Click here to close now.


Microsoft Cloud Authors: Jordan Sanders, Carmen Gonzalez, Pat Romanski, Keith Mayer, Jayaram Krishnaswamy

News Feed Item

Kirkland Lake Gold Inc.: Fiscal 2013 Q2 Operational and Financial Results

KIRKLAND LAKE, ONTARIO -- (Marketwire) -- 12/13/12 -- Kirkland Lake Gold Inc. (the "Company"), (TSX:KGI)(AIM:KGI) an operating and exploration gold mining company, today announces financial and operational results for the second quarter of its fiscal year 2013 (August, September, and October 2012).

Mr. Harry Dobson, Chairman commented, "The focus of the Company remains the execution of the Mine Expansion Project to a production capacity of 2,200 tons of ore per day. Reaching this milestone will be a key step towards achieving the Company's goal of becoming a sustainable and consistently profitable intermediate gold mining company. The current critical path activity for this Expansion Project is the Service Cage Project. Regrettably, delays in completing this critical path activity have resulted in a delay in the overall Project, and are preventing the Company from meeting its production goals for the current fiscal year. Accordingly, the Company is reducing its guidance for the year ending April 30 to between 90,000 to 110,000 ounces of gold sold. This setback notwithstanding, the Company does remain committed to reaching the above referenced production capacity of 2,200 tons per day as close to the original plan target date of January 2014 as practicable."

Mr. Mark Tessier, Chief Operating Officer, added, "The current critical path item in this expansion project is the Service Cage Project, which will allow hoisting of ore and waste to begin to exceed the current 1,000 ton per day limit. Unfortunately, the completion of this Project continues to be delayed by technical issues with the hoist, primarily software and electronic issues; and also by additional shaft work that had to be moved up in the overall project schedule, and into the scope of the Service Cage Project. The delay in this Project has delayed the ramp up in ore tonnage produced that should have begun in Q2, has delayed the hiring and training of necessary underground workers, and has delayed development work required to access higher grade ore that was required to allow the Company to produce at the planned ore grades this year."

"The Service Cage Project is close to completion, but due to past delays in this Project, the Company is currently allowing in its projections that the Project will not be fully complete before the end of Q3, and that ore tonnage will not begin to ramp up until mid Q4, as a precaution. The Company is also slowing the expected rate of that ore tonnage ramp up to reflect the additional time that will be required to hire and train needed underground workers, and to reflect the time that will be required to complete the development work in the Mine that has been delayed."


--  Net loss before income taxes for the quarter ended October 31, 2012 of
    $0.8 million ($0.01 per share). This compares to net loss before taxes
    of $0.3 million ($0.00 per share) for the previous quarter and a net
    income before taxes of $11.8 million ($0.16 per share) for Q2 of fiscal
    2012. Ore production for the quarter continued to be skewed towards
    lower grade areas, as access to higher grade ore was restricted due to
    delays in the Service Cage Project. Costs were also high as the Company
    had completed some hiring and training and committed to other work and
    activities in Q1 and Q2 in preparation for the planned production
--  Cash flows generated from operating activities were $10.5 million for
    the quarter compared to $2.4 million in the previous quarter and $13.4
    million in Q2 of fiscal 2012. Year to date cash flows from operating
    activities were $12.9 million compared to $19.7 million in the previous
    fiscal year. 
--  Operating costs for the quarter were $360 per ton of ore ($1,253 per
    ounce of gold), compared with $316 per ton ($1,276 per ounce) in the
    prior quarter, and $277 per ton ($793 per ounce) in Q2 of fiscal 2012.
    The Company expects to lower operating costs to less than $250 per ton
    upon completion of the Mine Expansion Project. 
--  In the quarter, 70,800 tons of ore were produced at a head grade of 0.30
    ounces of gold per ton (opt) and a gold recovery rate of 95.74% to
    produce 20,358 ounces of gold. Year to date, 141,001 tons of ore have
    been produced at a head grade of 0.28 opt and a gold recovery rate of
    95.52% to produce 37,754 ounces. Ounces sold in the quarter were 22,345
    ounces, bringing the year to date total to 42,309 ounces sold. The head
    grade of the ore coming from the South Mine Complex (SMC) in the quarter
    was 0.34 opt, which was above the 0.27 opt grade realized in the
    previous quarter, but well below the normal grade of ore coming from
    that area. The head grade of ore coming from the Main Break in the
    quarter was 0.25 opt. 
--  As at December 12, 2012, the Company's cash resources were $101.1
    million. Net of the liability to Queenston and restricted cash, the
    Company's cash resources were $71.1 million. 
--  Work remaining on the Service Cage Project as of December 12 included
    some ongoing trials and upgrades planned for operation of the hoist in
    Cage mode, completion of shaft work between 53 Level and 54 Level, and
    completion of 50% to 60% of the required station work. Commissioning
    work on the hoist and cage took up most of the month of November due to
    some problems with software and electronics for the control systems and
    held back the work in other areas. The work platform remains in the
    shaft and is being used in combination with the cage as required for the
    shaft work. At present the hoist is operating in cage/work platform mode
    for shaft work with no issues, and is also being operated in cage only
    mode on a spare/trial basis with no issues. 
--  The Company is planning to replace the ten ton skips in the existing
    conveyance arrangement with newly designed 12.5 ton skips after
    completion of the Service Cage Project. Slight modifications to the
    shaft loading chairs will be required at the same time. This will
    increase the capacity of the mine hoisting plant to 2,275 tons per day
    of ore and waste. Completion of additional shaft work prior to January
    2014 will bring the capacity of the mine hoisting plant to 3,200 tons
    per day. The shaft work brought ahead into the Service Cage Project was
    originally part of this later stage of the overall Project. 
--  The testing of the prototype battery scoop underground has been
    completed successfully. The scoop is currently commissioned and in
    production and performing very well, and this program is currently
    meeting all Project schedule requirements at this time. 
--  The new ball mill is currently on site; work is ongoing to expand the
    mill to 2,200 tons per day capacity. 
--  The Company workforce totalled 957 employees at quarter-end, up from 907
    at the beginning of Q1. The Company is not experiencing difficulty
    meeting its workforce requirements in terms of numbers at this time.
    However, more hiring of inexperienced underground employees than
    expected has been required, with a resultant increase in training
    activities, and with lower than planned initial productivities. This has
    slightly impacted mining costs this fiscal year. 
--  The Expansion Project budget remains on track at $95.0 million, of which
    $72.7 million had been spent by the end of October, 2012. The Processing
    Plant Upgrade, the Hoisting Capacity Upgrade Project, and the remaining
    underground mobile equipment purchases represent the largest segments of
    unspent Project capital. Project spending in some non critical path
    Project areas has been delayed as necessary and where practicable to
    match progress on the critical path. 
--  Subsequent to quarter-end on November 7, the Company completed a $68.5
    million (net of transaction costs) private placement of convertible
    debentures. The funds will be used in part to fund portions of the
    Expansion Project that had been expected to be funded from production. 


The Company's ability to achieve production goals and targets is being impacted by the complex multi-year Exploration and Expansion Project that the Company is currently implementing. The Company's current and future production targets will therefore include additional contingencies to reflect the potential for greater variances arising from unanticipated or unknown problems, for unexpected challenges or delays that may arise, and for the higher priority status of project work over production. Work on next fiscal year's budget will begin shortly. At this time, the Company intends to budget based on gold sales of 150,000 to 180,000 ounces for fiscal year 2014, again using the methodology outlined above. The Company intends to increase gold sales further from these levels in future years. Please refer to the Company's Management Discussion and Analysis available on SEDAR and the Company's website for further information.

Financial Highlights                           Three months ended,          
(All amounts in 000's of Canadian                                           
 Dollars, except shares and per share                                       
                                     Oct 31, 2012 Jul 31, 2012 Oct 31, 2011 
Gold Sales (ounces)                        22,345       19,964       24,762 
Average Price (per ounce)                   1,660        1,635        1,628 
Revenue                                    37,101       32,648       40,307 
Production Expenses                        30,042       26,616       23,527 
Exploration Expenses                        4,710        4,332        3,419 
Net Income (Loss) before Income Taxes        (826)        (295)      11,785 
Net and Comprehensive Income (Loss)          (783)         413        9,264 
Per share (basic and diluted)               (0.01)        0.01         0.13 
Cash Flow from operating activities        10,454        2,403       13,421 
Cash Flow from financing activities         3,945       54,085        1,031 
Cash Flow used in investing                                                 
 activities                               (47,781)     (38,319)     (15,941)
Net increase (decrease) in cash           (33,382)      18,169       (1,449)
Total cash resources                       39,954       73,288       38,386 
Other Current Assets                       22,976       25,767       18,888 
Current Liabilities                        63,058       26,844       20,003 
Working Capital                              (128)      72,211       37,721 
Total Assets                              364,493      327,085      245,400 
Total Liabilities                         123,884       86,185       24,442 
Weighted average number of shares                                           
 outstanding                           70,150,912   70,150,912   69,867,941 
Dividends per share                           NIL          NIL          NIL 

About the Company

Kirkland Lake Gold's corporate goal is to create a self sustaining and long lived intermediate Gold Mining Company based in the historic Kirkland Lake Gold Camp. The Company plans to do this by increasing production capacity to 2,200 tons of ore per day in several stages, and by decreasing production costs by realizing the economies of scale associated with that higher production capacity. At the same time, the company is committed to maintaining a significant exploration program aimed at developing and maintaining a property wide reserve and resource base sufficient to sustain a mine life of more than ten years for as long as practicable.

Cautionary Note Regarding Forward-Looking Statements

This Press Release contains statements which constitute "forward-looking statements", including statements regarding the plans, intentions, beliefs and current expectations of the Company with respect to the future business activities and operating performance of the Company. The words "may", "would", "could", "will", "intend", "plan", "anticipate", "believe", "estimate", "expect" and similar expressions, as they relate to the Company, are intended to identify such forward-looking statements. Investors are cautioned that forward-looking statements are based on the opinions, assumptions and estimates of management considered reasonable at the date the statements are made, and are inherently subject to a variety of risks and uncertainties and other known and unknown factors that could cause actual events or results to differ materially from those projected in the forward-looking statements. These factors include the Company's expectations in connection with the projects and exploration programs being met, the impact of general business and economic conditions, global liquidity and credit availability on the timing of cash flows and the values of assets and liabilities based on projected future conditions, fluctuating gold prices, currency exchange rates (such as the Canadian dollar versus the United States Dollar), possible variations in ore grade or recovery rates, changes in accounting policies, changes in the Company's corporate mineral resources, changes in project parameters as plans continue to be refined, changes in project development, construction, production and commissioning time frames, risks related to joint venture operations, the possibility of project cost overruns or unanticipated costs and expenses, higher prices for fuel, power, labour and other consumables contributing to higher costs and general risks of the mining industry, failure of plant, equipment or processes to operate as anticipated, unexpected changes in mine life, seasonality and unanticipated weather changes, costs and timing of the development of new deposits, success of exploration activities, permitting time lines, government regulation of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims, and limitations on insurance, as well as those risk factors discussed or referred to in the Company's annual Management's Discussion and Analysis and Annual Information Form for the year ended April 30, 2012 filed with the securities regulatory authorities in certain provinces of Canada and available at

Should one or more of these risks or uncertainties materialize, or should assumptions underlying the forward-looking statements prove incorrect, actual results may vary materially from those described herein as intended, planned, anticipated, believed, estimated or expected. Although the Company has attempted to identify important risks, uncertainties and factors which could cause actual results to differ materially, there may be others that cause results not be as anticipated, estimated or intended. The Company does not intend, and does not assume any obligation, to update these forward-looking statements except as otherwise required by applicable law.

Neither the Toronto Stock Exchange nor the AIM Market of the London Stock Exchange has reviewed and neither accepts responsibility for the adequacy or accuracy of this news release.

Kirkland Lake Gold Inc.
Brian Hinchcliffe
+1 705 567 5208
+1 705 568 6444 (FAX)
[email protected]

Kirkland Lake Gold Inc.
Lindsay Carpenter
Director of Investor Relations
+1 416-840-7884
+1 705 568 6444 (FAX)
[email protected]

NOMAD: Panmure Gordon (UK) Limited
Katherine Roe
+44 (0) 20 7 8862500
[email protected]

NOMAD: Panmure Gordon (UK) Limited
Callum Stewart
+44 (0) 20 7 8862500
[email protected]

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
Today air travel is a minefield of delays, hassles and customer disappointment. Airlines struggle to revitalize the experience. GE and M2Mi will demonstrate practical examples of how IoT solutions are helping airlines bring back personalization, reduce trip time and improve reliability. In their session at @ThingsExpo, Shyam Varan Nath, Principal Architect with GE, and Dr. Sarah Cooper, M2Mi’s VP Business Development and Engineering, explored the IoT cloud-based platform technologies driving this change including privacy controls, data transparency and integration of real time context with p...
I recently attended and was a speaker at the 4th International Internet of @ThingsExpo at the Santa Clara Convention Center. I also had the opportunity to attend this event last year and I wrote a blog from that show talking about how the “Enterprise Impact of IoT” was a key theme of last year’s show. I was curious to see if the same theme would still resonate 365 days later and what, if any, changes I would see in the content presented.
Cloud computing delivers on-demand resources that provide businesses with flexibility and cost-savings. The challenge in moving workloads to the cloud has been the cost and complexity of ensuring the initial and ongoing security and regulatory (PCI, HIPAA, FFIEC) compliance across private and public clouds. Manual security compliance is slow, prone to human error, and represents over 50% of the cost of managing cloud applications. Determining how to automate cloud security compliance is critical to maintaining positive ROI. Raxak Protect is an automated security compliance SaaS platform and ma...
The Internet of Things (IoT) is growing rapidly by extending current technologies, products and networks. By 2020, Cisco estimates there will be 50 billion connected devices. Gartner has forecast revenues of over $300 billion, just to IoT suppliers. Now is the time to figure out how you’ll make money – not just create innovative products. With hundreds of new products and companies jumping into the IoT fray every month, there’s no shortage of innovation. Despite this, McKinsey/VisionMobile data shows "less than 10 percent of IoT developers are making enough to support a reasonably sized team....
Just over a week ago I received a long and loud sustained applause for a presentation I delivered at this year’s Cloud Expo in Santa Clara. I was extremely pleased with the turnout and had some very good conversations with many of the attendees. Over the next few days I had many more meaningful conversations and was not only happy with the results but also learned a few new things. Here is everything I learned in those three days distilled into three short points.
DevOps is about increasing efficiency, but nothing is more inefficient than building the same application twice. However, this is a routine occurrence with enterprise applications that need both a rich desktop web interface and strong mobile support. With recent technological advances from Isomorphic Software and others, rich desktop and tuned mobile experiences can now be created with a single codebase – without compromising functionality, performance or usability. In his session at DevOps Summit, Charles Kendrick, CTO and Chief Architect at Isomorphic Software, demonstrated examples of com...
As organizations realize the scope of the Internet of Things, gaining key insights from Big Data, through the use of advanced analytics, becomes crucial. However, IoT also creates the need for petabyte scale storage of data from millions of devices. A new type of Storage is required which seamlessly integrates robust data analytics with massive scale. These storage systems will act as “smart systems” provide in-place analytics that speed discovery and enable businesses to quickly derive meaningful and actionable insights. In his session at @ThingsExpo, Paul Turner, Chief Marketing Officer at...
In his keynote at @ThingsExpo, Chris Matthieu, Director of IoT Engineering at Citrix and co-founder and CTO of Octoblu, focused on building an IoT platform and company. He provided a behind-the-scenes look at Octoblu’s platform, business, and pivots along the way (including the Citrix acquisition of Octoblu).
In his General Session at 17th Cloud Expo, Bruce Swann, Senior Product Marketing Manager for Adobe Campaign, explored the key ingredients of cross-channel marketing in a digital world. Learn how the Adobe Marketing Cloud can help marketers embrace opportunities for personalized, relevant and real-time customer engagement across offline (direct mail, point of sale, call center) and digital (email, website, SMS, mobile apps, social networks, connected objects).
The Internet of Everything is re-shaping technology trends–moving away from “request/response” architecture to an “always-on” Streaming Web where data is in constant motion and secure, reliable communication is an absolute necessity. As more and more THINGS go online, the challenges that developers will need to address will only increase exponentially. In his session at @ThingsExpo, Todd Greene, Founder & CEO of PubNub, exploreed the current state of IoT connectivity and review key trends and technology requirements that will drive the Internet of Things from hype to reality.
Two weeks ago (November 3-5), I attended the Cloud Expo Silicon Valley as a speaker, where I presented on the security and privacy due diligence requirements for cloud solutions. Cloud security is a topical issue for every CIO, CISO, and technology buyer. Decision-makers are always looking for insights on how to mitigate the security risks of implementing and using cloud solutions. Based on the presentation topics covered at the conference, as well as the general discussions heard between sessions, I wanted to share some of my observations on emerging trends. As cyber security serves as a fou...
We all know that data growth is exploding and storage budgets are shrinking. Instead of showing you charts on about how much data there is, in his General Session at 17th Cloud Expo, Scott Cleland, Senior Director of Product Marketing at HGST, showed how to capture all of your data in one place. After you have your data under control, you can then analyze it in one place, saving time and resources.
With all the incredible momentum behind the Internet of Things (IoT) industry, it is easy to forget that not a single CEO wakes up and wonders if “my IoT is broken.” What they wonder is if they are making the right decisions to do all they can to increase revenue, decrease costs, and improve customer experience – effectively the same challenges they have always had in growing their business. The exciting thing about the IoT industry is now these decisions can be better, faster, and smarter. Now all corporate assets – people, objects, and spaces – can share information about themselves and thei...
The cloud. Like a comic book superhero, there seems to be no problem it can’t fix or cost it can’t slash. Yet making the transition is not always easy and production environments are still largely on premise. Taking some practical and sensible steps to reduce risk can also help provide a basis for a successful cloud transition. A plethora of surveys from the likes of IDG and Gartner show that more than 70 percent of enterprises have deployed at least one or more cloud application or workload. Yet a closer inspection at the data reveals less than half of these cloud projects involve production...
Continuous processes around the development and deployment of applications are both impacted by -- and a benefit to -- the Internet of Things trend. To help better understand the relationship between DevOps and a plethora of new end-devices and data please welcome Gary Gruver, consultant, author and a former IT executive who has led many large-scale IT transformation projects, and John Jeremiah, Technology Evangelist at Hewlett Packard Enterprise (HPE), on Twitter at @j_jeremiah. The discussion is moderated by me, Dana Gardner, Principal Analyst at Interarbor Solutions.
Discussions of cloud computing have evolved in recent years from a focus on specific types of cloud, to a world of hybrid cloud, and to a world dominated by the APIs that make today's multi-cloud environments and hybrid clouds possible. In this Power Panel at 17th Cloud Expo, moderated by Conference Chair Roger Strukhoff, panelists addressed the importance of customers being able to use the specific technologies they need, through environments and ecosystems that expose their APIs to make true change and transformation possible.
Too often with compelling new technologies market participants become overly enamored with that attractiveness of the technology and neglect underlying business drivers. This tendency, what some call the “newest shiny object syndrome” is understandable given that virtually all of us are heavily engaged in technology. But it is also mistaken. Without concrete business cases driving its deployment, IoT, like many other technologies before it, will fade into obscurity.
Microservices are a very exciting architectural approach that many organizations are looking to as a way to accelerate innovation. Microservices promise to allow teams to move away from monolithic "ball of mud" systems, but the reality is that, in the vast majority of organizations, different projects and technologies will continue to be developed at different speeds. How to handle the dependencies between these disparate systems with different iteration cycles? Consider the "canoncial problem" in this scenario: microservice A (releases daily) depends on a couple of additions to backend B (re...
The Internet of Things is clearly many things: data collection and analytics, wearables, Smart Grids and Smart Cities, the Industrial Internet, and more. Cool platforms like Arduino, Raspberry Pi, Intel's Galileo and Edison, and a diverse world of sensors are making the IoT a great toy box for developers in all these areas. In this Power Panel at @ThingsExpo, moderated by Conference Chair Roger Strukhoff, panelists discussed what things are the most important, which will have the most profound effect on the world, and what should we expect to see over the next couple of years.
Container technology is shaping the future of DevOps and it’s also changing the way organizations think about application development. With the rise of mobile applications in the enterprise, businesses are abandoning year-long development cycles and embracing technologies that enable rapid development and continuous deployment of apps. In his session at DevOps Summit, Kurt Collins, Developer Evangelist at, examined how Docker has evolved into a highly effective tool for application delivery by allowing increasingly popular Mobile Backend-as-a-Service (mBaaS) platforms to quickly crea...