Click here to close now.

Welcome!

.NET Authors: Greg O'Connor, Pat Romanski, Jayaram Krishnaswamy, Adine Deford, Peter Silva

News Feed Item

B2Gold Corp. Announces Robust Results from the Feasibility Study for the Otjikoto Project in Namibia

Commencement of Construction at the Otjikoto Project

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 01/10/13 -- B2Gold Corp. (TSX:BTO)(OTCQX:BGLPF)(NAMIBIAN:B2G) ("B2Gold" or the "Company") is pleased to announce robust results from the Feasibility Study ("FS") and commencement of construction at the Otjikoto gold project in Namibia. The Company also announces the acceptance of a committed letter of offer for a $150 million secured revolving corporate loan facility ("Facility"). All dollar figures are in United States dollars unless otherwise indicated.

Highlights of the Otjikoto Feasibility Study


--  Open pit gold mine with an initial life of mine ("LOM") of 12 years
    based on the probable mineral reserves 
--  Average annual gold production for years one to five of 141,000 ounces
    per year at a $524 operating cash cost per ounce 
--  Average annual gold production LOM of 112,000 ounces per year at an
    operating cash cost of $689 per ounce 
--  New probable open pit mineral reserves of 29.4 million tonnes at a grade
    of 1.42 grams per tonne ("g/t") gold containing 1.34 million ounces of
    gold at a stripping ratio of 5.59:1 
--  Average LOM gold recovery increased to 95.6% 
--  Estimated pre-production capital cost of $244.2 million 
--  Cumulative LOM net cash flow pre-tax of $659 million and after-tax of
    $413 million 
--  Net present value ("NPV") pre-tax of $402 million and after-tax of
    $243.4 million at a 5% discount rate generating an after-tax internal
    rate of return ("IRR") of 23.6% 
--  Plant and supporting infrastructure will be built to support a plant
    expansion from initial design capacity of 2.5 million tonnes per annum
    to 3.0 million tonnes per annum with minimal additional capital required
--  Recent high grade discovery indicates the potential to expand reserves
    and mill through put capacity which could facilitate an increase in
    annual gold production 
--  B2Gold Namibia has received all required government permits and licenses
    for construction 
--  Construction activities have commenced at the Otjikoto project 

Project Overview

The Otjikoto gold project is located approximately 300 kilometres north of Windhoek, the capital of Namibia, and is owned 92% by B2Gold and 8% by EVI Gold (Pty) Ltd, a Namibian black empowerment group. The property has excellent infrastructure. It is located adjacent to a major paved highway and drilling has outlined water on site well in excess of the LOM requirements.

The Otjikoto project will be developed as an open pit mine, where run-of-mine ore will be trucked to the plant, crushed, and then treated in a grinding circuit utilizing conventional SAG and ball mills, and a carbon in leach ("CIL") recovery process.

The mine plan is based on probable mineral reserves of 29.4 million tonnes at a grade of 1.42 g/t containing 1,341,000 ounces of gold at a stripping ratio of 5.59:1 to be mined over an initial 12 year period. All necessary government permits and licenses have been received. Construction has commenced and is scheduled for completion in the fourth quarter of 2014 when mill production will begin.

The current average annual production for the first five years is approximately 141,000 ounces of gold per year at an average operating cash cost of $525 per ounce and for the LOM approximately 112,000 ounces of gold per year at an average operating cash cost of $689 per ounce. The total pre-production capital costs are estimated to be $244.2 million (see pre-production capital costs table below for further details).

The plant facility and support infrastructure will be built to support a plant expansion from the initial processing capability of 2.5 million tonnes per annum to 3.0 million tonnes with minimal additional capital expenditure.

The financial modeling for the Otjikoto project indicates robust economics. At a gold price of $1,550 per ounce, the project is projected to yield a positive after-tax NPV of $243.4 million at a discount rate of 5%. The IRR after-tax is 23.6%. The project has a 32 month pay-back period after first gold production. See appendix 1 at the end of this news release for additional project assumptions and parameters.

The Otjikoto gold project has excellent exploration potential. An aggressive exploration drilling program continues on the success of the high grade Wolfshag zone discovered in late 2012, that is adjacent to the planned Otjikoto pit. These positive results indicate significant exploration upside and the potential to outline additional resources which could lead to the expansion of through-put capacity and increase annual average gold production.

A trade-off study with metallurgical testwork and economic evaluations was conducted to evaluate the optimal processing design for the Otjikoto project. Based on the findings of metallurgical testwork, the study recommended utilizing a whole ore carbon in leach ("CIL") recovery system rather than the previous concept of utilizing a flotation recovery circuit. While this change results in increased pre-construction capital costs of approximately $50 million, it significantly improves project economics by increasing gold recoveries by more than 5% over those achieved by a floatation circuit.

The Company has accepted a committed letter of offer from Macquarie Bank Limited ("Macquarie Bank") for a fully underwritten $150 million secured Facility for a four year term with a final repayment date of March 31, 2017.

B2Gold's strong financial position and anticipated future operating cash flows combined with the recently signed committed Facility term sheet are expected to provide the Company with sufficient financial resources to bring the Otjikoto project into production and fund all additional expenditures projected for 2013.

Mining, Production and Resources

The mineral reserves established for the Otjikoto project are based only on the indicated mineral resource and are therefore eligible for conversion to the Probable mineral reserve category. The mineral reserve estimate was calculated based on a gold price of $1,350 and resulted in a cut-off grade of approximately 0.4 g/t. The mineral reserve estimate is as follows:


--  Probable reserve of 29.4 million tonnes at a grade of 1.42 g/t gold
    containing 1.34 million ounces of gold at a stripping ratio of 5.59:1
    derived from the ultimate pit. The reserve is summarized in the table
    below 

--  These mineral reserves have been generated in accordance with the
    guidelines developed by the National Instrument 43-101 

------------------------------------------------------------
                                                    Otjikoto
                                    Unit            Reserves
------------------------------------------------------------
Total Ore                         Tonnes          29,408,899
------------------------------------------------------------
Total Waste                       Tonnes         164,266,045
------------------------------------------------------------
Stripping Ratio              Waste / Ore                5.59
------------------------------------------------------------
Ore Grade                            g/t                1.42
------------------------------------------------------------
Gold Content                      Ounces           1,341,292
------------------------------------------------------------
Gold Produced                     Ounces           1,281,013
------------------------------------------------------------

--  Quality assurance and quality control procedures include the systematic
    insertion of blanks, standards and duplicates into the rock sample
    strings. The primary laboratory for Otjikoto is ALS Minerals in
    Vancouver. Samples are prepared at Intertek Genalysis, Walvis Bay.
    Bureau Vertitas, Swakopmund, Namibia, is the umpire laboratory. All
    results stated in this announcement have passed B2Gold's quality
    assurance and quality control ("QA/QC") protocols. Tom Garagan is
    B2Gold's Qualified Person as defined under National Instrument 43-101 

An elevated cut-off strategy was used to increase production in the early years, shorten the payback period and improve overall project economics. An ore grade of 0.6 g/t gold was applied in the production schedule which leads to a projected 6.5 million tonne low grade stockpile for ore with a grade ranging from 0.4 g/t gold to 0.6 g/t gold. The low grade ore stockpile will be processed primarily during the last two years of the mine life.

The mineral resource at the Otjikoto project at a 0.4 g/t gold cut-off within a $1,350 per ounce optimized pit is:


            --------------------------------------------------------------
                      INDICATED                       INFERRED            
------------------------------------------ -------------------------------
                Tonnes    Gold      Ounces      Tonnes    Gold      Ounces
Weathering  (thousands)   (g/t) (thousands) (thousands)   (g/t) (thousands)
--------------------------------------------------------------------------
Ox/Trans         3,049    1.31         129          93    0.78           2
--------------------------------------------------------------------------
Sulphide        25,899    1.53       1,276          55    1.83           3
--------------------------------------------------------------------------
Total           28,949    1.51       1,405         149    1.17           6
--------------------------------------------------------------------------

--  Quality assurance and quality control procedures include the systematic
    insertion of blanks, standards and duplicates into the rock sample
    strings. The primary laboratory for Otjikoto is ALS Minerals in
    Vancouver. Samples are prepared at Intertek Genalysis, Walvis Bay.
    Bureau Vertitas, Swakopmund, Namibia, is the umpire laboratory. All
    results stated in this announcement have passed B2Gold's quality
    assurance and quality control ("QA/QC") protocols. Tom Garagan is
    B2Gold's Qualified Person as defined under National Instrument 43-101 
--  Mineral resources do not include material from the recently discovered
    Wolfshag zone 
--  Mineral resources are inclusive of probable mineral reserves 

Process and Metallurgy

As part of the FS, an extensive testwork programme was undertaken in order to establish the process design parameters, formulate the process flowsheet and evaluate ore variability.

Based on the findings of this testwork programme the process plant design parameters were determined. The design basis of the selected process is based on a whole ore leach flowsheet at a nominal treatment rate of 2.5 million tonnes per annum and a 25% design factor on the crusher, conveyors, mills, mainstream pumps and piping, cyanide destruction circuit and thickeners to allow for a possible future expansion to 3.0 million tonnes per annum with minimal additional capital expenditure. The process plant and design as detailed in the FS is based on the recovery of gold by gravity concentration followed by an intensive leach circuit, and a cyanide leach process for gold recovery from gravity tailings.

Run-of-Mine ore from the open pit operations will be delivered by 100 tonne trucks to the primary crusher. The ore will be fed to a crushing plant which consists of a gyratory crusher and conveyor system that feeds the coarse ore stockpile. Material will be reclaimed from the stockpile and treated in a grinding circuit which is comprised of a primary SAG mil and a secondary ball mill. The entire ball mill discharge stream will be treated in a gravity concentration circuit for recovery of coarse gold. The gravity concentrate will be processed in an intensive leach circuit.

The gravity tailings product is thickened to 45% solids and treated in a cyanide leach circuit. The leach product stream is pumped to a carbon in pulp ("CIP") circuit for recovery of gold in solution. The tailings stream from the CIP circuit is treated in a cyanide destruction circuit using the SO2/Air process, before being pumped to a lined tailing storage facility.

Gold is recovered from the CIP circuit loaded carbon in a split AARL elution circuit. Gold solutions from the gravity intensive leach circuit and elution circuit are treated in an electrowinning process followed by smelting to produce Dore bars. Final recoveries of gold are projected at 95.6%.

Mine Operating Cash Cost

Operating cash costs are expected to average $524 per ounce of gold for the first five years of the project and $689 per ounce of gold over the 12 year LOM. The expected average site operating cash cost is $33.21 per tonne processed. The operating cost estimate was prepared by B2Gold and engineering contractors supporting the feasibility study and is based on actual or estimated supply costs, actual and estimated logistics costs, engineered productivity / production rates, and equipment operating and maintenance costs from other operating mines and equipment manufacturers.

Pre-Production Capital Cost Estimates

The requirement of the FS was to produce a capital estimate accurate to +/- 10%. The estimate is base dated December 2012. The capital costs for the project are summarized in the table below.

The pre-production capital cost estimate for the Otjikoto project's processing plant and infrastructure was compiled by the project management team supported by the primary feasibility consultant, DRA Mineral Projects Ltd, and other FS engineering contractors that contributed significantly to the capital cost estimate form and basis. DRA Mineral Projects Ltd provided the plant process and infrastructure capital costs. VBKOM Consulting Engineers Namibia provided the form and basis for the surface mining capital costs inclusive of the mining equipment and mine development costs. Epoch Resources (Pty) Ltd provided the designs and quantities for the tailing pond cost estimates.

The total pre-production capital costs are estimated to be $244.2 million, which includes working capital for supplies, taxes and owners costs.


-------------------------------------------------------
Pre-Production Capital Costs                 $ millions
-------------------------------------------------------
Earthworks                                         14.2
-------------------------------------------------------
Tailings Storage Facility                          25.3
-------------------------------------------------------
Process Plant                                     106.3
-------------------------------------------------------
Electrical & Power Generation                          
 (leased)                                           8.4
-------------------------------------------------------
Mining Equipment (leased)                          18.0
-------------------------------------------------------
Construction Equipment                              2.7
-------------------------------------------------------
Mine Infrastructure, Mine                              
 Buildings                                          7.1
-------------------------------------------------------
Buildings, Ancillary                                   
 Facilities                                         7.6
-------------------------------------------------------
Owners Costs - Other                               19.8
-------------------------------------------------------
Mechanical & Electrical Spares                      3.3
-------------------------------------------------------
Owners Construction Management                      2.4
-------------------------------------------------------
EPCM                                               13.6
-------------------------------------------------------
Contingency                                        15.5
-------------------------------------------------------
Total                                             244.2
-------------------------------------------------------

A trade-off study with metallurgical testwork and economic evaluations were conducted to evaluate the optimal processing design for the Otjikoto project. Based on the findings of metallurgical testwork, the study recommended utilizing a whole ore carbon in leach ("CIL") recovery system rather than the previous concept of utilizing a flotation recovery circuit. While this change results in increased pre-construction capital costs of approximately $50 million, as outlined above, it significantly improves project economics by increasing gold recoveries by more than 5% above recoveries achievable by a floatation circuit.

In addition, in order to attain higher gold production in the initial years of production and optimize project economics, the Company plans to expend approximately $33 million on extensive pre-production waste stripping and ore stockpiling during construction.

Corporate Social Responsibility ("CSR")

B2Gold's CSR is a key aspect of every project and B2Gold Namibia has worked closely with communities around the Otjikoto project area to develop a CSR program that benefits all stakeholders. Through a transparent mechanism, B2Gold Namibia is supporting community driven projects in public health, education, development of small to medium enterprises and environmental conservation. Projects included scholarships to historically disadvantaged students, support to the Namibian Institute of Mining and Technology, a partnership with the Cheetah Conservation Foundation to monitor and protect endangered species, identification of potential small to medium enterprises within the communities where our workers live, support of educational needs with the Ministry of Education, support of programs that help at risk teens, and providing equipment and facilities to support local medical needs.

Sensitivity Analysis

The Otjikoto project sensitivity analysis was performed on the following parameters with summary returns as indicated in the following table. The project shows normal sensitivities, but none of the negative modifications cause returns to modify the robust project financial analysis.


---------------------------------------------------------------------------
Parameter                           Low       Feasibility              High
---------------------------------------------------------------------------
Cumulative net cash                                                        
 flow (pre-tax)          $403.0 million    $658.8 million    $914.7 million
Gold Price             $1,350 per ounce  $1,550 per ounce  $1,750 per ounce
---------------------------------------------------------------------------
Cumulative net cash                                                        
 flow (pre-tax)          $694.7 million    $658.8 million    $623.0 million
Diesel Fuel ($ per                                                         
 litre)               $0.7925 per litre $1.0565 per litre $1.3206 per litre
---------------------------------------------------------------------------
Cumulative net cash                                                        
 flow (pre-tax)          $706.9 million    $658.8 million    $610.8 million
HFO - Heavy Fuel Oil                                                       
 ($ per liter)        $0.5903 per litre $0.7881 per litre $0.9838 per litre
---------------------------------------------------------------------------
Cumulative net cash                                                        
 flow (pre-tax)          $539.2 million    $658.8 million    $756.7 million
Exchange rate                                                              
 (NAD/USD)                   7.6500 / 1        8.5000 / 1        9.3500 / 1
---------------------------------------------------------------------------
Cumulative net cash                                                        
 flow (pre-tax)          $685.4 million    $658.8 million    $632.3 million
National labor                     -25%           Current               25%
---------------------------------------------------------------------------

Project Implementation

The Otjikoto project execution plan encompasses project management by B2Gold and utilizes a delivery method comprised of a combination of Engineering, Procurement, and Construction combined with multiple prime engineering contracts and some self-performed owner construction.

Engineering and procurement will be managed from the B2Gold corporate offices in Vancouver, British Columbia, Canada with construction management occurring from the Otjikoto project site. The majority of equipment and supplies will be sourced from South Africa, North America or European suppliers and will be ocean shipped to the seaport at Walvis Bay, Namibia, with subsequent overland delivery utilizing contracted commercial trucking firms.

The site development will take place year round, utilizing a work force of experienced Namibian nationals, trained and supervised by Namibian and expatriate supervision. Many of the expatriate supervisors have worked on previous successful projects associated with B2Gold and Bema Gold Corporation.

Logistics will be supported from the existing B2Gold support structure in place and operating in Namibia. Construction activities have commenced. The mills and primary crusher were ordered in December 2012. The grinding mills, crushing equipment and the construction man camp have been secured and partial payment has been made and they are undergoing fabrication and shipping. The generators will be procured in February 2013. The process plant is expected to be ready to receive ore in the fourth quarter of 2014.

Committed Letter of Offer for a $150 Million Revolving Corporate Credit Facility

B2Gold is pleased to announce that it has accepted a committed letter of offer from Macquarie Bank for a fully underwritten $150 million secured Facility. Macquarie Bank is the Sole Underwriter and the Facility Agent. The syndicate will include HSBC Securities (USA) Inc. as a Lead Arranger and HSBC Bank USA, National Association has committed to fund $50 million of the Facility.

The Facility comprises three tranches of $50 million each for a total of $150 million and replaces the existing $25 million revolving credit facility with Macquarie Bank. Drawdowns are subject to the completion of loan documentation and satisfaction of certain conditions precedent. Drawdowns in excess of $50 million required the completion of a FS for the Otjikoto gold project in Namibia, which has now been completed.

The term of the Facility will be for a period of four years with a final repayment date of March 31, 2017 and the Facility has an interest rate of LIBOR plus a margin of 3.5%. The Facility will be used to fund construction and development costs related to the Otjikoto gold project in Namibia and for general corporate purposes.

In Conclusion

The Company's Board of Directors has accepted the Otjikoto gold project's feasibility study and has instructed management to implement the study's recommendations to develop and bring the Otjikoto gold project to commercial production. B2Gold's strong financial position and anticipated future operating cash flows, combined with the recently signed committed Facility term sheet, are expected to provide the Company with sufficient financial resources to bring the Otjikoto project into production and fund all additional expenditures projected for 2013.

With our proven technical team, strong operational performance, financial strength and high quality development and exploration projects, B2Gold is well positioned to continue our rapid growth as an intermediate gold producer from existing projects.

Qualified Persons for Feasibility Study (1)

ON BEHALF OF B2GOLD CORP.

Clive T. Johnson, President and Chief Executive Officer

(1) Qualified Persons for Feasibility Study

Specialist consultants were engaged by B2Gold to undertake the design of the mine pit, processing plant, and the tailings disposal facility. This work was carried out the following specialist consultants:


-  DRA Mineral Projects (Pty) Ltd  Val Coetzee - Lead Process Engineer -  
   (S. Africa)                     Pr. Eng, M Eng - Mill and              
                                   Infrastructure                         
-  VBKom - Mining Engineers        Werner Moeller - Mining Engineer - B   
   (Namibia)                       Eng (Mining); B Eng. (Hon) (Ind. Eng.) -
                                   Mining                               
                                   Manie Kriel - Senior Mining Engineer - 
                                   Pr. Eng, B. Eng (Mining), MBL, CP -    
                                   Resource reserve conversion            
-  Epoch Resources (Pty) Ltd (S.   George Papageorgiou - Director -  
   Africa)                         Pr. Eng, Phd, M Eng (civil) - Tailings 
-  SLR (Pty) Ltd (Namibia)         Werner Petrick - Environmental         
                                   Assessment Practitioner - BEng Civil   
                                   MEM (Masters Environmental Management) 
                                   Alexandra Speiser - Environmental      
                                   Specialist - MSc. Geology, MPhil       
                                   Environmental Management- Environmental
                                   Arnold Bitner - Groundwater Specialist -
                                   MSc (Geology) Hydrology, Geohydrology
-  SRK (SA) (Pty) Ltd              Alan Naismith - Partner and Principal  
                                   Rock Engineer - Pr. Eng, M Eng         
                                   (Geological Eng.) - Geotechnical       
                                   Assessment                             
-  AGES (Pty) Ltd (S. Africa)      Koos Vivier - Senior Geohydrologist -  
                                   Pr. Sci Nat, M.Sc Geohydrology         
                                   Geochemical and groundwater modeling   
-  Ashby & Associates              Auriol Ashby - Socio-Economist - 
                                   BSc (Hons) Environmental Sciences,     
                                   Certificate in Education (UK) -        
                                   Stakeholder Engagement and Corporate   
                                   Social Responsibility implementation   

Quality assurance and quality control procedures include the systematic insertion of blanks, standards and duplicates into the rock sample strings. The primary laboratory for Otjikoto is ALS Minerals in Vancouver where samples are analysed by fire assay / gravimetric finish using one assay tonne. Samples are prepared at Intertek Genalysis, Walvis Bay. Bureau Vertitas, Swakopmund, Namibia, is the umpire laboratory. All results stated in this announcement have passed B2Gold's quality assurance and quality control ("QA/QC") protocols. Tom Garagan is B2Gold's Qualified Person as defined under National Instrument 43-101.

A National Instrument 43-101 compliant Technical Report will be filed on the Company's website and on SEDAR within 45 days.

Cautionary Statements on Forward-Looking Information: Statements in this news release are forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of Canadian securities laws (collectively "forward-looking statements"). All statements, other than statements of historical fact, are forward-looking statements. Generally, forward-looking statements can be identified by the use of words or phrases such as; "expects", "anticipates", "plans", projects", "estimates", "assumes", "intends", " "objectives", "potential" or variations thereof, or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms or similar expressions. These forward-looking statements are subject to a variety of known and unknown risks, uncertainties and other factors that could cause actual events or results to differ from those expressed or implied, including, without limitation, risks relating to: changes in economic conditions or financial markets; changes in prices for the Company's mineral products or increases in input costs; uncertainty of production and cost estimates for the Otjikoto Project; risks and uncertainties associated with new mining operations including start-up delays and operational issues; litigation, legislative, tax (including employee profit sharing arrangements), environmental and other judicial, regulatory, political and competitive developments in Canada, Namibia and other jurisdictions in which the Company may carry on business; labour relations matters; and foreign exchange rate fluctuations, as well as other factors described in the Company's most recent annual information form filed with Canadian regulatory authorities.

This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements. The Company's forward-looking statements are based on what the Company's management considers to be reasonable assumptions, beliefs, expectations and opinions based on information currently available to management. We cannot assure you that actual events, performance or results will be consistent with these forward looking statements, and management's assumptions may prove to be incorrect. You are cautioned that the foregoing list is not exhaustive of all factors and assumptions which may have been used. The Company's forward looking statements reflect current expectations regarding future events and operating performance and speak only as of the date hereof and the Company does not assume any obligation to update forward-looking statements if circumstances or management's beliefs, expectations or opinions should change other than as required by applicable law. For the reasons set forth above, you should not place undue reliance on forward-looking statements.


Appendix 1                                                                
                                                                          
Project Assumptions and Parameters                                        
                                                                          
Gold Price ($per ounce)                                     1,550         
Silver Price ($per ounce)                                   30            
Diesel Fuel ($per litre)                                    1.056         
Heavy Fuel Oil (HFO) ($per litre)                           0.787         
                                                                          
Namibian Dollar to US Dollar (NAD/USD)                      8.50          
                                                                          
Minerals Act Royalty (%)                                    3.0           
Corporate Income Tax (%)                                    37.5          
                                                                          
Project Statistics for the Minable Reserves                               
                                                                          
Mine Life (years)                                           12            
Average Strip Ratio (waste : ore tonnes)                    5.59:1        
Average Gold Grade (g/t)                                    1.42          
Total Contained Gold (million ounces)                       1.34          
Estimated Gold Recovery (%)                                 95.6          
Total Recovered Gold (million ounces)                       1.28          
                                                                          
Average annual gold production (first five years) (ounces)  141,000       
Average annual gold production (LOM) (ounces)               112,000       
                                                                          
Costs                                                                     
                                                                          
Pre-Production Capital Cost ($million)                      244.2         
Sustaining and Mine Closure Capital ($million)              107.4         
Average Operating Cash Cost (1st five years) ($per ounce                  
 of gold produced)                                          524           
Average Operating Cash Cost (LOM) ($per ounce of gold                     
 produced)                                                  689           
Average Total Cash Cost (1st five years) ($per ounce of                   
 gold produced)                                             570           
Average Total Cash Cost (LOM) ($per ounce of gold                         
 produced)                                                  736           
                                                                          
Financial Analysis                                                        
                                                                          
Cumulative Cash Flow (pre-tax) (LOM) ($million)             659           
Cumulative Cash Flow (post-tax) (LOM) ($million)            413           
NPV (pre-tax at 5% discount) ($million)                     402           
NPV (post-tax at 5% discount) ($million)                    243           
IRR (pre-tax) (%)                                           30.4          
IRR (post-tax) (%)                                          23.6          
Payback Period (post-tax) (months)                          32            

The Toronto Stock Exchange neither approves nor disapproves the information contained in this News Release.

Contacts:
B2Gold Corp.
Ian MacLean
Vice President, Investor Relations
604-681-8371

B2Gold Corp.
Kerry Suffolk
Manager, Investor Relations
604-681-8371
www.b2gold.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
SOA Software has changed its name to Akana. With roots in Web Services and SOA Governance, Akana has established itself as a leader in API Management and is expanding into cloud integration as an alternative to the traditional heavyweight enterprise service bus (ESB). The company recently announced that it achieved more than 90% year-over-year growth. As Akana, the company now addresses the evolution and diversification of SOA, unifying security, management, and DevOps across SOA, APIs, microservices, and more.
GENBAND has announced that SageNet is leveraging the Nuvia platform to deliver Unified Communications as a Service (UCaaS) to its large base of retail and enterprise customers. Nuvia’s cloud-based solution provides SageNet’s customers with a full suite of business communications and collaboration tools. Two large national SageNet retail customers have recently signed up to deploy the Nuvia platform and the company will continue to sell the service to new and existing customers. Nuvia’s capabilities include HD voice, video, multimedia messaging, mobility, conferencing, Web collaboration, deskt...
SYS-CON Media announced today that @WebRTCSummit Blog, the largest WebRTC resource in the world, has been launched. @WebRTCSummit Blog offers top articles, news stories, and blog posts from the world's well-known experts and guarantees better exposure for its authors than any other publication. @WebRTCSummit Blog can be bookmarked ▸ Here @WebRTCSummit conference site can be bookmarked ▸ Here
SYS-CON Events announced today that Cisco, the worldwide leader in IT that transforms how people connect, communicate and collaborate, has been named “Gold Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Cisco makes amazing things happen by connecting the unconnected. Cisco has shaped the future of the Internet by becoming the worldwide leader in transforming how people connect, communicate and collaborate. Cisco and our partners are building the platform for the Internet of Everything by connecting the...
Temasys has announced senior management additions to its team. Joining are David Holloway as Vice President of Commercial and Nadine Yap as Vice President of Product. Over the past 12 months Temasys has doubled in size as it adds new customers and expands the development of its Skylink platform. Skylink leads the charge to move WebRTC, traditionally seen as a desktop, browser based technology, to become a ubiquitous web communications technology on web and mobile, as well as Internet of Things compatible devices.
SYS-CON Events announced today that robomq.io will exhibit at SYS-CON's @ThingsExpo, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. robomq.io is an interoperable and composable platform that connects any device to any application. It helps systems integrators and the solution providers build new and innovative products and service for industries requiring monitoring or intelligence from devices and sensors.
The WebRTC Summit 2014 New York, to be held June 9-11, 2015, at the Javits Center in New York, NY, announces that its Call for Papers is open. Topics include all aspects of improving IT delivery by eliminating waste through automated business models leveraging cloud technologies. WebRTC Summit is co-located with 16th International Cloud Expo, @ThingsExpo, Big Data Expo, and DevOps Summit.
Docker is an excellent platform for organizations interested in running microservices. It offers portability and consistency between development and production environments, quick provisioning times, and a simple way to isolate services. In his session at DevOps Summit at 16th Cloud Expo, Shannon Williams, co-founder of Rancher Labs, will walk through these and other benefits of using Docker to run microservices, and provide an overview of RancherOS, a minimalist distribution of Linux designed expressly to run Docker. He will also discuss Rancher, an orchestration and service discovery platf...
Wearable technology was dominant at this year’s International Consumer Electronics Show (CES) , and MWC was no exception to this trend. New versions of favorites, such as the Samsung Gear (three new products were released: the Gear 2, the Gear 2 Neo and the Gear Fit), shared the limelight with new wearables like Pebble Time Steel (the new premium version of the company’s previously released smartwatch) and the LG Watch Urbane. The most dramatic difference at MWC was an emphasis on presenting wearables as fashion accessories and moving away from the original clunky technology associated with t...
SYS-CON Events announced today that Vitria Technology, Inc. will exhibit at SYS-CON’s @ThingsExpo, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Vitria will showcase the company’s new IoT Analytics Platform through live demonstrations at booth #330. Vitria’s IoT Analytics Platform, fully integrated and powered by an operational intelligence engine, enables customers to rapidly build and operationalize advanced analytics to deliver timely business outcomes for use cases across the industrial, enterprise, and consumer segments.
SYS-CON Events announced today that Solgenia will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY, and the 17th International Cloud Expo®, which will take place on November 3–5, 2015, at the Santa Clara Convention Center in Santa Clara, CA. Solgenia is the global market leader in Cloud Collaboration and Cloud Infrastructure software solutions. Designed to “Bridge the Gap” between Personal and Professional Social, Mobile and Cloud user experiences, our solutions help large and medium-sized organizations dr...
SYS-CON Events announced today that Liaison Technologies, a leading provider of data management and integration cloud services and solutions, has been named "Silver Sponsor" of SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York, NY. Liaison Technologies is a recognized market leader in providing cloud-enabled data integration and data management solutions to break down complex information barriers, enabling enterprises to make smarter decisions, faster.
@ThingsExpo has been named the Top 5 Most Influential M2M Brand by Onalytica in the ‘Machine to Machine: Top 100 Influencers and Brands.' Onalytica analyzed the online debate on M2M by looking at over 85,000 tweets to provide the most influential individuals and brands that drive the discussion. According to Onalytica the "analysis showed a very engaged community with a lot of interactive tweets. The M2M discussion seems to be more fragmented and driven by some of the major brands present in the M2M space. This really allows some room for influential individuals to create more high value inter...
After making a doctor’s appointment via your mobile device, you receive a calendar invite. The day of your appointment, you get a reminder with the doctor’s location and contact information. As you enter the doctor’s exam room, the medical team is equipped with the latest tablet containing your medical history – he or she makes real time updates to your medical file. At the end of your visit, you receive an electronic prescription to your preferred pharmacy and can schedule your next appointment.
The world's leading Cloud event, Cloud Expo has launched Microservices Journal on the SYS-CON.com portal, featuring over 19,000 original articles, news stories, features, and blog entries. DevOps Journal is focused on this critical enterprise IT topic in the world of cloud computing. Microservices Journal offers top articles, news stories, and blog posts from the world's well-known experts and guarantees better exposure for its authors than any other publication. Follow new article posts on Twitter at @MicroservicesE
The list of ‘new paradigm’ technologies that now surrounds us appears to be at an all time high. From cloud computing and Big Data analytics to Bring Your Own Device (BYOD) and the Internet of Things (IoT), today we have to deal with what the industry likes to call ‘paradigm shifts’ at every level of IT. This is disruption; of course, we understand that – change is almost always disruptive.
SYS-CON Events announced today the IoT Bootcamp – Jumpstart Your IoT Strategy, being held June 9–10, 2015, in conjunction with 16th Cloud Expo and Internet of @ThingsExpo at the Javits Center in New York City. This is your chance to jumpstart your IoT strategy. Combined with real-world scenarios and use cases, the IoT Bootcamp is not just based on presentations but includes hands-on demos and walkthroughs. We will introduce you to a variety of Do-It-Yourself IoT platforms including Arduino, Raspberry Pi, BeagleBone, Spark and Intel Edison. You will also get an overview of cloud technologies s...
SYS-CON Events announced today that SafeLogic has been named “Bag Sponsor” of SYS-CON's 16th International Cloud Expo® New York, which will take place June 9-11, 2015, at the Javits Center in New York City, NY. SafeLogic provides security products for applications in mobile and server/appliance environments. SafeLogic’s flagship product CryptoComply is a FIPS 140-2 validated cryptographic engine designed to secure data on servers, workstations, appliances, mobile devices, and in the Cloud.
SYS-CON Events announced today that Akana, formerly SOA Software, has been named “Bronze Sponsor” of SYS-CON's 16th International Cloud Expo® New York, which will take place June 9-11, 2015, at the Javits Center in New York City, NY. Akana’s comprehensive suite of API Management, API Security, Integrated SOA Governance, and Cloud Integration solutions helps businesses accelerate digital transformation by securely extending their reach across multiple channels – mobile, cloud and Internet of Things. Akana enables enterprises to share data as APIs, connect and integrate applications, drive part...
Cloud is not a commodity. And no matter what you call it, computing doesn’t come out of the sky. It comes from physical hardware inside brick and mortar facilities connected by hundreds of miles of networking cable. And no two clouds are built the same way. SoftLayer gives you the highest performing cloud infrastructure available. One platform that takes data centers around the world that are full of the widest range of cloud computing options, and then integrates and automates everything. Join SoftLayer on June 9 at 16th Cloud Expo to learn about IBM Cloud's SoftLayer platform, explore se...