Canadian Oil Sands' 2013 Budget Focused on Advancing Major Capital Projects

CALGARY, ALBERTA -- (Marketwire) -- 11/30/12 --

Unless otherwise noted: All figures are based on Canadian Oil Sands' 36.74 per cent working interest in the Syncrude joint venture; all financial figures are in Canadian dollars and have been prepared in accordance with Canadian Generally Accepted Accounting Principles ("GAAP").

Canadian Oil Sands Limited's (TSX:COS) (OTCQX:COSWF) (COS) budget for 2013 supports continued progress on Syncrude's multi-year major capital projects program, which is scheduled to be largely complete by the end of 2014. This program is directed at improving environmental performance and maintaining a strong base of long-life crude oil production.

COS plans to invest about $1.3 billion at Syncrude in 2013. Approximately 63 per cent, or $836 million, will be invested in major projects to replace or relocate mining infrastructure and to develop facilities to reclaim tailings, a by-product of the mining process. About $393 million is directed to regular maintenance, which represents smaller projects and annually occurring expenditures to maintain production. The remaining $97 million reflects capitalized interest.

"Syncrude's major projects are advancing on-schedule and on-budget, and our finance plan for these projects is in excellent shape. Our balance sheet is stronger than we had anticipated exiting 2012," said Marcel Coutu, President and Chief Executive Officer. "We intend to maintain our current quarterly dividend of $0.35 per share through 2013 based on our healthy financial position and the assumptions provided today in our 2013 budget."

Major Projects Capital Allocation


                                   Expected                                 
                                   Spend to   Expected   Expected           
                                   Dec. 31,   Spend in   Spend in           
($ billions, COS' 36.74% share)        2012       2013  2014-2015      Total
----------------------------------------------------------------------------
                                                                            
                                                                            
Mine Train                                                                  
 Replacements/Relocations             $ 0.8      $ 0.6      $ 0.6      $ 2.0
                                                                            
Aurora North Tailings Management                                            
 (1)                                    0.2        0.1        0.0        0.3
                                                                            
Centrifuge Tailings Management          0.1        0.2        0.4        0.7
                                                                            
----------------------------------------------------------------------------
Total Major Projects Spending         $ 1.1      $ 0.9      $ 1.0      $ 3.0
----------------------------------------------------------------------------
(1) Aurora North Tailings Management expected spend in 2014 is approximately
$20 million (net 36.74% to COS).                                            
Total project costs include both capital costs and certain non-production   
costs. Costs exclude capitalized interest.                                  

Added Coutu: "We are looking forward to making significant progress on Syncrude's major capital projects in 2013, which will greatly reduce any perceived capital risk. Once this investment has been made in our base operations, we are in the advantageous position of having the infrastructure in place to produce strong, stable volumes of fully upgraded, light crude oil for decades."

2013 Objectives

COS has established the following objectives for 2013:


--  Aim to maintain a quarterly dividend of $0.35 per share in 2013, based
    on the assumptions outlined in the 2013 budget. 
--  Maintain a strong balance sheet while remaining unhedged on oil prices,
    thereby providing investors with the full potential of this commodity. 
--  Increase production by about three per cent, equivalent to three million
    barrels gross to Syncrude, over estimated 2012 production. 
--  Improve per barrel operating expenses in 2013 over 2012. 
--  Complete the Aurora North Tailings Management project. 
--  Achieve 90 per cent completion on the Aurora Mine Train Relocation. 
--  Achieve 75 per cent completion on the Mildred Lake Mine Train
    Replacement. 
--  Invest $25 million ($70 million gross to Syncrude) in research and
    development, directed at reducing operating expenses, improving
    reliability, enhancing environmental performance and realizing potential
    cost savings in environmental initiatives. 

2013 Budget Highlights


--  COS' production outlook for Syncrude is 105 million to 115 million
    barrels (39 to 42 million barrels net to COS). The single point
    production estimate is 110 million barrels (40.4 million barrels net to
    COS). The production outlook incorporates a planned turnaround of Coker
    8-1 in the second half of 2013. 
--  Sales, net of crude oil purchases and transportation expense, are
    anticipated to total $3,233 million, based on a WTI crude oil price
    assumption of US$85 per barrel, a foreign exchange rate of $1.00
    U.S./Cdn, and a discount for Syncrude Crude Oil (SCO) to Cdn WTI of $5
    per barrel. 
--  Operating expenses are anticipated to total $1,482 million to produce
    Syncrude's blend of fully upgraded SCO. On a per barrel basis, operating
    expenses are estimated to be $36.67, which includes purchased energy
    costs of $4.40. 
--  Cash flow from operations is estimated at $1,045 million ($2.16 per
    share). 
--  Cash balances will be used to fund 2013 capital spending and to support
    dividends, resulting in an expected net debt level of about $1.3 billion
    at year-end 2013. 
--  Allowable deductible costs for royalty purposes in 2013 are anticipated
    to exceed deemed bitumen revenues. As a result, COS expects to pay
    minimum royalties at one per cent of gross deemed bitumen revenues in
    2013. In addition, we will continue to accrue the transition royalty and
    upgrader growth capital recapture payments.  
--  COS estimates current taxes of approximately $350 million in 2013. COS
    expects deductions for capital expenditures made in 2012 and 2013 will
    be available in 2014 and beyond, resulting in lower taxes in subsequent
    years, based on the assumptions outlined in the 2013 budget.  

2013 Budget Summary


----------------------------------------------------------------------------
(millions of Canadian dollars, except volume and per barrel                 
 amounts)                                                                   
----------------------------------------------------------------------------
Syncrude production (mmbbls)                                             110
Canadian Oil Sands sales (mmbbls)                                       40.4
Sales, net of crude oil purchases and transportation                   3,233
Operating expenses                                                     1,482
Operating expenses per barrel                                          36.67
Crown royalties                                                          113
Cash flow from operations                                              1,045
Total capital expenditures                                             1,326
----------------------------------------------------------------------------
Business environment assumptions                                            
West Texas Intermediate (U.S.$/bbl)                                    85.00
Premium (Discount) to average Cdn$ WTI prices (Cdn$/bbl)               -5.00
Foreign exchange rate (U.S.$/Cdn$)                                      1.00
AECO natural gas (Cdn$/GJ)                                              3.50
----------------------------------------------------------------------------

The 2013 budget may be impacted by a variety of factors. Some of the more significant variables include, without limitation:


--  Crude oil prices: Canadian Oil Sands' 2013 production is currently
    unhedged. Accordingly, COS' cash flow from operations is highly
    sensitive to changes in crude oil prices and foreign exchange rates.
    Every US$1.00 per barrel change in the annual WTI crude oil price
    impacts cash flow from operations by about $30 million, or $0.06 per
    share. 
--  Syncrude operational reliability and production: Timing of unit
    turnarounds and maintenance are not always precisely scheduled and
    unplanned outages may occur. In addition to the impact on production,
    unplanned maintenance costs can affect operating expenses. Every two
    million barrel change in Syncrude annual production impacts cash flow
    from operations by about $44 million, or $0.09 per share. 
--  Given the sensitivity of earnings and cash flow to conditions such as
    oil prices and differentials, exchange rates, production levels and
    operating and capital costs, the corporation may need to adjust
    dividends in 2013 if the operating environment as projected in the
    budget does not prevail. 

2013 Cash Flow From Operations Sensitivities

(after tax; COS anticipates recording approximately $350 million in current taxes in 2013)

An opposite change in each of these variables will result in the opposite cash flow from operations impact


----------------------------------------------------------------------------
                                                       $ Millions    $/Share
----------------------------------------------------------------------------
Syncrude operating expense decrease (Cdn $1.00/bbl)            30       0.06
Syncrude operating expense decrease (Cdn $50 million)          14       0.03
WTI crude oil price increase (U.S. $1.00/bbl)                  30       0.06
Syncrude production increase (2 million bbls)                  44       0.09
Canadian dollar weakening (U.S. $0.01/Cdn$)                    25       0.05
AECO natural gas price decrease (Cdn $0.50/GJ)                 16       0.03
----------------------------------------------------------------------------

More information on Canadian Oil Sands' 2013 Budget is provided in our 2013 Guidance Document, which is available on COS' web site at www.cdnoilsands.com under "Investor Centre". Canadian Oil Sands intends to continue providing quarterly updates to its guidance.

2013 Budget Conference Call

A conference call and webcast will be held tomorrow, November 30, 2012 at 8:00 a.m. MT (10:00 a.m. ET).

To participate, please dial (888) 231-8191 (toll-free in North America) or (647) 427-7450 approximately 10 minutes prior to the conference call. An archived recording of the call will be available from approximately 11:00 a.m. MT on November 30 until midnight of December 7, 2012 by dialing (855) 859-2056 or (403) 451-9481 and entering conference password 70803185.

A live and archived audio webcast of the conference call will also be available on Canadian Oil Sands' website at www.cdnoilsands.com, under the Presentations and Events section in the Investor Centre, or via the following link:

http://event.on24.com/r.htm?e=542350&s=1&k=B2B8C275990C46324C22634ED6B9F160

Canadian Oil Sands Limited

Canadian Oil Sands is a pure investment opportunity in light, sweet crude oil. Through our 36.74% interest in the Syncrude project, we offer a solid, robust production stream of fully upgraded crude oil, exposure to future crude oil prices, potential growth through high-quality oil sands leases and an attractive dividend.

For more information please visit our web site at: www.cdnoilsands.com

Ticker Symbols

Toronto Stock Exchange: COS

OCTQX: COSWF

Forward-looking Information Advisory: In the interest of providing Canadian Oil Sands Limited ("Canadian Oil Sands" or the "Corporation") shareholders and potential investors with information regarding the Corporation, including management's assessment of the Corporation's future production and cost estimates, plans and operations, certain statements throughout this release contain "forward-looking information" under applicable securities law.

Forward-looking statements are typically identified by words such as "anticipate", "expect", "believe", "plan", "intend" or similar words suggesting future outcomes. Forward-looking statements in this press release include, but are not limited to, statements with respect to: the expected amount of total major projects spending in 2013; the expected amount of regular maintenance costs and capitalized interest in 2013; the expectation that spending on the Syncrude major projects will taper off after 2014; the intention to maintain the current quarterly dividend of $0.35 per share through 2013 based on the assumptions in the 2013 budget; future dividends and any increase or decrease from current payment amounts; the expected amount of total capital expenditures in 2013; the expected amount of 2012-2015 major project spending for the mine train relocations/replacements, the Aurora North composite tails plant and the Mildred Lake centrifuge plant; the expected amount of total major project spending; the belief that Syncrude's major projects will provide the necessary infrastructure to produce crude oil for decades; the expectation that 2013 Syncrude production will increase by about three per cent over estimated 2012 production; plans regarding crude oil hedges in the future; the expectation that the Aurora North composite tails plant will be complete in 2013; the expectation that the Aurora North mine train relocations will be 90 per cent complete after 2013; the expectation that the Mildred Lake mine train replacements will be 75 per cent complete after 2013; the expectation that the Corporation will invest $25 million ($70 million gross to Syncrude) in research and development in 2013; the expected 2013 single-point Syncrude production estimate of 110 million barrels (40.4 million barrels net to the Corporation) and the expected 2013 Syncrude production range of 105 to 115 million barrels (39 to 42 million barrels net to the Corporation); the timing of the turnaround of Coker 8-1; the expected sales in 2013; the expected West Texas Intermediate ("WTI") price in 2013; the expected average discount for synthetic crude oil ("SCO") to WTI in 2013; the expected foreign exchange rate in 2013; the expected operating expenses and purchased energy costs in 2013; the expected cash flow from operations and cash flow from operations per share in 2013; all expectations regarding net debt; the expected amount of Crown royalties in 2013; the expected amount of current taxes in 2013; the expectations regarding the amount of taxes after 2013; the expected natural gas prices in 2013; and the anticipated impact of increases or decreases in oil prices, production, operating expenses, foreign exchange rates and natural gas prices on the Corporation's cash flow from operations.

You are cautioned not to place undue reliance on forward-looking statements, as there can be no assurance that the plans, intentions or expectations upon which they are based will occur. By their nature, forward-looking statements involve numerous assumptions, known and unknown risks and uncertainties, both general and specific, that contribute to the possibility that the predictions, forecasts, projections and other forward-looking statements will not occur. Although the Corporation believes that the expectations represented by such forward-looking statements are reasonable and reflect the current views of the Corporation, there can be no assurance that such expectations will prove to be correct.

The factors or assumptions on which the forward-looking information is based include, but are not limited to: the assumptions outlined in the Corporation's 2012 and 2013 guidance document as posted on the Corporation's website at www.cdnoilsands.com as of the date hereof and as subsequently amended or replaced from time to time, including without limitation, the assumptions as to production, operating expenses and oil prices; the successful and timely implementation of capital projects; Syncrude's major project spending plans; the ability to obtain regulatory and Syncrude joint venture owner approval; the Corporation's ability to either generate sufficient cash flow from operations to meet its current and future obligations or obtain external sources of debt and equity capital; the continuation of assumed tax, royalty and regulatory regimes and the accuracy of the estimates of the Corporation's reserves and resources volumes.

Some of the risks and other factors which could cause results to differ materially from those expressed in the forward-looking statements contained in this press release include, but are not limited to: general operational issues relating to a complex, integrated mining and upgrading facility; operating constraints due to weather, especially as it relates to bitumen production; general economic, business and market conditions; changes in commodity prices; the unanimous joint venture owner approval for major expansions; the impact that pipeline capacity and refinery demand have on prices for the Corporation's product; the occurrence of unexpected events such as fires, equipment failures and other similar events; the impacts of legislative or regulatory changes, especially as such relate to royalties, taxation, the environment and tailings; unsuccessful and untimely implementation of planned turnarounds and capital projects; the volatility of crude oil prices; the volatility of the SCO to WTI differential and such other risks and uncertainties described in the Corporation's Annual Information Form dated February 23, 2012 and in the reports and filings made with the securities regulatory authorities from time to time by the Corporation, which are available on the Corporation's profile on SEDAR at www.sedar.com and on the Corporation's website at www.cdnoilsands.com.

You are cautioned that the foregoing list of important factors is not exhaustive. The 2013 Budget reflects various assumptions, which are outlined in the guidance document dated November 29, 2012. Furthermore, the forward-looking statements contained in this press release are made as of the date of this press release, and unless required by law, the Corporation does not undertake any obligation to update publicly or to revise any of the included forward-looking statements, whether as a result of new information, future events or otherwise. The forward-looking statements contained in this press release are expressly qualified by this cautionary statement. The information was approved by management on November 29, 2012 and circumstances after this date may change the outcomes or results achieved.

Non-GAAP Financial Measures: In this press release we refer to financial measures that do not have any standardized meaning as prescribed by Canadian GAAP, such as cash flow from operations, cash flow from operations on a per share basis, free cash flow, net debt and certain per barrel measures. Please refer to Canadian Oil Sands' Third Quarter 2012 Report, which is available on the Corporation's profile on SEDAR at www.sedar.com and on the Corporation's website at www.cdnoilsands.com for more information regarding non-GAAP financial measures. Free cash flow is not discussed in our Third Quarter 2012 Report, but is discussed in this release. Free cash flow (cash flow from operations less capital expenditures) is a non-GAAP financial measure which we believe provides additional meaningful information about the Corporation's liquidity and its capacity to fund dividends.

Contacts:
Canadian Oil Sands Limited
Siren Fisekci
VP, Investor & Corporate Relations
(403) 218-6228

Canadian Oil Sands Limited
Alison Trollope
Manager Investor Relations
(403) 218-6231
www.cdnoilsands.com

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
With an estimated 50 billion devices connected to the Internet by 2020, several industries will begin to expand their capabilities for retaining end point data at the edge to better utilize the range of data types and sheer volume of M2M data generated by the Internet of Things. In his session at @ThingsExpo, Don DeLoach, CEO and President of Infobright, will discuss the infrastructures businesses will need to implement to handle this explosion of data by providing specific use cases for filte...
SYS-CON Events announced today that VAI, a leading ERP software provider, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. VAI (Vormittag Associates, Inc.) is a leading independent mid-market ERP software developer renowned for its flexible solutions and ability to automate critical business functions for the distribution, manufacturing, specialty retail and service sectors. An IBM Premier Business Part...
Cognitive Computing is becoming the foundation for a new generation of solutions that have the potential to transform business. Unlike traditional approaches to building solutions, a cognitive computing approach allows the data to help determine the way applications are designed. This contrasts with conventional software development that begins with defining logic based on the current way a business operates. In her session at 18th Cloud Expo, Judith S. Hurwitz, President and CEO of Hurwitz & ...
Fortunately, meaningful and tangible business cases for IoT are plentiful in a broad array of industries and vertical markets. These range from simple warranty cost reduction for capital intensive assets, to minimizing downtime for vital business tools, to creating feedback loops improving product design, to improving and enhancing enterprise customer experiences. All of these business cases, which will be briefly explored in this session, hinge on cost effectively extracting relevant data from ...
SYS-CON Events announced today that Men & Mice, the leading global provider of DNS, DHCP and IP address management overlay solutions, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. The Men & Mice Suite overlay solution is already known for its powerful application in heterogeneous operating environments, enabling enterprises to scale without fuss. Building on a solid range of diverse platform support,...
As enterprises work to take advantage of Big Data technologies, they frequently become distracted by product-level decisions. In most new Big Data builds this approach is completely counter-productive: it presupposes tools that may not be a fit for development teams, forces IT to take on the burden of evaluating and maintaining unfamiliar technology, and represents a major up-front expense. In his session at @BigDataExpo at @ThingsExpo, Andrew Warfield, CTO and Co-Founder of Coho Data, will dis...
SYS-CON Events announced today that Pythian, a global IT services company specializing in helping companies adopt disruptive technologies to optimize revenue-generating systems, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Founded in 1997, Pythian is a global IT services company that helps companies compete by adopting disruptive technologies such as cloud, Big Data, advanced analytics, and DevO...
SYS-CON Events announced today that iDevices®, the preeminent brand in the connected home industry, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. iDevices, the preeminent brand in the connected home industry, has a growing line of HomeKit-enabled products available at the largest retailers worldwide. Through the “Designed with iDevices” co-development program and its custom-built IoT Cloud Infrastruc...
SYS-CON Events announced today that Alert Logic, Inc., the leading provider of Security-as-a-Service solutions for the cloud, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Alert Logic, Inc., provides Security-as-a-Service for on-premises, cloud, and hybrid infrastructures, delivering deep security insight and continuous protection for customers at a lower cost than traditional security solutions. Ful...
SYS-CON Events announced today that Interoute, owner-operator of one of Europe's largest networks and a global cloud services platform, has been named “Bronze Sponsor” of SYS-CON's 18th Cloud Expo, which will take place on June 7-9, 2015 at the Javits Center in New York, New York. Interoute is the owner-operator of one of Europe's largest networks and a global cloud services platform which encompasses 12 data centers, 14 virtual data centers and 31 colocation centers, with connections to 195 ad...
SYS-CON Events announced today that Commvault, a global leader in enterprise data protection and information management, has been named “Bronze Sponsor” of SYS-CON's 18th International Cloud Expo, which will take place on June 7–9, 2016, at the Javits Center in New York City, NY, and the 19th International Cloud Expo, which will take place on November 1–3, 2016, at the Santa Clara Convention Center in Santa Clara, CA. Commvault is a leading provider of data protection and information management...
Eighty percent of a data scientist’s time is spent gathering and cleaning up data, and 80% of all data is unstructured and almost never analyzed. Cognitive computing, in combination with Big Data, is changing the equation by creating data reservoirs and using natural language processing to enable analysis of unstructured data sources. This is impacting every aspect of the analytics profession from how data is mined (and by whom) to how it is delivered. This is not some futuristic vision: it's ha...
With the Apple Watch making its way onto wrists all over the world, it’s only a matter of time before it becomes a staple in the workplace. In fact, Forrester reported that 68 percent of technology and business decision-makers characterize wearables as a top priority for 2015. Recognizing their business value early on, FinancialForce.com was the first to bring ERP to wearables, helping streamline communication across front and back office functions. In his session at @ThingsExpo, Kevin Roberts...
One of the bewildering things about DevOps is integrating the massive toolchain including the dozens of new tools that seem to crop up every year. Part of DevOps is Continuous Delivery and having a complex toolchain can add additional integration and setup to your developer environment. In his session at @DevOpsSummit at 18th Cloud Expo, Miko Matsumura, Chief Marketing Officer of Gradle Inc., will discuss which tools to use in a developer stack, how to provision the toolchain to minimize onboa...
The cloud promises new levels of agility and cost-savings for Big Data, data warehousing and analytics. But it’s challenging to understand all the options – from IaaS and PaaS to newer services like HaaS (Hadoop as a Service) and BDaaS (Big Data as a Service). In her session at @BigDataExpo at @ThingsExpo, Hannah Smalltree, a director at Cazena, will provide an educational overview of emerging “as-a-service” options for Big Data in the cloud. This is critical background for IT and data profes...
Silver Spring Networks, Inc. (NYSE: SSNI) extended its Internet of Things technology platform with performance enhancements to Gen5 – its fifth generation critical infrastructure networking platform. Already delivering nearly 23 million devices on five continents as one of the leading networking providers in the market, Silver Spring announced it is doubling the maximum speed of its Gen5 network to up to 2.4 Mbps, increasing computational performance by 10x, supporting simultaneous mesh communic...
SYS-CON Events announced today that Fusion, a leading provider of cloud services, will exhibit at SYS-CON's 18th International Cloud Expo®, which will take place on June 7-9, 2016, at the Javits Center in New York City, NY. Fusion, a leading provider of integrated cloud solutions to small, medium and large businesses, is the industry's single source for the cloud. Fusion's advanced, proprietary cloud service platform enables the integration of leading edge solutions in the cloud, including clou...
Most people haven’t heard the word, “gamification,” even though they probably, and perhaps unwittingly, participate in it every day. Gamification is “the process of adding games or game-like elements to something (as a task) so as to encourage participation.” Further, gamification is about bringing game mechanics – rules, constructs, processes, and methods – into the real world in an effort to engage people. In his session at @ThingsExpo, Robert Endo, owner and engagement manager of Intrepid D...
WebRTC has had a real tough three or four years, and so have those working with it. Only a few short years ago, the development world were excited about WebRTC and proclaiming how awesome it was. You might have played with the technology a couple of years ago, only to find the extra infrastructure requirements were painful to implement and poorly documented. This probably left a bitter taste in your mouth, especially when things went wrong.
Learn how IoT, cloud, social networks and last but not least, humans, can be integrated into a seamless integration of cooperative organisms both cybernetic and biological. This has been enabled by recent advances in IoT device capabilities, messaging frameworks, presence and collaboration services, where devices can share information and make independent and human assisted decisions based upon social status from other entities. In his session at @ThingsExpo, Michael Heydt, founder of Seamless...