Click here to close now.

Welcome!

.NET Authors: Dana Gardner, Pat Romanski, Andreas Grabner, Elizabeth White, Tad Anderson

News Feed Item

Chieftain Prepares to Publish Feasibility Study in January 2013

TORONTO, ONTARIO -- (Marketwire) -- 12/21/12 -- Chieftain Metals Inc. ("Chieftain" or the "Company") (TSX: CFB) is pleased to announce its preparation to publish its full feasibility study results completed by JDS Energy and Mining Inc. in January 2013. As part of this process, it has revised the payback period of the feasibility study on a pre-tax and post-tax basis to 4.3 years (instead of 3.9 and 4.4 years respectively), the post-tax IRR to 14.7% (instead of 14.9%). Accordingly, the post-tax NPV 8% is $138.7 million (instead of $146.0 million). The pre-tax NPV8% and pre-tax IRR remain unchanged at $192.7 million and 16.5% respectively.

After publication of the feasibility study, the Company will continue its optimization work in the areas of improving its copper concentrates, examining further infrastructure and materials handling improvements, resource optimization and exploration potential to its Tulsequah Chief project. The Company expects to embark on partner and project finance discussions early in the New Year to arrange construction financing.

Gordon Doerksen of JDS Energy & Mining Inc., a Qualified Person under NI 43-101, has reviewed and approved the technical content of this news release.

The news release published on December 12, 2012, at 8:15 a.m. EST entitled "Chieftain Announces Robust Tulsequah Chief Feasibility Study Results" is shown below in its entirety reflecting the above-mentioned changes:

Chieftain Announces Robust Tulsequah Chief Feasibility Study Results

TORONTO, ONTARIO--(Marketwire - Dec. 12, 2012) - Chieftain Metals Inc. ("Chieftain" or the "Company") (TSX:CFB) is pleased to announce that JDS Energy and Mining Inc. has led the completion of an independent, NI 43-101 compliant Feasibility Study on the high-grade Tulsequah Chief polymetallic deposit located in north-western British Columbia.

Highlights of the Tulsequah Chief Feasibility (Table 1)


--  The study is based on a 2,000 tonne per day underground mining operation
    with a 9-year mine life. 
--  Pre-production capital costs are estimated to total $439.5 million, with
    an additional $64.0 million in sustaining capital over the life-of-mine
    and closure costs net of salvage value of $6.2 million (all amounts in
    Canadian dollars unless stated otherwise). 
--  Operating costs are estimated to total $125.96/tonne. 
--  Price deck for metals and foreign exchange is based on the three year
    trailing average prices. 
--  The study yields a pre-tax NPV8% of $192.7 million and an IRR of 16.5%
    and post-tax NPV8% of $138.7 million and an IRR of 14.7%. 

Victor Wyprysky, President and CEO commented: "We are pleased to deliver a feasibility study demonstrating robust economics for Tulsequah. The NPV8% of $192.7 million represents a pre-tax Net Asset Value of approximately $13.24 per share and average annual EBITDA at full production of $120.4 million or $8.28 per share based on the current outstanding shares. This study will enable Chieftain to finalize project financing and plan construction start-up. The project will bring significant benefits for the Taku River First Nation, the Atlin community and British Columbia, and Chieftain is fully committed to continue to build strong relationships with the community while developing the project in a socially and environmentally responsible manner within the guidelines of the Atlin-Taku Land Use Plan."


----------------------------------------------------------------------------
Table 1.Highlights of the Tulsequah Chief Feasibility Study                 
                                                                            
----------------------------------------------------------------------------
                                            Payable Metal   Metal Pricing(1)
                                     ---------------------------------------
Probable Reserve              6.45 Mt                                       
                                                                            
                       Au    2.30 g/t          403.9 k oz       US$ 1,455/oz
                       Ag   81.38 g/t       11,971.8 k oz       US$ 28.00/oz
                       Zn       5.59%         601.5 M lbs        US$ 0.97/lb
                       Cu       1.12%         135.5 M lbs        US$ 3.66/lb
                       Pb       1.04%          93.0 M lbs        US$ 1.01/lb
            Exchange Rate                                       1.01 CDN:USD
----------------------------------------------------------------------------
Mining rate              2,000 t/d   NSR                          $ 265.71/t
Mine life                9 years                                            
Initial Capex            $ 439.5 M   Operating cost                         
Sustaining Capex         $ 64.0 M     - Site                       $ 98.13/t
Closure Costs net of                                                        
Salvage Value            $ 6.2 M      - Off-site                   $ 27.83/t
                                                    Total         $ 125.96/t
----------------------------------------------------------------------------
                                                  Pre-Tax           Post-Tax
----------------------------------------------------------------------------
Undiscounted Net Cash                                                       
Flow                                            $ 570.7 M          $ 451.1 M
NPV (8%)                                        $ 192.7 M          $ 138.7 M
IRR                                                 16.5%              14.7%
Payback period                                  4.3 years          4.3 years
----------------------------------------------------------------------------
1. Three-year trailing average prices in US dollars.                        

Resources and Reserves

The mineral resource estimate (Table 2) was updated and classified using logic consistent with the Canadian Institute of Mining and Metallurgy ("CIM") definitions referred to in National Instrument 43-101 into Measured, Indicated, and Inferred Mineral Resources. The mineral resource estimate was developed using industry-accepted methods with GEMS software in blocks sized 5 m x 5 m x 4 m. For the purpose of resource estimation, all assay intervals within the mineralized units were composited to two metres and grades were capped prior to estimation. Zinc was capped at 30%, lead and copper at 10%, gold at 25 g/t and silver at 600 g/t for the resource estimate.


Table 2. Tulsequah Chief Mineral Resources (Inclusive of Mineral Reserves) 
 as of March 15, 2012                                                      
                                                                           
---------------------------------------------------------------------------
Category           Tonnes    Cu (%)    Pb (%)    Zn (%)  Au (g/t)  Ag (g/t)
---------------------------------------------------------------------------
Indicated          6.75Mt      1.19      1.10      5.89      2.40        85
---------------------------------------------------------------------------
Inferred           0.20Mt      0.67      0.76      4.02      1.81        62
---------------------------------------------------------------------------

1.  $100/tonne Equivalent cut-off used 
2.  Cut-off grades are based on a price of US$1,275 per ounce of gold, US$21
    per ounce for silver, US$1.10 per pound for zinc and lead and US$3.25
    for copper and recoveries of 81.8% for gold, 79.5% for silver, 87.8% for
    copper, 44.5% for lead and 88% for zinc. 
3.  Qualified Person for resource estimate is Gilles Arseneau, P.Geo. of SRK
    Consulting (Canada) Inc. 
4.  The Resources are inclusive of the Mineral Reserves stated in Table 3. 

The reserve estimate is summarized in Table 3 below. The probable reserve totals 6.45 Mt of minable material.

Table 3. Tulsequah Chief Mineral Reserves


---------------------------------------------------------------------------
Category           Tonnes    Cu (%)    Pb (%)    Zn (%)  Au (g/t)  Ag (g/t)
---------------------------------------------------------------------------
Probable           6.45Mt      1.12      1.04      5.59      2.30     81.38
---------------------------------------------------------------------------

1.  Mineral reserves are reported based on underground mining above a
    US$125/tonne Equivalent cut-off. Cut-off grades are based on a price of
    US$1,350 per ounce of gold, US$22 per ounce for silver, US$1.10 per
    pound for zinc and lead and US$3.10 for copper and recoveries of 81.8%
    for gold, 79.5% for silver, 87.8% for copper, 44.5% for lead and 88% for
    zinc. 

The Underground Mine

A new underground mine, adjacent to and beneath old workings that were previously operated by Cominco Ltd. from 1951-57, will be developed through the existing 5200 and 5400 Level adits and will be used as the primary access to the mine for all personnel, mine services, equipment and supplies.

The new mine will operate as a ramp-entry truck haulage operation via a spiral ramp that will be developed to a vertical depth of 750 meters with mining levels located at 30-meter vertical intervals. Sub-level stoping will be the primary mining method with a minor amount of mechanized cut-and-fill stoping. Paste backfill and unconsolidated loose waste rock will be used for replacement of mined voids for both methods. Where backfill walls will be exposed by future adjacent mining, additional cement will be added to the paste backfill for strength.

Metallurgy

A process plant was designed for the Tulsequah Chief project to process massive sulphide mineralization at a rate of 2000 t/d. The process facility will consist of a primary crushing plant, conveyor corridors; mill feed storage bin, grinding and flotation plant, effluent treatment plant and backfill plant. The process plant will operate two shifts per day and 365 days per year with an overall availability of 92%. The process plant will produce copper, lead and zinc concentrates and gold-silver dore as outlined in the following table predicted metallurgical response.

Table 4. Predicted Metallurgical Response


----------------------------------------------------------------------------
Product       Wt (t)            Assays                    Recoveries %      
                    --------------------------------------------------------
                     Cu % Pb % Zn % Ag g/t  Au g/t    Cu   Pb   Zn   Ag   Au
----------------------------------------------------------------------------
Copper Conc      5.3 21.0  2.7  7.6 1217.5    20.8  89.0 11.8  6.0 75.0 44.0
----------------------------------------------------------------------------
Lead Conc        1.3  1.0 60.0  8.4  586.4     7.6   0.8 66.2  1.6  9.0  4.0
----------------------------------------------------------------------------
Zinc Conc        9.6  0.7  0.8 62.0   69.7     0.8   5.5  6.8 89.0  7.8  3.0
----------------------------------------------------------------------------
Pyrite Conc       28  0.1  0.3  0.4   19.2     0.5   1.9  6.8  1.7  6.1  5.0
----------------------------------------------------------------------------
Tailings        55.7  0.1  0.2  0.2    2.4     0.1   2.8  8.4  1.7  1.6  2.0
----------------------------------------------------------------------------
Feed             100  1.3  1.2  6.7     86     2.5   100  100  100  100  100
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Dore Kg/100t                                                                
 feed          0.155                    30%     70%                 0.5 42.0
----------------------------------------------------------------------------

Access and Transportation

A new 128 kilometer long, Forestry approved 5m wide road will be constructed from the end of the Warm Bay road, south of Atlin, BC, to the Tulsequah Chief Mine site. The concentrates produced during operations are anticipated to be trucked to the Skagway terminal facility where improvements to the facility are planned to handle the storage and transfer of Chieftain's concentrates. Supplies will be transported to the mine by road utilizing the backhaul portion of the trip.

Infrastructure

All surface buildings will be located in close proximity to the mine, including the mineral process building, a 210-person camp and kitchen/dining facility, a two-story administration/mine dry building, which includes the ambulance building, an LNG/diesel-generated power plant, and the maintenance/warehouse facility for surface equipment.

The mine will operate on varying rotating schedules including four days on/three days off, two weeks on/two weeks off, and two weeks on/one week off. The schedules reflect the various work schedules required to cover the tasks on site. A 1,050 m long airstrip has been constructed approximately 2 km north of the mine near Shazah Creek.

A 3.0 Mt capacity tailings facility is designed and will be constructed approximately 5 km north of the mine in the valley of Shazah Creek. De-pyritized tailings will be transported in the form of a dense slurry by pipe.

Capital Costs

The initial capital requirement for the Project is estimated to be $439.5 M, as detailed in Table 5.

Table 5. Pre-production Capital Costs


------------------------------------------------------------
Items                                          Estimate (M$)
------------------------------------------------------------
Site Development                                         7.4
Underground Mining                                      38.5
Underground Process Facilities                          11.7
Limestone Quarry                                         0.2
Processing Plant                                        63.1
Tailings & Waste Rock Management                        15.5
On-Site Infrastructure                                  61.5
Mine Access Road (directs)                              54.2
Project Indirects                                       91.6
Engineering & EPCM                                      31.4
Owner's Costs                                           17.3
------------------------------------------------------------
Subtotal Pre-Production Capital                        392.4
------------------------------------------------------------
Contingency (12.0%)                                     47.1
------------------------------------------------------------
Total Pre-Production Capital                           439.5
------------------------------------------------------------

The Project has a total sustaining capital requirement of $64.0 million. Sustaining capital is required for extension of the main ramp to depth, mobile equipment rebuilds and replacements, and capital improvements.

Reclamation/Closure & Salvage Costs

Total reclamation/closure and salvage costs have been estimated as follows:

Table 6. Reclamation/Closure & Salvage Costs


-----------------------------------
Items                            M$
-----------------------------------
Reclamation/Closure            13.8
Salvage Value                 (7.6)
-----------------------------------

Operating Costs

Total operating costs for the Project have been estimated as follows:


Table 7. Operating Costs                     
                                             
---------------------------------------------
Items                                 $/tonne
---------------------------------------------
Mining                                  30.06
Processing                              23.02
Power                                   22.58
G&A                                     22.47
Transportation (Conc. and supplies)     27.83
---------------------------------------------
Total                                  125.96
---------------------------------------------

This cost represents the Life of Mine Cash Cost of the Project, from years 1 - 9 inclusive.

Financial Analysis and Sensitivities

Using the three year trailing average commodity prices, the study yields a pre-tax NPV8% of $192.7 million and an IRR of 16.5% with a payback period of 4.3 years and a post-tax NPV8% of $138.7 million and an IRR of 14.7% with a payback period of 4.3 years.

Sensitivity tables for changes in capital costs, operating costs, metal prices, and discount rates are shown below. The Project's NPV is most sensitive to grade, metal prices, followed by operating costs, and least sensitive to capital costs.


Table 8. Project Economics Sensitivity                          
                                                                
----------------------------------------------------------------
                Pre-tax NPV (8.0%) ($M) Average Full Production 
                                            Year EBITDA ($M)    
                ------------------------------------------------
                    -15%      0%     15%    -15%      0%     15%
----------------------------------------------------------------
Capital Cost      260.0   192.7   125.4   120.4   120.4   120.4 
Operating Cost    249.5   192.7   135.9   131.2   120.4   109.7 
Metal Prices       22.1   192.7   359.8    86.9   120.4   153.3 
----------------------------------------------------------------

Table 9. Project NPV Sensitivity to Discount Rate


------------------------------------------------------
Discount Rate     Pre-tax NPV ($M)  After-tax NPV ($M)
------------------------------------------------------
7.0%                         226.3               166.8
7.5%                         209.1               152.4
8.0%                         192.7               138.7
------------------------------------------------------

Project Schedule

Project construction is expected to commence in the Spring of 2013, subject to project financing. Site earthworks are expected to begin in Q3 2013, mill and site construction in Q4 2014, and tailings construction in Q1 2015, with commissioning and production beginning in Q4 2015.

Technical Report

A NI 43-101 Technical Report will be filed within 45 days on SEDAR and will be available at that time on the corporate website.

Qualified Persons

The technical content of this release was reviewed by Keith Boyle, P. Eng., Chief Operating Officer of Chieftain Metals Inc. and qualified person under NI 43-101.

The Feasibility Study was conducted under the overall review of Gordon Doerksen, P. Eng. of JDS Energy and Mining Inc. of Vancouver, British Columbia, and serves as Principal Author of the Technical Report.

The following Independent Qualified Persons have assumed authorship of this report:


Gordon Doerksen     P. Eng., Project Director, JDS Energy and Mining Inc.   
Gilles Arseneau     Ph.D., P. Geo. Associate Consultant, SRK Consulting     
                    (Canada) Inc.                                           
Robert Marsland     P. Eng., Senior Environmental Engineer, Marsland        
                    Environmental Associates                                
David West          P. Eng., David West Consulting                          
Harvey McLeod       P. Eng., P.Geo., Klohn Crippen Berger                   
Kenneth Sangster    C.Eng., Ken Sangster and Associates Ltd.                

About Chieftain Metals Inc.:

Chieftain Metals Inc.'s principal business is the acquisition, exploration and development of mineral properties. Since incorporation, the Company's business has focused entirely on the acquisition, and thereafter the development, of the Tulsequah Chief Polymetallic Project, in north-western British Columbia, Canada. Chieftain's Property consists of 39 mineral claims and Crown-grants covering approximately 14,089 hectares and covers two previously producing mines. For more information on Tulsequah and related projects, please refer to the Company's NI 43-101 compliant technical reports, "Tulsequah Chief Deposit, Tulsequah Chief Property, Northern British Columbia" and "Big Bull Project, Tulsequah Chief Property, Technical Report, Northern British Columbia", each dated as of November 8, 2010 and available under the Company's profile on SEDAR (www.sedar.com).

Forward-Looking Information:

This press release includes certain "forward-looking statements" within the meaning of the Ontario Securities Act or other laws or regulations. All statements, other than statements of historical fact, included herein, including without limitation, statements regarding potential mineralization, mineral resources or reserves, exploration results, future plans and objectives of Chieftain Metals Inc. are forward-looking statements that involve risks and uncertainties. There can be no assurance that such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements.

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
The cloud is now a fact of life but generating recurring revenues that are driven by solutions and services on a consumption model have been hard to implement, until now. In their session at 16th Cloud Expo, Ermanno Bonifazi, CEO & Founder of Solgenia, and Ian Khan, Global Strategic Positioning & Brand Manager at Solgenia, will discuss how a top European telco has leveraged the innovative recurring revenue generating capability of the consumption cloud to enable a unique cloud monetization model to drive results.
As organizations shift toward IT-as-a-service models, the need for managing and protecting data residing across physical, virtual, and now cloud environments grows with it. CommVault can ensure protection &E-Discovery of your data – whether in a private cloud, a Service Provider delivered public cloud, or a hybrid cloud environment – across the heterogeneous enterprise. In his session at 16th Cloud Expo, Randy De Meno, Chief Technologist - Windows Products and Microsoft Partnerships, will discuss how to cut costs, scale easily, and unleash insight with CommVault Simpana software, the only si...
Analytics is the foundation of smart data and now, with the ability to run Hadoop directly on smart storage systems like Cloudian HyperStore, enterprises will gain huge business advantages in terms of scalability, efficiency and cost savings as they move closer to realizing the potential of the Internet of Things. In his session at 16th Cloud Expo, Paul Turner, technology evangelist and CMO at Cloudian, Inc., will discuss the revolutionary notion that the storage world is transitioning from mere Big Data to smart data. He will argue that today’s hybrid cloud storage solutions, with commodity...
Cloud data governance was previously an avoided function when cloud deployments were relatively small. With the rapid adoption in public cloud – both rogue and sanctioned, it’s not uncommon to find regulated data dumped into public cloud and unprotected. This is why enterprises and cloud providers alike need to embrace a cloud data governance function and map policies, processes and technology controls accordingly. In her session at 15th Cloud Expo, Evelyn de Souza, Data Privacy and Compliance Strategy Leader at Cisco Systems, will focus on how to set up a cloud data governance program and s...
Roberto Medrano, Executive Vice President at SOA Software, had reached 30,000 page views on his home page - http://RobertoMedrano.SYS-CON.com/ - on the SYS-CON family of online magazines, which includes Cloud Computing Journal, Internet of Things Journal, Big Data Journal, and SOA World Magazine. He is a recognized executive in the information technology fields of SOA, internet security, governance, and compliance. He has extensive experience with both start-ups and large companies, having been involved at the beginning of four IT industries: EDA, Open Systems, Computer Security and now SOA.
The industrial software market has treated data with the mentality of “collect everything now, worry about how to use it later.” We now find ourselves buried in data, with the pervasive connectivity of the (Industrial) Internet of Things only piling on more numbers. There’s too much data and not enough information. In his session at @ThingsExpo, Bob Gates, Global Marketing Director, GE’s Intelligent Platforms business, to discuss how realizing the power of IoT, software developers are now focused on understanding how industrial data can create intelligence for industrial operations. Imagine ...
We certainly live in interesting technological times. And no more interesting than the current competing IoT standards for connectivity. Various standards bodies, approaches, and ecosystems are vying for mindshare and positioning for a competitive edge. It is clear that when the dust settles, we will have new protocols, evolved protocols, that will change the way we interact with devices and infrastructure. We will also have evolved web protocols, like HTTP/2, that will be changing the very core of our infrastructures. At the same time, we have old approaches made new again like micro-services...
Every innovation or invention was originally a daydream. You like to imagine a “what-if” scenario. And with all the attention being paid to the so-called Internet of Things (IoT) you don’t have to stretch the imagination too much to see how this may impact commercial and homeowners insurance. We’re beyond the point of accepting this as a leap of faith. The groundwork is laid. Now it’s just a matter of time. We can thank the inventors of smart thermostats for developing a practical business application that everyone can relate to. Gone are the salad days of smart home apps, the early chalkb...
Operational Hadoop and the Lambda Architecture for Streaming Data Apache Hadoop is emerging as a distributed platform for handling large and fast incoming streams of data. Predictive maintenance, supply chain optimization, and Internet-of-Things analysis are examples where Hadoop provides the scalable storage, processing, and analytics platform to gain meaningful insights from granular data that is typically only valuable from a large-scale, aggregate view. One architecture useful for capturing and analyzing streaming data is the Lambda Architecture, representing a model of how to analyze rea...
Today’s enterprise is being driven by disruptive competitive and human capital requirements to provide enterprise application access through not only desktops, but also mobile devices. To retrofit existing programs across all these devices using traditional programming methods is very costly and time consuming – often prohibitively so. In his session at @ThingsExpo, Jesse Shiah, CEO, President, and Co-Founder of AgilePoint Inc., discussed how you can create applications that run on all mobile devices as well as laptops and desktops using a visual drag-and-drop application – and eForms-buildi...
SYS-CON Events announced today that Vitria Technology, Inc. will exhibit at SYS-CON’s @ThingsExpo, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Vitria will showcase the company’s new IoT Analytics Platform through live demonstrations at booth #330. Vitria’s IoT Analytics Platform, fully integrated and powered by an operational intelligence engine, enables customers to rapidly build and operationalize advanced analytics to deliver timely business outcomes for use cases across the industrial, enterprise, and consumer segments.
Containers and microservices have become topics of intense interest throughout the cloud developer and enterprise IT communities. Accordingly, attendees at the upcoming 16th Cloud Expo at the Javits Center in New York June 9-11 will find fresh new content in a new track called PaaS | Containers & Microservices Containers are not being considered for the first time by the cloud community, but a current era of re-consideration has pushed them to the top of the cloud agenda. With the launch of Docker's initial release in March of 2013, interest was revved up several notches. Then late last...
SYS-CON Events announced today that Dyn, the worldwide leader in Internet Performance, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Dyn is a cloud-based Internet Performance company. Dyn helps companies monitor, control, and optimize online infrastructure for an exceptional end-user experience. Through a world-class network and unrivaled, objective intelligence into Internet conditions, Dyn ensures traffic gets delivered faster, safer, and more reliably than ever.
In their session at @ThingsExpo, Shyam Varan Nath, Principal Architect at GE, and Ibrahim Gokcen, who leads GE's advanced IoT analytics, focused on the Internet of Things / Industrial Internet and how to make it operational for business end-users. Learn about the challenges posed by machine and sensor data and how to marry it with enterprise data. They also discussed the tips and tricks to provide the Industrial Internet as an end-user consumable service using Big Data Analytics and Industrial Cloud.
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @ThingsExpo, Michael Sick, a Senior Manager and Big Data Architect within Ernst and Young's Financial Servi...
Performance is the intersection of power, agility, control, and choice. If you value performance, and more specifically consistent performance, you need to look beyond simple virtualized compute. Many factors need to be considered to create a truly performant environment. In his General Session at 15th Cloud Expo, Harold Hannon, Sr. Software Architect at SoftLayer, discussed how to take advantage of a multitude of compute options and platform features to make cloud the cornerstone of your online presence.
Even as cloud and managed services grow increasingly central to business strategy and performance, challenges remain. The biggest sticking point for companies seeking to capitalize on the cloud is data security. Keeping data safe is an issue in any computing environment, and it has been a focus since the earliest days of the cloud revolution. Understandably so: a lot can go wrong when you allow valuable information to live outside the firewall. Recent revelations about government snooping, along with a steady stream of well-publicized data breaches, only add to the uncertainty
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @ThingsExpo, Michael Sick, a Senior Manager and Big Data Architect within Ernst and Young's Financial Servi...
Docker is an excellent platform for organizations interested in running microservices. It offers portability and consistency between development and production environments, quick provisioning times, and a simple way to isolate services. In his session at DevOps Summit at 16th Cloud Expo, Shannon Williams, co-founder of Rancher Labs, will walk through these and other benefits of using Docker to run microservices, and provide an overview of RancherOS, a minimalist distribution of Linux designed expressly to run Docker. He will also discuss Rancher, an orchestration and service discovery platf...
PubNub on Monday has announced that it is partnering with IBM to bring its sophisticated real-time data streaming and messaging capabilities to Bluemix, IBM’s cloud development platform. “Today’s app and connected devices require an always-on connection, but building a secure, scalable solution from the ground up is time consuming, resource intensive, and error-prone,” said Todd Greene, CEO of PubNub. “PubNub enables web, mobile and IoT developers building apps on IBM Bluemix to quickly add scalable realtime functionality with minimal effort and cost.”