM).

Additional information about the Company is available on Avala's website (www.avalaresources.com) and on SEDAR (www.sedar.com).

Cautionary Statement Regarding Forward-Looking Information

This press release contains 'forward-looking information' within the meaning of Canadian securities legislation. Forward looking information in this press release includes information about the results of a Preliminary Economic Assessment (PEA). This PEA is the first in a series of development studies for the project assessing the potential viability of a potential mining operation on the Timok Gold Project. The operating and capital costs estimated in the PEA were developed to be reasonable estimates within industry benchmarks. The PEA is intended to quantify the project's cost parameters which will, in turn, be used to guide ongoing exploration and engineering work and to define the optimal scale of the operation for a feasibility study. Forward looking information in this press release also includes information about planned metallurgical testwork and the ability to increase metal recoveries through additional work, completion of a pre-feasibility study, the potential to incorporate an underground operation into the open pit plans for the Timok Gold Project, and the exploration potential of the Bigar Istok license and the target areas nearby Bigar Hill, Korkan, Kraku Pester, and Korkan East. This press release also includes an updated mineral resource estimate. Mineral resources are not mineral reserves and do not have demonstrated economic viability. Inferred resources have a great amount of uncertainty as to their existence, and economic and legal feasibility. Since forward-looking information is based on assumptions and addresses future events and conditions, by its very nature it involves risks and uncertainties. Certain assumptions used in the PEA and the resource estimate are summarized in this press release. Actual results could differ materially from those anticipated in the forward looking information for many reasons including, but not limited to: changes in general economic conditions and conditions in the financial markets; changes in demand and prices for gold; changes in prices of inputs and other assumptions in the PEA and the resource estimate; unavailability of the 10-year tax holiday; legislative, environmental and other regulatory, political and competitive developments; operational difficulties encountered in connection with the activities of the Company; and the Company's financial condition and financial resources to execute its business plans. These and other factors referred to in public disclosures and filings by the Company should be considered carefully, and readers should not place undue reliance on the Company's forward-looking information. The Company does not undertake to update any forward-looking information, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
There's Big Data, then there's really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. In her session at Big Data Expo®, Hannah Smalltree, Director at Treasure Data, discussed how IoT, Big Data and deployments are processing massive data volumes from wearables, utilities and other machines...
SYS-CON Events announced today that Gridstore™, the leader in hyper-converged infrastructure purpose-built to optimize Microsoft workloads, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Gridstore™ is the leader in hyper-converged infrastructure purpose-built for Microsoft workloads and designed to accelerate applications in virtualized environments. Gridstore’s hyper-converged infrastructure is the industry’s first all flash version of HyperConverged Appliances that include both compute and storag...
The Internet of Things promises to transform businesses (and lives), but navigating the business and technical path to success can be difficult to understand. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, demonstrated how to approach creating broadly successful connected customer solutions using real world business transformation studies including New England BioLabs and more.
WebRTC defines no default signaling protocol, causing fragmentation between WebRTC silos. SIP and XMPP provide possibilities, but come with considerable complexity and are not designed for use in a web environment. In his session at @ThingsExpo, Matthew Hodgson, technical co-founder of the Matrix.org, discussed how Matrix is a new non-profit Open Source Project that defines both a new HTTP-based standard for VoIP & IM signaling and provides reference implementations.
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete at launch. DevOps may be disruptive, but it is essential.
Explosive growth in connected devices. Enormous amounts of data for collection and analysis. Critical use of data for split-second decision making and actionable information. All three are factors in making the Internet of Things a reality. Yet, any one factor would have an IT organization pondering its infrastructure strategy. How should your organization enhance its IT framework to enable an Internet of Things implementation? In his session at Internet of @ThingsExpo, James Kirkland, Chief Architect for the Internet of Things and Intelligent Systems at Red Hat, described how to revolutioniz...
The Internet of Things is tied together with a thin strand that is known as time. Coincidentally, at the core of nearly all data analytics is a timestamp. When working with time series data there are a few core principles that everyone should consider, especially across datasets where time is the common boundary. In his session at Internet of @ThingsExpo, Jim Scott, Director of Enterprise Strategy & Architecture at MapR Technologies, discussed single-value, geo-spatial, and log time series data. By focusing on enterprise applications and the data center, he will use OpenTSDB as an example t...
Connected devices and the Internet of Things are getting significant momentum in 2014. In his session at Internet of @ThingsExpo, Jim Hunter, Chief Scientist & Technology Evangelist at Greenwave Systems, examined three key elements that together will drive mass adoption of the IoT before the end of 2015. The first element is the recent advent of robust open source protocols (like AllJoyn and WebRTC) that facilitate M2M communication. The second is broad availability of flexible, cost-effective storage designed to handle the massive surge in back-end data in a world where timely analytics is e...
Scott Jenson leads a project called The Physical Web within the Chrome team at Google. Project members are working to take the scalability and openness of the web and use it to talk to the exponentially exploding range of smart devices. Nearly every company today working on the IoT comes up with the same basic solution: use my server and you'll be fine. But if we really believe there will be trillions of these devices, that just can't scale. We need a system that is open a scalable and by using the URL as a basic building block, we open this up and get the same resilience that the web enjoys.
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
How do APIs and IoT relate? The answer is not as simple as merely adding an API on top of a dumb device, but rather about understanding the architectural patterns for implementing an IoT fabric. There are typically two or three trends: Exposing the device to a management framework Exposing that management framework to a business centric logic Exposing that business layer and data to end users. This last trend is the IoT stack, which involves a new shift in the separation of what stuff happens, where data lives and where the interface lies. For instance, it's a mix of architectural styles ...
The definition of IoT is not new, in fact it’s been around for over a decade. What has changed is the public's awareness that the technology we use on a daily basis has caught up on the vision of an always on, always connected world. If you look into the details of what comprises the IoT, you’ll see that it includes everything from cloud computing, Big Data analytics, “Things,” Web communication, applications, network, storage, etc. It is essentially including everything connected online from hardware to software, or as we like to say, it’s an Internet of many different things. The difference ...
The security devil is always in the details of the attack: the ones you've endured, the ones you prepare yourself to fend off, and the ones that, you fear, will catch you completely unaware and defenseless. The Internet of Things (IoT) is nothing if not an endless proliferation of details. It's the vision of a world in which continuous Internet connectivity and addressability is embedded into a growing range of human artifacts, into the natural world, and even into our smartphones, appliances, and physical persons. In the IoT vision, every new "thing" - sensor, actuator, data source, data con...
P2P RTC will impact the landscape of communications, shifting from traditional telephony style communications models to OTT (Over-The-Top) cloud assisted & PaaS (Platform as a Service) communication services. The P2P shift will impact many areas of our lives, from mobile communication, human interactive web services, RTC and telephony infrastructure, user federation, security and privacy implications, business costs, and scalability. In his session at @ThingsExpo, Robin Raymond, Chief Architect at Hookflash, will walk through the shifting landscape of traditional telephone and voice services ...
"Matrix is an ambitious open standard and implementation that's set up to break down the fragmentation problems that exist in IP messaging and VoIP communication," explained John Woolf, Technical Evangelist at Matrix, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
An entirely new security model is needed for the Internet of Things, or is it? Can we save some old and tested controls for this new and different environment? In his session at @ThingsExpo, New York's at the Javits Center, Davi Ottenheimer, EMC Senior Director of Trust, reviewed hands-on lessons with IoT devices and reveal a new risk balance you might not expect. Davi Ottenheimer, EMC Senior Director of Trust, has more than nineteen years' experience managing global security operations and assessments, including a decade of leading incident response and digital forensics. He is co-author of t...
We are reaching the end of the beginning with WebRTC, and real systems using this technology have begun to appear. One challenge that faces every WebRTC deployment (in some form or another) is identity management. For example, if you have an existing service – possibly built on a variety of different PaaS/SaaS offerings – and you want to add real-time communications you are faced with a challenge relating to user management, authentication, authorization, and validation. Service providers will want to use their existing identities, but these will have credentials already that are (hopefully) i...
The 3rd International @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The Internet of Things (IoT) is the most profound change in personal and enterprise IT since the creation of the Worldwide Web more than 20 years ago. All major researchers estimate there will be tens of billions devices - computers, smartphones, tablets, and sensors - connected to the Internet by 2020. This number will continue to grow at a rapid pace for the next several decades.
The Internet of Things will greatly expand the opportunities for data collection and new business models driven off of that data. In her session at @ThingsExpo, Esmeralda Swartz, CMO of MetraTech, discussed how for this to be effective you not only need to have infrastructure and operational models capable of utilizing this new phenomenon, but increasingly service providers will need to convince a skeptical public to participate. Get ready to show them the money!
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.