Click here to close now.

Welcome!

.NET Authors: Plutora Blog, Aria Blog, Pat Romanski, Elizabeth White, Hovhannes Avoyan

News Feed Item

Minera IRL Ltd Announces Definitive Feasibility Study, Ollachea Project, Peru

LONDON, UNITED KINGDOM and TORONTO, ONTARIO -- (Marketwire) -- 11/29/12 -- Minera IRL Limited ("Minera IRL" or the "Company") (TSX:IRL)(AIM:MIRL)(BVL:MIRL), the Latin American gold mining company, is pleased to announce the results of a Definitive Feasibility Study ("DFS") on its Ollachea Project (the "Project"), Peru. The Project is 100% owned by Minera IRL SA subsidiary Minera Kuri Kullu SA ("MKK"). The DFS was carried out by international engineering firm AMEC in conjunction with Coffey Mining, who contributed the resource estimation and underground mining aspects of the study.

Highlights:

Project Economic Indicators


--  Using a gold price of $1,300 per ounce, NPV @ 7% real of $264 million
    (pre-tax) and $155 million (post tax); and IRR of 29.2% (pre tax) and
    22.1% (post tax) 
    
--  Up-front capital cost estimate of $177.5 million 
    
--  Life-of-mine ("LOM") cash operating cost of $499 per ounce 

Project Physical Indicators


--  Canadian National Instrument 43-101 ("NI 43-101") compliant Indicated
    Resource of 10.6 million tonnes grading 4.0g/t gold containing 1.4
    million ounces gold 
    
--  Probable Mineral Reserve of 9.3 million tonnes grading 3.4g/t gold
    containing 1.0 million ounces 
    
--  Rate of 1.1 million tonnes per annum to produce an average of 113,000
    ounces gold per year at full capacity 
    
--  Nine year initial mine life including ramp-up and down 
    
--  Underground mining accessed by a 1.2km tunnel currently over 800 metres
    advanced 
    
--  Conventional metallurgical processing to extract 91% of the gold 

Next Steps


--  Environmental Impact Assessment ("EIA") to be submitted before year-end
    thereby initiating permitting 
    
--  Investigating financing and early commencement of detailed engineering 
    
--  Production forecast to commence beginning 2015 
    
--  Upside potential includes the adjacent Concurayoc Zone with a 0.9
    million ounces Inferred Resource which is not included in the DFS. The
    Minapampa and Concurayoc zones are open ended both along strike and down
    dip. 

Note: $ denominates United States ("US") dollars unless otherwise stated.

"Ollachea's DFS confirms that Minera IRL has an economically and technically robust, long life project." said Courtney Chamberlain, Executive Chairman of Minera IRL. "Our team of engineers and consultants have done an excellent job on this comprehensive evaluation. This has been bolstered by the practical underground mining experience being obtained from the ongoing exploration drive, which has now advanced over 800 meters. We are confident of a much longer mine life than the initial nine years defined in this study considering that over one million ounces of Inferred Resource has already been identified and that the gold bearing structures are open ended along strike and down dip."

"The EIA will be submitted to the Peruvian authorities shortly thus commencing the permitting process. We are investigating financing options and intend to commence detailed engineering early in 2013. Our target is to start ore processing at the beginning of 2015."

Financial Analysis

The financial analysis was undertaken in constant US dollars, 100% Project, stand alone in country and 100% equity finance basis. It was undertaken at a base case gold price of $1,300/oz. However, the analysis was also performed using a gold price of $1,600/oz to show the impact of a higher gold price. The results of the financial analysis are set out below.


----------------------------------------------------------------------------
Parameter              Units                Financial Results               
                             -----------------------------------------------
                              $1,300/oz (base case)         $1,600/oz       
                             -----------------------------------------------
                               Pre-tax    Post-tax     Pre-tax    Post-tax  
----------------------------------------------------------------------------
Project cash flow       $M       489         325         749         486    
----------------------------------------------------------------------------
NPV at 5% real          $M       316         194         506         310    
----------------------------------------------------------------------------
NPV at 7% real          $M       264         155         434         258    
----------------------------------------------------------------------------
NPV at 10% real         $M       199         108         343         194    
----------------------------------------------------------------------------
IRR (real)               %       29.2       22.1        40.2        30.2    
----------------------------------------------------------------------------
Payback                years     3.2         3.7         2.5         3.0    
----------------------------------------------------------------------------
Note:                                                                       
1. NPVs as at commencement of construction                                  
2. NPVs are based on mid-period discounting                                 
3. Before tax is before Special Mining Tax, Workers' Participation Profit of
    8% and Income Taxes of 30%                                              
4. Payback starts from the commencement of production                       
5. The financial results are on 100% Project basis and exclude the agreement
    with the community for a 5% participation in MKK on commencement of     
    production and the Second Additional Payment payable by MKK and due to  
    Rio Tinto in accordance with Mining Claim Transfer Agreement dated 23   
    February 2007.                                                          
----------------------------------------------------------------------------

Other assumptions included in the financial analysis are:


--  US$: PEN (Peru Sol) of 2.65 
--  Third party 1% NSR Royalty 
--  Peru Royalty based on an operating margin sliding scale 
--  Peru Special Mining Tax based on a operating margin sliding scale 
--  Peru Workers' Profit Participation of 8% of pre-tax profits 
--  Peru Income tax rate of 30% 

Mineral Resources and Mineral Reserves

A NI 43-101 compliant Mineral Resource estimate was announced on 18 July 2012. This Mineral Resource estimate was carried out by consulting firm Coffey Mining Pty Ltd.

The Indicated Mineral Resource estimate over the Minapampa Zone totals 10.6 million tonnes averaging 4.0 g/t gold containing 1.4 million ounces. This resource is contained within six discrete horizons over a strike length of approximately 950 meters and down- dip approximately 350 meters. This estimate was based upon 151 diamond drill holes for 59,509 meters. The mineral resource estimate applies a 2g/t gold bottom cut and top cutting as appropriate for each of the six discrete gold-mineralized horizons that have been defined to date. The dry in-situ bulk density within mineralised zones, based upon 103 bulk density determinations, is 2.83 tonnes per cubic meter.

Included within the Indicated Mineral Resource envelope, the higher grade core Indicated Mineral Resource, using a 3.5g/t gold cut-off, totals 5.1 million tonnes grading 5.3g/t gold containing 0.9 million ounces.

In addition, the Inferred Mineral Resource at Minapampa and Concurayoc, approximately 400 meters west of Minapampa, totals 13.7 million tonnes grading 2.9 g/t gold for 1.2 million ounces. With additional future resource definition drilling, this Inferred Mineral Resource offers potential for a significant mine life extension. The deposit remains open along strike and down dip providing significant future exploration potential.

Probable Mineral Reserves at Minapampa, are shown in the following table. The Probable Mineral Reserves are included within the Indicated Mineral Resources and inclusive of mining dilution.


----------------------------------------------------------------------------
                                       Tonnage     Au Grade    Contained Au 
Category                                 Mt          g/t           koz      
----------------------------------------------------------------------------
Ore (+2g/t Au)                           8.7         3.5           983      
----------------------------------------------------------------------------
Low Grade Development Ore                0.6         1.5            28      
(+1g/t to 2g/t Au)                                                          
----------------------------------------------------------------------------
Probable Mineral Reserves                9.3         3.4          1,011     
----------------------------------------------------------------------------

The low grade development ore is sourced from development drives that traverse through Indicated Mineral Resource but has been diluted below the Project COG of 2.0g/t Au. As the mining cost for this material will have already been expensed, it is economic to treat through the plant. A mill cut-off grade of 1.0g/t Au has been applied to this material.

Mining & Processing

The mining method will be long-hole open stoping with paste backfill. The main access to the orebody will be via a 1.2 km-long exploration access drive from the plant site in the adjacent valley. This drive is currently in progress and has already advanced over 800 meters. The drive will access the orebody near the lower limit of the drill defined deposit so most ore mining will be from the bottom upwards. Extraction will occur along the orebody strike direction on a retreat basis.

Mine development will continue in parallel with the plant and infrastructure construction. Whilst some ore will be mined and stockpiled during the development period, the actual ore stoping production is scheduled to commence in early 2015, ramping up to the full 1.1 million tonnes per annum rate by mid-2016. Development waste of 2.6Mt will be mined over the LOM.

A comprehensive metallurgical testing programme has been completed in Australia and the United States. This demonstrated good metallurgical response to conventional crush, grind, gravity concentration and carbon-in-leach technology. Gold recovery of 91% is projected.

The processing plant will have a capacity of 1.1 million tonnes per annum. Tailings will be filtered and split between underground cemented fill and dry stacking on surface.

The average steady state (approx. 6.6 years) gold production is approximately 113koz per annum. The following table summarises the mine and processing production.


----------------------------------------------------------------------------
                           LG Dev. Ore                                      
           Ore Mined          Mined      Ore Processed                      
      --------------------------------------------------                    
                    Au             Au   Total     Au                  Au    
          Ore     grade     Ore   grade  Ore    grade    Recovery Production
Year     (kt)     (g/t)    (kt)   (g/t) (kt)    (g/t)      (%)      (koz)   
----------------------------------------------------------------------------
2014      35       3.11     11    1.56    -       -         -         -     
----------------------------------------------------------------------------
2015      586      3.46     110   1.51   680     3.21     90.2%       63    
----------------------------------------------------------------------------
2016      811      3.07     80    1.53   938     2.91     88.8%       78    
----------------------------------------------------------------------------
2017     1,097     3.48     55    1.49  1,117    3.45     90.3%      112    
----------------------------------------------------------------------------
2018     1,095     3.66     99    1.44  1,127    3.60     91.2%      119    
----------------------------------------------------------------------------
2019     1,099     3.63     87    1.47  1,120    3.59     91.2%      118    
----------------------------------------------------------------------------
2020     1,106     3.81     132   1.51  1,132    3.76     92.0%      126    
----------------------------------------------------------------------------
2021     1,099     3.58     16    1.50  1,137    3.51     91.5%      118    
----------------------------------------------------------------------------
2022      862      3.25      -      -   1,128    2.83     91.1%       94    
----------------------------------------------------------------------------
2023      738      3.50      -      -    738     3.50     91.8%       76    
----------------------------------------------------------------------------
2024      203      2.90      -      -    203     2.90     93.1%       18    
----------------------------------------------------------------------------
Total    8,730     3.50     590   1.49  9,320    3.38     91.0%      921    
----------------------------------------------------------------------------

Taking into account the potential to convert the Inferred Mineral Resource at the nearby Concurayoc Zone to the Measured and Indicated categories, as well as the exploration upside, the Company considers that there is an excellent opportunity to extend the full 1.1 million tonnes per annum mining and treatment rate well beyond 2022.

Infrastructure

Ollachea is well served by existing infrastructure and sits astride the new Southern Interoceanic Highway. A high tension power line passes over the project site and a long term contract has been signed with the hydroelectric supplier. There is an abundant source of water and a significant portion of the workforce will be recruited from the local community.

A permanent camp will be developed close to the plant site to accommodate 200 employees.

Capital Cost Estimate

Project development capital cost is estimated to be $177.5 million with an additional LOM sustaining capital of $41.6 million and $4.2 million for closure capital. Capital costs are summarised in the following table.


----------------------------------------------------------------------------
Item                                                                 Cost   
                                                                      $M    
----------------------------------------------------------------------------
Project Capital                                                             
----------------------------------------------------------------------------
  Mining                                                             55.4   
----------------------------------------------------------------------------
  Site Development                                                    3.9   
----------------------------------------------------------------------------
  Process Plant                                                      58.4   
----------------------------------------------------------------------------
  Ancillary Buildings                                                 3.9   
----------------------------------------------------------------------------
  Tailings System                                                     5.7   
----------------------------------------------------------------------------
  Indirect and Owners Cost                                           31.4   
----------------------------------------------------------------------------
  Contingency                                                        19.0   
----------------------------------------------------------------------------
  Total Project Capital                                              177.5  
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Sustaining Capital                                                   41.6   
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Closure Costs (net) - End of LOM                                      4.2   
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Total LOM Capital Cost                                               223.3  
----------------------------------------------------------------------------
Note:                                                                       
----------------------------------------------------------------------------
  1. Costs are in 3Q 2012 $.                                                
----------------------------------------------------------------------------

Operating Cost Estimate

Operating costs to mine and treat at a steady state production rate of 1.1 million tonnes per annum were derived from first principles. The LOM average unit operating costs are summarised in the following table.


----------------------------------------------------------------------------
Item                           $/t ore                      $/oz            
----------------------------------------------------------------------------
Mining                          23.4                         237            
----------------------------------------------------------------------------
Processing                      21.5                         218            
----------------------------------------------------------------------------
G&A                              4.3                         44             
----------------------------------------------------------------------------
Total operating                 49.2                         499            
costs                                                                       
----------------------------------------------------------------------------
Note:                                                                       
 1. Costs are in 3Q 2012 $.                                                 
 2. Operating cash costs exclude costs for freight and refining dore, and   
royalties.                                                                  
----------------------------------------------------------------------------

Environmental & Permitting

Environmental baseline information has been collected over approximately a three year period. This is being used in conjunction with special studies, such as hydrogeology and geotechnical, and DFS design details to produce an EIA which is currently in progress and is expected to be submitted by the end of 2012. The submission of the EIA to the Peruvian government authorities will be the basis for the development permitting process.

Community Relations

MKK has developed excellent relationships with the local community and has a 30 year development and operating permit in place. The community will become a 5% equity participant in MKK upon the commencement of production. A significant portion of the workforce will be local people who will be trained and employed at the operation.

Archaeological clearance has been granted for most of the required plant, tailings and infrastructure locations. Remaining clearance is in progress but no sites of national significance have been identified within the area of planned use.

Project Schedule and Moving Forward

The successful completion of the DFS establishes the basis for moving quickly towards development. The excellent progress on the exploration drive will provide the opportunity for uninterrupted progression toward establishing underground infrastructure and development. The EIA will be completed and submitted in a timely manner. Investigations into project financing will now be accelerated.

The project schedule is predicated upon a rapid move toward development. An engineering company will shortly be appointed to commence detailed design and identify long lead items for placement of early orders. Plant and infrastructure construction is scheduled for completion late in 2014 with first feed to the plant at the beginning of 2015. Canadian National Instrument 43-101 compliant report will be filed within the ensuing required 45 day period.

Competent Persons Statement

The preparation of the technical information contained herein was supervised by Courtney Chamberlain, Executive Chairman, BSc and MSc Metallurgical Engineering, a Fellow of the Australian Institute of Mining and Metallurgy (FAusIMM), who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release. Also by Donald McIver, VP Exploration of the Company, MSc Exploration and Economic Geology, a Fellow of the Australian Institute of Mining and Metallurgy (FAusIMM), as well as the Society of Economic Geologists (FSEG), who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the resource information in this press release.

The preparation of the Probable Mineral Reserve contained herein was supervised by John Hearne, FAusIMM, of Coffey Mining, who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release.

The preparation of the Indicated Mineral Resources contained herein was estimated by Doug Corley, Member of the Australasian Institute of Geoscientists (MAIG), and Registered Professional Geoscientist (RP Geo), of Coffey Mining, who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release.

Conference Call

Following the release, Minera IRL plans to host a conference call at 10:00 am Toronto (EDT), 3:00 pm UK (BST), 10:00 am Lima (PET) on November 29, 2012. To participate in the call please dial:


Toll Free (North America): 877-240-9772                                     
Local Toronto and International: 416-340-8527                               
Global: 800-2787-2090                                                       

A live webcast and archive will be available at: http://www.gowebcasting.com/4028

REPLAY:


Dial-in numbers: 905-694-9451 / 800-408-3053/ 800-3366-3052                 
The replay is available till December 6th, 2012                             
Passcode: 5695777                                                           

To view the images associated with this release, please visit the following link: http://media3.marketwire.com/docs/miner11.pdf

Minera IRL Limited is the AIM traded, TSX and BVL listed holding company of precious metals mining and exploration companies focused in Latin America. Minera IRL is led by an experienced senior management team with extensive industry experience, particularly operating in South America. The Group operates the Corihuarmi Gold Mine and the advanced gold projects Ollachea in Peru and Don Nicolas in Argentina. For more information, please visit www.minera-irl.com.

Some of the statements contained in this release are forward-looking statements, such as estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.

While these forward-looking statements, and any assumptions upon which they are based, are made in good faith and reflect our current judgment regarding the direction of our business, actual results will almost always vary, sometimes materially, from any estimates, predictions, projections, assumptions or other future performance suggestions herein. Except as required by applicable law or regulation, Minera IRL Limited does not intend to update any forward-looking statements to conform these statements to actual results.

Quality Assurance and Quality Control Procedures Disclosure

The Company has implemented and maintains a Minera IRL quality assurance/quality control (QA/QC) protocol on the Ollachea Project to ensure best industry practice in sampling and analysis of exploration and resource drill core samples. The insertion of field duplicates, certified standards and blank samples into the sample stream form part of the MIRL procedure (these act as an independent check on contamination, precision and accuracy in the analytical laboratory).

Assay results are reported once rigorous QAQC procedures have been approved.

Independent Audit Programmes

Towards maintaining compliancy with international standards as they pertain to the minerals industry resource evaluation and estimation procedure, MIRL regularly contracts the services of industry experts to conduct detailed audits of established QAQC procedures.

The Toronto Stock Exchange neither approves nor disapproves the information contained in this News Release.

Contacts:
Minera IRL
Trish Kent
Vice President, Corporate Relations
+511 418 1230

Canaccord Genuity Limited
(Nominated Adviser & Broker, London)
Adam Miller
+ 44 (0)20 7523 8350

finnCap (Co-broker, London)
Geoff Nash (Corporate Finance)
Matthew Robinson (Corporate Finance)
Joanna Weaving (Corporate Broking)
+ 44 (0)20 7600 1658

RBC Europe Ltd (Co-broker, London)
Stephen Foss
Martin Eales
+44 (0)20 7653 4000

Buchanan (Financial PR, London)
Bobby Morse
Gordon Poole
Louise Mason
+44 (0)20 7466 5000

Hill+Knowlton Strategies (PR, Toronto)
Rick Harari
+1 416 413 4766

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
SYS-CON Events announced today that GENBAND, a leading developer of real time communications software solutions, has been named “Silver Sponsor” of SYS-CON's WebRTC Summit, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. The GENBAND team will be on hand to demonstrate their newest product, Kandy. Kandy is a communications Platform-as-a-Service (PaaS) that enables companies to seamlessly integrate more human communications into their Web and mobile applications - creating more engaging experiences for their customers and boosting collaboration and productiv...
Roberto Medrano, Executive Vice President at SOA Software, had reached 30,000 page views on his home page - http://RobertoMedrano.SYS-CON.com/ - on the SYS-CON family of online magazines, which includes Cloud Computing Journal, Internet of Things Journal, Big Data Journal, and SOA World Magazine. He is a recognized executive in the information technology fields of SOA, internet security, governance, and compliance. He has extensive experience with both start-ups and large companies, having been involved at the beginning of four IT industries: EDA, Open Systems, Computer Security and now SOA.
From telemedicine to smart cars, digital homes and industrial monitoring, the explosive growth of IoT has created exciting new business opportunities for real time calls and messaging. In his session at @ThingsExpo, Ivelin Ivanov, CEO and Co-Founder of Telestax, shared some of the new revenue sources that IoT created for Restcomm – the open source telephony platform from Telestax. Ivelin Ivanov is a technology entrepreneur who founded Mobicents, an Open Source VoIP Platform, to help create, deploy, and manage applications integrating voice, video and data. He is the co-founder of TeleStax, a...
The industrial software market has treated data with the mentality of “collect everything now, worry about how to use it later.” We now find ourselves buried in data, with the pervasive connectivity of the (Industrial) Internet of Things only piling on more numbers. There’s too much data and not enough information. In his session at @ThingsExpo, Bob Gates, Global Marketing Director, GE’s Intelligent Platforms business, to discuss how realizing the power of IoT, software developers are now focused on understanding how industrial data can create intelligence for industrial operations. Imagine ...
Operational Hadoop and the Lambda Architecture for Streaming Data Apache Hadoop is emerging as a distributed platform for handling large and fast incoming streams of data. Predictive maintenance, supply chain optimization, and Internet-of-Things analysis are examples where Hadoop provides the scalable storage, processing, and analytics platform to gain meaningful insights from granular data that is typically only valuable from a large-scale, aggregate view. One architecture useful for capturing and analyzing streaming data is the Lambda Architecture, representing a model of how to analyze rea...
SYS-CON Events announced today that Vitria Technology, Inc. will exhibit at SYS-CON’s @ThingsExpo, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Vitria will showcase the company’s new IoT Analytics Platform through live demonstrations at booth #330. Vitria’s IoT Analytics Platform, fully integrated and powered by an operational intelligence engine, enables customers to rapidly build and operationalize advanced analytics to deliver timely business outcomes for use cases across the industrial, enterprise, and consumer segments.
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @ThingsExpo, Michael Sick, a Senior Manager and Big Data Architect within Ernst and Young's Financial Servi...
SYS-CON Events announced today that Open Data Centers (ODC), a carrier-neutral colocation provider, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place June 9-11, 2015, at the Javits Center in New York City, NY. Open Data Centers is a carrier-neutral data center operator in New Jersey and New York City offering alternative connectivity options for carriers, service providers and enterprise customers.
When it comes to the Internet of Things, hooking up will get you only so far. If you want customers to commit, you need to go beyond simply connecting products. You need to use the devices themselves to transform how you engage with every customer and how you manage the entire product lifecycle. In his session at @ThingsExpo, Sean Lorenz, Technical Product Manager for Xively at LogMeIn, will show how “product relationship management” can help you leverage your connected devices and the data they generate about customer usage and product performance to deliver extremely compelling and reliabl...
SYS-CON Events announced today that CodeFutures, a leading supplier of database performance tools, has been named a “Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9–11, 2015, at the Javits Center in New York, NY. CodeFutures is an independent software vendor focused on providing tools that deliver database performance tools that increase productivity during database development and increase database performance and scalability during production.
The IoT market is projected to be $1.9 trillion tidal wave that’s bigger than the combined market for smartphones, tablets and PCs. While IoT is widely discussed, what not being talked about are the monetization opportunities that are created from ubiquitous connectivity and the ensuing avalanche of data. While we cannot foresee every service that the IoT will enable, we should future-proof operations by preparing to monetize them with extremely agile systems.
There’s Big Data, then there’s really Big Data from the Internet of Things. IoT is evolving to include many data possibilities like new types of event, log and network data. The volumes are enormous, generating tens of billions of logs per day, which raise data challenges. Early IoT deployments are relying heavily on both the cloud and managed service providers to navigate these challenges. Learn about IoT, Big Data and deployments processing massive data volumes from wearables, utilities and other machines.
The explosion of connected devices / sensors is creating an ever-expanding set of new and valuable data. In parallel the emerging capability of Big Data technologies to store, access, analyze, and react to this data is producing changes in business models under the umbrella of the Internet of Things (IoT). In particular within the Insurance industry, IoT appears positioned to enable deep changes by altering relationships between insurers, distributors, and the insured. In his session at @ThingsExpo, Michael Sick, a Senior Manager and Big Data Architect within Ernst and Young's Financial Servi...
The major cloud platforms defy a simple, side-by-side analysis. Each of the major IaaS public-cloud platforms offers their own unique strengths and functionality. Options for on-site private cloud are diverse as well, and must be designed and deployed while taking existing legacy architecture and infrastructure into account. Then the reality is that most enterprises are embarking on a hybrid cloud strategy and programs. In this Power Panel at 15th Cloud Expo (http://www.CloudComputingExpo.com), moderated by Ashar Baig, Research Director, Cloud, at Gigaom Research, Nate Gordon, Director of T...
“In the past year we've seen a lot of stabilization of WebRTC. You can now use it in production with a far greater degree of certainty. A lot of the real developments in the past year have been in things like the data channel, which will enable a whole new type of application," explained Peter Dunkley, Technical Director at Acision, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Intelligent Systems Services will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Established in 1994, Intelligent Systems Services Inc. is located near Washington, DC, with representatives and partners nationwide. ISS’s well-established track record is based on the continuous pursuit of excellence in designing, implementing and supporting nationwide clients’ mission-critical systems. ISS has completed many successful projects in Healthcare, Commercial, Manufacturing, ...
PubNub on Monday has announced that it is partnering with IBM to bring its sophisticated real-time data streaming and messaging capabilities to Bluemix, IBM’s cloud development platform. “Today’s app and connected devices require an always-on connection, but building a secure, scalable solution from the ground up is time consuming, resource intensive, and error-prone,” said Todd Greene, CEO of PubNub. “PubNub enables web, mobile and IoT developers building apps on IBM Bluemix to quickly add scalable realtime functionality with minimal effort and cost.”
Sensor-enabled things are becoming more commonplace, precursors to a larger and more complex framework that most consider the ultimate promise of the IoT: things connecting, interacting, sharing, storing, and over time perhaps learning and predicting based on habits, behaviors, location, preferences, purchases and more. In his session at @ThingsExpo, Tom Wesselman, Director of Communications Ecosystem Architecture at Plantronics, will examine the still nascent IoT as it is coalescing, including what it is today, what it might ultimately be, the role of wearable tech, and technology gaps stil...
DevOps tends to focus on the relationship between Dev and Ops, putting an emphasis on the ops and application infrastructure. But that’s changing with microservices architectures. In her session at DevOps Summit, Lori MacVittie, Evangelist for F5 Networks, will focus on how microservices are changing the underlying architectures needed to scale, secure and deliver applications based on highly distributed (micro) services and why that means an expansion into “the network” for DevOps.
In the consumer IoT, everything is new, and the IT world of bits and bytes holds sway. But industrial and commercial realms encompass operational technology (OT) that has been around for 25 or 50 years. This grittier, pre-IP, more hands-on world has much to gain from Industrial IoT (IIoT) applications and principles. But adding sensors and wireless connectivity won’t work in environments that demand unwavering reliability and performance. In his session at @ThingsExpo, Ron Sege, CEO of Echelon, will discuss how as enterprise IT embraces other IoT-related technology trends, enterprises with i...