Click here to close now.

Welcome!

.NET Authors: Aria Blog, Pat Romanski, Elizabeth White, Hovhannes Avoyan, Sanjeev Sharma

News Feed Item

Avanti Mining Updates Kitsault Feasibility Study

VANCOUVER, BC -- (Marketwire) -- 02/05/13 -- Avanti Mining Inc. (TSX VENTURE: AVT) (PINKSHEETS: AVNMF) ("Avanti") is pleased to provide the results of an update to its 2010 National Instrument ("NI") 43-101 compliant Feasibility Study ("FS") prepared by AMEC on its 100% owned Kitsault Molybdenum property in northwest British Columbia, Canada. The technical report summarizing the complete FS update report will be filed on SEDAR and Avanti's web site, www.avantimining.com, within 45 days of the issue of this press release. All figures are in Canadian dollars (converted at a long term rate of US$ 0.93 = C$ 1.00) except where noted.

Highlights include:

  • Initial capital costs including working capital are estimated at $938 million and LOM sustaining capital at $ 106 million (+/- 15% accuracy);
  • Cash operating cost at the mine site are estimated at $6.65 per pound of Mo produced, but it drops to $5.73 per pound of Mo (US$ 5.33), after a by-product silver credit of $0.91 per pound of molybdenum is realized. Total cash cost including transportation and beneficiation would be $6.73 (US$ 6.26) per pound of Mo.
  • The new mine plan based upon an updated resource model developed in 2012 calls for a total of 228 million tonnes of proven and probable reserves grading 0.083% molybdenum and 5.0 g/t silver to be mined over a 16-year mine life, producing 374 million pounds of molybdenum and 14.4 million ounces of silver. The molybdenum grade to the mill over the first five years of production averages 0.103% Mo;
  • At a long term molybdenum price of US$14.50/lb, that approximates the 3 year trailing average price, the project has an after tax Net Present Value (NPV) at an 8% discount rate of $433 million and a 16.6% IRR.
  • The mine has certain infrastructure in place with road access and will be serviced by the existing BC Hydro transmission grid;
  • The reopening of the mine is projected to create over 300 high paying local jobs during its 16-year life, and at the peak of construction, over 700 jobs. The construction period is estimated at 25 months;
  • The project is progressing through the environmental assessment process under the BC and federal legislation as well as the Nisga'a Final Agreement. The Referral Report to the BC Ministries of Environment and Energy, Mines and Natural Gas is expected to be submitted by mid-February. The Ministries then have up to 45 days to render their decision on the Environmental Assessment Certificate. The federal environmental assessment process, although largely coordinated with the province, is expected to be completed two months after the BC process because of statutory differences in the approval process between the two Acts.
  • Inaugural NI 43-101 compliant mineral resource statements were prepared at the Roundy Creek and Bell Moly prospects. Roundy Creek is located 4 km due west of Kitsault, yielded an Indicated Mineral Resource of 1.94 million tonnes grading 0.109% Mo at the Sunshine and Sunlight Areas containing 4.7 million pounds molybdenum, and an additional Inferred Mineral Resource of 0.33 million tonnes grading 0.079% Mo for 0.6 million pounds of molybdenum. The adjacent Roundy Area contains an additional Inferred Mineral Resource of 4.32 million tonnes grading 0.073% Mo containing 7.0 million pounds of molybdenum.
  • The Bell Moly prospect located 6.5 km northeast of Kitsault, yielded an Inferred Mineral Resource of 109.7 million tonnes grading 0.048% Mo containing 115.8 million pounds of molybdenum.

"We are pleased to present the cost update of our 2010 Feasibility Study by AMEC and other contributors on the Kitsault Mine Project," stated Craig J. Nelsen, Avanti's President and CEO. "The project continues to show robust economics despite the sharp industry-wide rise in capital and operating cost. In fact, Kitsault's projected cash costs are in the lowest quartile of primary molybdenum producers worldwide. We are fortunate to have been able to add silver by-product revenue to help offset the increased operating costs. Initial NI 43-101 resources at the neighboring Roundy Creek and Bell Moly prospects continue to add value to the long term reserve expansion possibilities of the Kitsault property." Mark Premo, Avanti's Chief Operating Officer, added, "Although pleased with this update, Avanti is currently engaging a third party engineering and business optimization group to review this FS update and examine ways of further optimizing the project's initial capital cost by potentially staging production increases funded largely out of free cash flow. This additional project optimization review will allow us an opportunity to select the best-fit initial production level combined with planned staged development to achieve the mine's increased production levels. This staged approach also is supported by short term supply demand outlook."

Project Description

The Kitsault property is located about 140 km north of Prince Rupert, British Columbia, and south of the head of Alice Arm, an inlet of the Pacific Ocean. The property includes three known molybdenum deposits, Kitsault, Bell Moly, and Roundy Creek. The Kitsault mine was a producer of molybdenum between 1967 and 1972 and from 1981 to 1982 with total production on the property during both periods being approximately 31 million pounds of molybdenum.

Kitsault has road access to the mine site and is serviced by the BC Hydro transmission grid. The FS update estimates that the Kitsault Mine would operate at an annual mill throughput rate of 14.6 million tonnes, or 40,000 tpd, with a strip ratio of 1.05:1 for a mine life of 16 years. The ore mined by conventional truck and shovel open pit methods will be crushed in a gyratory primary crusher, then ground using a SAG-ball mill configuration. Conventional flotation and five stages of cleaning will produce molybdenum concentrate that will be dried and packaged into bags for shipment. The life-of-mine molybdenum production is estimated at 374 million pounds of molybdenum contained in approximately 350,800 tonnes of molybdenum concentrate produced from the processing of 228 million tonnes of reserves grading 0.083% Mo. Total molybdenum recovery varies depending on mill head grade but is estimated to average 90% over the life of the mine. During the desulfidation of the tailings for environmental considerations, a process was developed to recover by-product silver that averages 5.0 g/t in the mill feed. Silver production of 14.4 million ounces is indicated at a metallurgical recovery of about 39%.

Mineral Reserves Statement

The Kitsault mine Mineral Reserves have been prepared in accordance with NI 43-101 standards and CIM Definition Standard (2010). This statement was prepared by Mr. Ramon Mendoza Reyes (P.Eng.) of AMEC, a QP as defined in NI 43-101. These reserves are sufficient for 16 years of operation at an annual production rate of 40,000 t/d. Mineral Reserves are summarized by category in Table 1. The notes accompanying Table 1 are an integral part of the Mineral Reserves and should be read in conjunction with the Mineral Reserve statement.

Table 1. Kitsault Mineral Reserves, Effective Date February 4, 2013, Ramon
Mendoza Reyes, P. Eng. (cut-off 0.026% Mo)

============================================================================
                                                         Contained Contained
Classification              Tonnage (Mt) Mo (%) Ag (g/t) Mo (M lb) Ag (M Oz)
============================================================================
Proven                          129.0     0.092    5.0     262.4      20.7
Probable                        99.2      0.070    5.0     153.1      15.9
----------------------------------------------------------------------------
Total Proven and Probable       228.2     0.083    5.0     415.5      36.6
============================================================================

Notes:

1. Mineral Reserves are defined within a mine plan, with pit phase designs guided by Lerchs-Grossmann (LG) pit shells, and reported at a 0.026% Mo cut-off grade, after dilution and mining loss adjustments. The LG shell generation was performed on Measured and Indicated mineral resources only, using a molybdenum price of $13.58/lb, an average mining cost of $1.88/t mined, a combined ore based cost of $7.09/t milled, and a selling cost of $1.24 /lb of Mo sold. Metallurgical recovery used was a function of the head grade, defined as Recovery =7.5808*Ln (Mo %) +108.63 with a cap applied at 95%. Revenue from silver was not included in the LG shell generation. Overall pit slopes varied from 42 to 48 degrees.

2. Dilution and Mining loss have been accounted for based on a contact dilution approach assuming a dilution band of one meter around the contact edges. 2.6Mt of Measured and Indicated mineral resources above cut-off was routed as waste. 1.4Mt of Measured and Indicated material below cut-off has been included as dilution material. The grade of the diluting material was the grade of those blocks. An additional 0.3Mt of Inferred dilution material with grades set to zero is included in the mine plan as mill feed.

3. Tonnages are rounded to the nearest 100,000 tonnes; grades are rounded to three decimal places for Mo and one decimal place for Ag.

4. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal content.

5. Tonnage and grade measurements are in metric units; contained molybdenum is in imperial pounds and contained silver is in troy ounces.

6. The life-of-mine strip ratio is 1.05:1

Capital Costs

Initial capital costs are estimated at $938 million compared with $837 million in the initial FS for an increase of approximately 12%. Life-of-Mine sustaining mine capital was estimated to be $106 million, which is comprised mainly of mobile equipment replacement, ongoing Tailings Management Facility ("TMF") embankment construction and estimated closure and reclamation cost requirements. This compares with $85 million in the initial FS for an increase of about 25%. All capital costs are [+/-15%] accuracy in this estimate.

The capital costs for the mine, plant and TMF and comparison with the 2010 FS are given in Table 2 below.

Table 2. Capital Cost Summary Comparison

----------------------------------------------------------------------------
                           Kitsault Capital Costs
----------------------------------------------------------------------------
                                                 2010     2013        %
Preproduction Capital                            FS      Update   Difference

1000 Mining                              $000  91,055   111,269      22%
2000 Site Preparation and Roads          $000  38,636   44,318       15%
3000 Process Facilities                  $000 212,069   238,665      13%
4000 Tailings Management and Reclaim
Systems                                  $000  97,614   120,936      24%
5000 Utilities                           $000  43,131   37,521      (13%)
6000 Ancillary Buildings and Facilities  $000  41,733   49,896       20%
8000 Owners Costs                        $000  22,858   22,069       (3%)
9000 Indirects, excluding contingency    $000 176,071   173,951      (1%)
9900 Contingency                         $000 113,834   139,597      23%

----------------------------------------------------------------------------
Total Pre-Production Capital             $000 837,000   938,221      12%
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Sustaining Capital
            Closure and Reclamation Cost $000  31,368   33,960        8%
      Sustaining Capital Operating Years $000  53,806   72,357       34%

----------------------------------------------------------------------------
Total Sustaining Capital                 $000  85,174   106,317      25%
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Total Capital Cost                       $000 922,174  1,044,538     13%
----------------------------------------------------------------------------

Operating Costs

LOM cash mine site operating costs are estimated at $6.65 per pound molybdenum (+/-15% accuracy). Total cash cost including a silver credit of $0.91 per pound molybdenum and transportation and beneficiation charges are $6.73 per pound molybdenum (US $6.26). These costs are about 11% higher than the 2010 FS. The Life-of-Mine (LOM) unit cash operating costs are also summarized in Table 3 below:

Table 3. Cash Operating Costs Summary Comparison (LOM average)

---------------------------------------------------------------------------
                          Kitsault Operating Cost
---------------------------------------------------------------------------
                                                                      %
Area                                2010 FS        2013 Update   Difference
---------------------------------------------------------------------------
                                           Cash            Cash
                                           Cost            Cost
                                Total LOM  $/lb Total LOM  $/lb
                                   $000     Mo    C$000     Mo



Mine Operations                  573,954   1.54  933,896   2.50      63%
Processing Operations           1,102,207  2.95 1,244,879  3.33      13%
G&A                              252,984   0.68  307,166   0.82      21%
  Subtotal Mine Site            1,929,145  5.16 2,485,941  6.65      29%
Ag Credit                                       (340,878) (0.91)
Transportation and Beneficiation 342,146   0.92  371,195   0.91      8%

---------------------------------------------------------------------------
Total                           2,271,291  6.08 2,516,259  6.73      11%
---------------------------------------------------------------------------

Project Economics

The Feasibility Study economic results utilized assumptions summarized in the Table 4 below:

Table 4 Financial Analysis Parameters

============================================================================
                            Parameters                                Inputs
============================================================================
General Assumptions
----------------------------------------------------------------------------
  Mine Life                                                         16 years
----------------------------------------------------------------------------
  Available mill operating days per year                                 365
----------------------------------------------------------------------------
  Production Rate (average)                                       40,000 tpd
----------------------------------------------------------------------------
  Average Process Recovery (Mo)                                          90%
----------------------------------------------------------------------------
 Average Process Recovery (Ag)                                           39%
----------------------------------------------------------------------------
  Molybdenum Concentrate Production - LOM                          350.8 wmt
----------------------------------------------------------------------------
 Concentrate Grade (% Mo)                                                52%
----------------------------------------------------------------------------
 Long Term CDN$:US$ exchange rate                                       0.93
----------------------------------------------------------------------------
Market
----------------------------------------------------------------------------
  Discount Rate                                                           8%
----------------------------------------------------------------------------
  Base Case LOM average molybdenum price                         US$14.50/lb
----------------------------------------------------------------------------
 Base Case LOM average silver price                              US$23.13/oz
----------------------------------------------------------------------------
Royalty
----------------------------------------------------------------------------
  Amax Zinc (Newfoundland) Ltd Net profits Interest                    9.22%
----------------------------------------------------------------------------
  Alcoa Royalty                                                         1.0%
============================================================================

The FS economic model for the base case in this study assumes a long-term average molybdenum price of $14.50/lb for revenue purposes, as projected by Avanti for comparison with the project economics in the 2010 FS.

The after-tax NPV at an 8% discount rate over the estimated mine life is $433 million. The after-tax IRR is 16.6%. Payback of the initial capital investment is estimated to occur in 4.3 years after the start of production. When the same molybdenum long term price of US$14.50/lb is applied to the 2010 FS model, the after-tax NPV at an 8% discount rate was $585 million, the after tax IRR was 21.7% and the payback of initial capital was 2.9 years. Figure 1 shows a comparison of the 2010 FS model with the 2013 Update by area and net contribution. This comparison was made by comparing Present Values of both studies to the start of construction in each case.

Sensitivity

Sensitivity analysis for key economic parameters is shown in Table 5 after tax effects. This analysis suggests that the project is most sensitive to exchange rates followed by commodity prices. The project is least sensitive to operating and capital costs.

Table 5 Base Case Sensitivity to Pre-Tax NPV at 8% Discount Rate

----------------------------------------------------------------------------
SENSITIVITY OF PRE-TAX NPV @
8%                                             Change in Factor

                            Factor -30%  -20%  -10%   0%    10%   20%   30%
----------------------------------------------------------------------------
       Exchange rate           1   1,210  888   636   433   264   120  (11)
       ---------------------------------------------------------------------
Factor Capital expenditure     2    618   557   495   433   369   304   238
       ---------------------------------------------------------------------
       Operating expenditure   3    696   608   521   433   344   256   166
       ---------------------------------------------------------------------
       Metal price             4   (167)  51    245   433   617   801   983
----------------------------------------------------------------------------

The financial model also examines the primary financial outputs at various long-term molybdenum prices and various discount rates. These results are displayed in Table 6.

Table 6 Sensitivity of Project as Various Metal Prices and Discount
Rates

----------------------------------------------------------------------
              CNCF
Moly Price  (Undisc.)  NPV @ 6%   NPV @ 8%   NPV @ 10%   IRR   Payback
 (US$/lb)   (CDN $M)   (CDN $M)   (CDN $M)   (CDN $M)     %    (Years)
----------------------------------------------------------------------
   12.50       913        302        173        67      11.5%    5.6
   14.50      1,367       597        433        299     16.6%    4.3
   15.00      1,482       669        497        355     17.8%    4.0
   17.50      2,058      1,032       814        635     23.4%    3.2
----------------------------------------------------------------------

Bell Moly and Roundy Creek NI 43-101 Resource Statement

Initial NI 43-101 compliant resources are presented for the Roundy Creek and Bell Moly prospects located 4 and 6.5 km west and northeast respectively from the Kitsault deposit. The mineral resources are reported in accordance with Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards and Estimation of Mineral Resources and Mineral Reserves Best Practices, and are compliant with NI 43-101. The resource estimates were prepared under the supervision of David Thomas, P.Geo, an independent Qualified Person (QP), as this term is defined in NI 43-101. The mineral resource statement for the Kitsault molybdenum project is presented in Table 7 and 8 below:

Table 7 Roundy Creek Mineral Resources, Effective date 1 May 2012, David
Thomas P. Geo. (0.022% Mo Cut-Off)

----------------------------------------------------------------------------
Sunshine and Sunlight Area                      Tonnage     Mo        Mo
Category                                         (Mt)        %       (Mlb)
============================================================================
Indicated                                        1.94      0.109      4.7
----------------------------------------------------------------------------
Inferred                                         0.33      0.079      0.6
----------------------------------------------------------------------------

----------------------------------------------------------------------------
Roundy Area                                     Tonnage     Mo        Mo
Category                                         (Mt)        %       (Mlb)
============================================================================
Inferred                                         4.32      0.073      7.0
----------------------------------------------------------------------------

Notes:

1. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability

2. Mineral Resources are defined with a Lerchs-Grossmann pit shell, and reported at a 0.022% Mo cut-off grade

3. An incremental mining cost of $1.20/t of resource was used to account for trucking of mineralized material to the Kitsault processing facility located approximately 7 Km to the east. A contractor mining cost of $2.90/t has been assumed.

4. Mineral Resources are reported using a commodity price of C$17.39/lb Mo, an average process recovery of 89%, a process cost of C$5.83/t and selling cost of C$1.24/lb of Mo sold.

5. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal.

6. Tonnage and grade measurements are in metric units; contained molybdenum is in imperial pounds.

Table 8 Bell Moly Mineral Resources, Effective date 1 May 2012, David Thomas
P. Geo. (0.020% Mo Cut-Off)

----------------------------------------------------------------------------
Bell Moly                                       Tonnage     Mo        Mo
Category                                         (Mt)        %       (Mlb)
============================================================================
Inferred                                         109.7     0.048     115.8
----------------------------------------------------------------------------

Notes:

1. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability

2. Mineral Resources are defined with a Lerchs-Grossmann pit shell, and reported at a 0.020% Mo cut-off grade

3. An incremental mining cost of $0.60/t of resource was used to account for trucking of mineralized material to the Kitsault processing facility located approximately 7 Km to the southeast.

4. Mineral Resources are reported using a commodity price of C$17.39/lb Mo, an average process recovery of 89%, a process cost of C$5.83/t and selling cost of C$1.24/lb of Mo sold.

5. Rounding as required by reporting guidelines may result in apparent summation differences between tonnes, grade and contained metal.

6. Tonnage and grade measurements are in metric units; contained molybdenum is in imperial pounds.

Financing and Environmental Assessment Update

Avanti continues to advance its strategy to finance the development of the Kitsault Mine. Toward that end it has signed a Letter of Intent with a major German steel maker for 50% of the production of Kitsault for the life of the mine and hopes to have a formal agreement in the near future. Contract volumes will be established annually based upon the mines plan and reference a market based monthly price for molybdenum. Based upon the strength of this off-take agreement and an application made by KFW, the German export credit bank and a member of our mandated banking syndicate, the project has received approval in principal for German government debt guarantee for up to US$300 million.

Avanti also continues discussions with a potential strategic partner that will assist in providing the equity component of the projects financing.

Avanti has received all the final comments on the review of its Environmental Assessment Application that is intended to fulfill its requirements under the BC EA Act. We expect the referral report prepared by BC EAO to be presented to the BC Ministers of Environment and Mines, Energy and Natural Gas in mid February 2013. The ministers then have up to 45 days to make their decision on the project. The federal process is expected to follow approximately two months after the provincial process because of statutory differences in the approval timeframes between the two Acts.

The NI 43-101 2013 Feasibility Study Update, Avanti Mining Inc., Kitsault Molybdenum Property, British Columbia, Canada was prepared by industry consultants, all of whom are independent of Avanti Mining Inc. and are QP's under NI 43-101. The QP's have reviewed and approved the content of this news release that summarizes the results of the 2013 Feasibility Study Update. The consultants (QP's) with their responsibilities are as follows:
AMEC Americas Limited, Mr. David Thomas (P. Geo.) for matters relating to geology and mineral resource reporting.

AMEC Americas Limited, Mr. Ramon Mendoza Reyes (P.Eng.) for matters relating to mineral reserve statements, mining plan, mining capital, and mine operating costs.

AMEC Americas Limited, Mr. Tony Lipiec (P.Eng.) for matters relating to the metallurgical testing review, mineral processing, and process operating costs.

AMEC Americas Limited under the direction of Mr. Gary Christie (P.Eng.) for matters relating to infrastructure, cost estimates, and financial analysis.

SRK Consulting (Canada) Inc. (SRK Canada) under the direction of Mr. Peter Healey (P.Eng) for matters and costs relating to mine closure and reclamation.

Knight Piésold Ltd. (KP) under the direction of Mr. Bruno Borntraeger (P.Eng.) for matters and costs relating to plant site geotechnical conditions, surface water diversions and the Tailings Management Facility (TMF).

Avanti Mining Inc. is focused on the development of the past producing Kitsault molybdenum mine located north of Prince Rupert in British Columbia. Mr. Mark Premo (P.Eng.MO), Chief Operating Officer for the Company and a Qualified Person as defined in NI 43-101, has reviewed and approved the scientific or technical information in this press release.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Forward-Looking Statements: This news release contains certain forward-looking information concerning the business of Avanti Mining Inc. (the "Corporation"). All statements, other than statements of historical fact, included herein including, without limitation; statements about the recoverability of molybdenum and silver at the Kitsault property, the results of the feasibility study, the timing of the receipt of environmental approvals and other regulatory permits, operating cost, capital cost, cash flow, the anticipated dates of commencement of construction and production, production schedule, molybdenum products meeting the specifications of the London Metals Exchange, silver concentrate quality and other matters related to the development of the Kitsault molybdenum mine, are forward-looking statements. These forward-looking statements are based on the opinions of management at the date the statements are made and are based on assumptions and subject to a variety of risks and uncertainties and other factors that could cause actual events to differ materially from those projected in forward-looking statements. Important factors that could cause actual results to differ materially from the Corporation's expectations include fluctuations in commodity prices and currency exchange rates; uncertainties relating to interpretation of drill results and the geology, continuity and grade of mineral deposits; uncertainty of estimates of capital and operating costs, recovery rates, production estimates and estimated economic return; the need for cooperation of government agencies and native groups in the exploration and development of properties and the issuance of required permits; the need to obtain additional financing to develop properties and uncertainty as to the availability and terms of future financing; the possibility of delay in exploration or development programs or in construction projects and uncertainty of meeting anticipated program milestones; uncertainty as to timely availability of permits and other governmental approvals; and other risks and uncertainties disclosed in the Corporation's Annual Information Form for the year ended December 31, 2010, which is available at www.Sedar.com. The Corporation is under no obligation to update forward-looking statements if circumstances or management's opinions should change, except as required by applicable securities laws. The reader is cautioned not to place undue reliance on forward-looking statements.

Image Available: http://www2.marketwire.com/mw/frame_mw?attachid=2220561

For further information, please visit www.avantimining.com, or contact:

Craig J. Nelsen
Chief Executive Officer
303-565-5491, extension 4471

Mark Premo
Chief Operating Officer
604-620-6659

A.J. Ali
Chief Financial Officer
303-565-5491, extension 4472

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
The industrial software market has treated data with the mentality of “collect everything now, worry about how to use it later.” We now find ourselves buried in data, with the pervasive connectivity of the (Industrial) Internet of Things only piling on more numbers. There’s too much data and not enough information. In his session at @ThingsExpo, Bob Gates, Global Marketing Director, GE’s Intelligent Platforms business, to discuss how realizing the power of IoT, software developers are now focused on understanding how industrial data can create intelligence for industrial operations. Imagine ...
Operational Hadoop and the Lambda Architecture for Streaming Data Apache Hadoop is emerging as a distributed platform for handling large and fast incoming streams of data. Predictive maintenance, supply chain optimization, and Internet-of-Things analysis are examples where Hadoop provides the scalable storage, processing, and analytics platform to gain meaningful insights from granular data that is typically only valuable from a large-scale, aggregate view. One architecture useful for capturing and analyzing streaming data is the Lambda Architecture, representing a model of how to analyze rea...
SYS-CON Events announced today that Vitria Technology, Inc. will exhibit at SYS-CON’s @ThingsExpo, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Vitria will showcase the company’s new IoT Analytics Platform through live demonstrations at booth #330. Vitria’s IoT Analytics Platform, fully integrated and powered by an operational intelligence engine, enables customers to rapidly build and operationalize advanced analytics to deliver timely business outcomes for use cases across the industrial, enterprise, and consumer segments.
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @ThingsExpo, Michael Sick, a Senior Manager and Big Data Architect within Ernst and Young's Financial Servi...
SYS-CON Events announced today that Open Data Centers (ODC), a carrier-neutral colocation provider, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place June 9-11, 2015, at the Javits Center in New York City, NY. Open Data Centers is a carrier-neutral data center operator in New Jersey and New York City offering alternative connectivity options for carriers, service providers and enterprise customers.
When it comes to the Internet of Things, hooking up will get you only so far. If you want customers to commit, you need to go beyond simply connecting products. You need to use the devices themselves to transform how you engage with every customer and how you manage the entire product lifecycle. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, will show how “product relationship management” can help you leverage your connected devices and the data they generate about customer usage and product performance to deliver extremely compelling and reliabl...
SYS-CON Events announced today that CodeFutures, a leading supplier of database performance tools, has been named a “Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9–11, 2015, at the Javits Center in New York, NY. CodeFutures is an independent software vendor focused on providing tools that deliver database performance tools that increase productivity during database development and increase database performance and scalability during production.
The IoT market is projected to be $1.9 trillion tidal wave that’s bigger than the combined market for smartphones, tablets and PCs. While IoT is widely discussed, what not being talked about are the monetization opportunities that are created from ubiquitous connectivity and the ensuing avalanche of data. While we cannot foresee every service that the IoT will enable, we should future-proof operations by preparing to monetize them with extremely agile systems.
There’s Big Data, then there’s really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. Learn about IoT, Big Data and deployments processing massive data volumes from wearables, utilities and other machines.
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @ThingsExpo, Michael Sick, a Senior Manager and Big Data Architect within Ernst and Young's Financial Servi...
“In the past year we've seen a lot of stabilization of WebRTC. You can now use it in production with a far greater degree of certainty. A lot of the real developments in the past year have been in things like the data channel, which will enable a whole new type of application," explained Peter Dunkley, Technical Director at Acision, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Intelligent Systems Services will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Established in 1994, Intelligent Systems Services Inc. is located near Washington, DC, with representatives and partners nationwide. ISS’s well-established track record is based on the continuous pursuit of excellence in designing, implementing and supporting nationwide clients’ mission-critical systems. ISS has completed many successful projects in Healthcare, Commercial, Manufacturing, ...
PubNub on Monday has announced that it is partnering with IBM to bring its sophisticated real-time data streaming and messaging capabilities to Bluemix, IBM’s cloud development platform. “Today’s app and connected devices require an always-on connection, but building a secure, scalable solution from the ground up is time consuming, resource intensive, and error-prone,” said Todd Greene, CEO of PubNub. “PubNub enables web, mobile and IoT developers building apps on IBM Bluemix to quickly add scalable realtime functionality with minimal effort and cost.”
The major cloud platforms defy a simple, side-by-side analysis. Each of the major IaaS public-cloud platforms offers their own unique strengths and functionality. Options for on-site private cloud are diverse as well, and must be designed and deployed while taking existing legacy architecture and infrastructure into account. Then the reality is that most enterprises are embarking on a hybrid cloud strategy and programs. In this Power Panel at 15th Cloud Expo (http://www.CloudComputingExpo.com), moderated by Ashar Baig, Research Director, Cloud, at Gigaom Research, Nate Gordon, Director of T...
Sensor-enabled things are becoming more commonplace, precursors to a larger and more complex framework that most consider the ultimate promise of the IoT: things connecting, interacting, sharing, storing, and over time perhaps learning and predicting based on habits, behaviors, location, preferences, purchases and more. In his session at @ThingsExpo, Tom Wesselman, Director of Communications Ecosystem Architecture at Plantronics, will examine the still nascent IoT as it is coalescing, including what it is today, what it might ultimately be, the role of wearable tech, and technology gaps stil...
DevOps tends to focus on the relationship between Dev and Ops, putting an emphasis on the ops and application infrastructure. But that’s changing with microservices architectures. In her session at DevOps Summit, Lori MacVittie, Evangelist for F5 Networks, will focus on how microservices are changing the underlying architectures needed to scale, secure and deliver applications based on highly distributed (micro) services and why that means an expansion into “the network” for DevOps.
The Internet of Everything (IoE) brings together people, process, data and things to make networked connections more relevant and valuable than ever before – transforming information into knowledge and knowledge into wisdom. IoE creates new capabilities, richer experiences, and unprecedented opportunities to improve business and government operations, decision making and mission support capabilities. In his session at @ThingsExpo, Gary Hall, Chief Technology Officer, Federal Defense at Cisco Systems, will break down the core capabilities of IoT in multiple settings and expand upon IoE for bo...
With several hundred implementations of IoT-enabled solutions in the past 12 months alone, this session will focus on experience over the art of the possible. Many can only imagine the most advanced telematics platform ever deployed, supporting millions of customers, producing tens of thousands events or GBs per trip, and hundreds of TBs per month. With the ability to support a billion sensor events per second, over 30PB of warm data for analytics, and hundreds of PBs for an data analytics archive, in his session at @ThingsExpo, Jim Kaskade, Vice President and General Manager, Big Data & Ana...
For years, we’ve relied too heavily on individual network functions or simplistic cloud controllers. However, they are no longer enough for today’s modern cloud data center. Businesses need a comprehensive platform architecture in order to deliver a complete networking suite for IoT environment based on OpenStack. In his session at @ThingsExpo, Dhiraj Sehgal from PLUMgrid will discuss what a holistic networking solution should really entail, and how to build a complete platform that is scalable, secure, agile and automated.
We’re no longer looking to the future for the IoT wave. It’s no longer a distant dream but a reality that has arrived. It’s now time to make sure the industry is in alignment to meet the IoT growing pains – cooperate and collaborate as well as innovate. In his session at @ThingsExpo, Jim Hunter, Chief Scientist & Technology Evangelist at Greenwave Systems, will examine the key ingredients to IoT success and identify solutions to challenges the industry is facing. The deep industry expertise behind this presentation will provide attendees with a leading edge view of rapidly emerging IoT oppor...