Welcome!

.NET Authors: Skytap Blog, Srinivasan Sundara Rajan, Adine Deford, David Fletcher, Pat Romanski

News Feed Item

Minera IRL Ltd Announces Definitive Feasibility Study, Ollachea Project, Peru

LONDON, UNITED KINGDOM and TORONTO, ONTARIO -- (Marketwire) -- 11/29/12 -- Minera IRL Limited ("Minera IRL" or the "Company") (TSX:IRL)(AIM:MIRL)(BVL:MIRL), the Latin American gold mining company, is pleased to announce the results of a Definitive Feasibility Study ("DFS") on its Ollachea Project (the "Project"), Peru. The Project is 100% owned by Minera IRL SA subsidiary Minera Kuri Kullu SA ("MKK"). The DFS was carried out by international engineering firm AMEC in conjunction with Coffey Mining, who contributed the resource estimation and underground mining aspects of the study.

Highlights:

Project Economic Indicators


--  Using a gold price of $1,300 per ounce, NPV @ 7% real of $264 million
    (pre-tax) and $155 million (post tax); and IRR of 29.2% (pre tax) and
    22.1% (post tax) 
    
--  Up-front capital cost estimate of $177.5 million 
    
--  Life-of-mine ("LOM") cash operating cost of $499 per ounce 

Project Physical Indicators


--  Canadian National Instrument 43-101 ("NI 43-101") compliant Indicated
    Resource of 10.6 million tonnes grading 4.0g/t gold containing 1.4
    million ounces gold 
    
--  Probable Mineral Reserve of 9.3 million tonnes grading 3.4g/t gold
    containing 1.0 million ounces 
    
--  Rate of 1.1 million tonnes per annum to produce an average of 113,000
    ounces gold per year at full capacity 
    
--  Nine year initial mine life including ramp-up and down 
    
--  Underground mining accessed by a 1.2km tunnel currently over 800 metres
    advanced 
    
--  Conventional metallurgical processing to extract 91% of the gold 

Next Steps


--  Environmental Impact Assessment ("EIA") to be submitted before year-end
    thereby initiating permitting 
    
--  Investigating financing and early commencement of detailed engineering 
    
--  Production forecast to commence beginning 2015 
    
--  Upside potential includes the adjacent Concurayoc Zone with a 0.9
    million ounces Inferred Resource which is not included in the DFS. The
    Minapampa and Concurayoc zones are open ended both along strike and down
    dip. 

Note: $ denominates United States ("US") dollars unless otherwise stated.

"Ollachea's DFS confirms that Minera IRL has an economically and technically robust, long life project." said Courtney Chamberlain, Executive Chairman of Minera IRL. "Our team of engineers and consultants have done an excellent job on this comprehensive evaluation. This has been bolstered by the practical underground mining experience being obtained from the ongoing exploration drive, which has now advanced over 800 meters. We are confident of a much longer mine life than the initial nine years defined in this study considering that over one million ounces of Inferred Resource has already been identified and that the gold bearing structures are open ended along strike and down dip."

"The EIA will be submitted to the Peruvian authorities shortly thus commencing the permitting process. We are investigating financing options and intend to commence detailed engineering early in 2013. Our target is to start ore processing at the beginning of 2015."

Financial Analysis

The financial analysis was undertaken in constant US dollars, 100% Project, stand alone in country and 100% equity finance basis. It was undertaken at a base case gold price of $1,300/oz. However, the analysis was also performed using a gold price of $1,600/oz to show the impact of a higher gold price. The results of the financial analysis are set out below.


----------------------------------------------------------------------------
Parameter              Units                Financial Results               
                             -----------------------------------------------
                              $1,300/oz (base case)         $1,600/oz       
                             -----------------------------------------------
                               Pre-tax    Post-tax     Pre-tax    Post-tax  
----------------------------------------------------------------------------
Project cash flow       $M       489         325         749         486    
----------------------------------------------------------------------------
NPV at 5% real          $M       316         194         506         310    
----------------------------------------------------------------------------
NPV at 7% real          $M       264         155         434         258    
----------------------------------------------------------------------------
NPV at 10% real         $M       199         108         343         194    
----------------------------------------------------------------------------
IRR (real)               %       29.2       22.1        40.2        30.2    
----------------------------------------------------------------------------
Payback                years     3.2         3.7         2.5         3.0    
----------------------------------------------------------------------------
Note:                                                                       
1. NPVs as at commencement of construction                                  
2. NPVs are based on mid-period discounting                                 
3. Before tax is before Special Mining Tax, Workers' Participation Profit of
    8% and Income Taxes of 30%                                              
4. Payback starts from the commencement of production                       
5. The financial results are on 100% Project basis and exclude the agreement
    with the community for a 5% participation in MKK on commencement of     
    production and the Second Additional Payment payable by MKK and due to  
    Rio Tinto in accordance with Mining Claim Transfer Agreement dated 23   
    February 2007.                                                          
----------------------------------------------------------------------------

Other assumptions included in the financial analysis are:


--  US$: PEN (Peru Sol) of 2.65 
--  Third party 1% NSR Royalty 
--  Peru Royalty based on an operating margin sliding scale 
--  Peru Special Mining Tax based on a operating margin sliding scale 
--  Peru Workers' Profit Participation of 8% of pre-tax profits 
--  Peru Income tax rate of 30% 

Mineral Resources and Mineral Reserves

A NI 43-101 compliant Mineral Resource estimate was announced on 18 July 2012. This Mineral Resource estimate was carried out by consulting firm Coffey Mining Pty Ltd.

The Indicated Mineral Resource estimate over the Minapampa Zone totals 10.6 million tonnes averaging 4.0 g/t gold containing 1.4 million ounces. This resource is contained within six discrete horizons over a strike length of approximately 950 meters and down- dip approximately 350 meters. This estimate was based upon 151 diamond drill holes for 59,509 meters. The mineral resource estimate applies a 2g/t gold bottom cut and top cutting as appropriate for each of the six discrete gold-mineralized horizons that have been defined to date. The dry in-situ bulk density within mineralised zones, based upon 103 bulk density determinations, is 2.83 tonnes per cubic meter.

Included within the Indicated Mineral Resource envelope, the higher grade core Indicated Mineral Resource, using a 3.5g/t gold cut-off, totals 5.1 million tonnes grading 5.3g/t gold containing 0.9 million ounces.

In addition, the Inferred Mineral Resource at Minapampa and Concurayoc, approximately 400 meters west of Minapampa, totals 13.7 million tonnes grading 2.9 g/t gold for 1.2 million ounces. With additional future resource definition drilling, this Inferred Mineral Resource offers potential for a significant mine life extension. The deposit remains open along strike and down dip providing significant future exploration potential.

Probable Mineral Reserves at Minapampa, are shown in the following table. The Probable Mineral Reserves are included within the Indicated Mineral Resources and inclusive of mining dilution.


----------------------------------------------------------------------------
                                       Tonnage     Au Grade    Contained Au 
Category                                 Mt          g/t           koz      
----------------------------------------------------------------------------
Ore (+2g/t Au)                           8.7         3.5           983      
----------------------------------------------------------------------------
Low Grade Development Ore                0.6         1.5            28      
(+1g/t to 2g/t Au)                                                          
----------------------------------------------------------------------------
Probable Mineral Reserves                9.3         3.4          1,011     
----------------------------------------------------------------------------

The low grade development ore is sourced from development drives that traverse through Indicated Mineral Resource but has been diluted below the Project COG of 2.0g/t Au. As the mining cost for this material will have already been expensed, it is economic to treat through the plant. A mill cut-off grade of 1.0g/t Au has been applied to this material.

Mining & Processing

The mining method will be long-hole open stoping with paste backfill. The main access to the orebody will be via a 1.2 km-long exploration access drive from the plant site in the adjacent valley. This drive is currently in progress and has already advanced over 800 meters. The drive will access the orebody near the lower limit of the drill defined deposit so most ore mining will be from the bottom upwards. Extraction will occur along the orebody strike direction on a retreat basis.

Mine development will continue in parallel with the plant and infrastructure construction. Whilst some ore will be mined and stockpiled during the development period, the actual ore stoping production is scheduled to commence in early 2015, ramping up to the full 1.1 million tonnes per annum rate by mid-2016. Development waste of 2.6Mt will be mined over the LOM.

A comprehensive metallurgical testing programme has been completed in Australia and the United States. This demonstrated good metallurgical response to conventional crush, grind, gravity concentration and carbon-in-leach technology. Gold recovery of 91% is projected.

The processing plant will have a capacity of 1.1 million tonnes per annum. Tailings will be filtered and split between underground cemented fill and dry stacking on surface.

The average steady state (approx. 6.6 years) gold production is approximately 113koz per annum. The following table summarises the mine and processing production.


----------------------------------------------------------------------------
                           LG Dev. Ore                                      
           Ore Mined          Mined      Ore Processed                      
      --------------------------------------------------                    
                    Au             Au   Total     Au                  Au    
          Ore     grade     Ore   grade  Ore    grade    Recovery Production
Year     (kt)     (g/t)    (kt)   (g/t) (kt)    (g/t)      (%)      (koz)   
----------------------------------------------------------------------------
2014      35       3.11     11    1.56    -       -         -         -     
----------------------------------------------------------------------------
2015      586      3.46     110   1.51   680     3.21     90.2%       63    
----------------------------------------------------------------------------
2016      811      3.07     80    1.53   938     2.91     88.8%       78    
----------------------------------------------------------------------------
2017     1,097     3.48     55    1.49  1,117    3.45     90.3%      112    
----------------------------------------------------------------------------
2018     1,095     3.66     99    1.44  1,127    3.60     91.2%      119    
----------------------------------------------------------------------------
2019     1,099     3.63     87    1.47  1,120    3.59     91.2%      118    
----------------------------------------------------------------------------
2020     1,106     3.81     132   1.51  1,132    3.76     92.0%      126    
----------------------------------------------------------------------------
2021     1,099     3.58     16    1.50  1,137    3.51     91.5%      118    
----------------------------------------------------------------------------
2022      862      3.25      -      -   1,128    2.83     91.1%       94    
----------------------------------------------------------------------------
2023      738      3.50      -      -    738     3.50     91.8%       76    
----------------------------------------------------------------------------
2024      203      2.90      -      -    203     2.90     93.1%       18    
----------------------------------------------------------------------------
Total    8,730     3.50     590   1.49  9,320    3.38     91.0%      921    
----------------------------------------------------------------------------

Taking into account the potential to convert the Inferred Mineral Resource at the nearby Concurayoc Zone to the Measured and Indicated categories, as well as the exploration upside, the Company considers that there is an excellent opportunity to extend the full 1.1 million tonnes per annum mining and treatment rate well beyond 2022.

Infrastructure

Ollachea is well served by existing infrastructure and sits astride the new Southern Interoceanic Highway. A high tension power line passes over the project site and a long term contract has been signed with the hydroelectric supplier. There is an abundant source of water and a significant portion of the workforce will be recruited from the local community.

A permanent camp will be developed close to the plant site to accommodate 200 employees.

Capital Cost Estimate

Project development capital cost is estimated to be $177.5 million with an additional LOM sustaining capital of $41.6 million and $4.2 million for closure capital. Capital costs are summarised in the following table.


----------------------------------------------------------------------------
Item                                                                 Cost   
                                                                      $M    
----------------------------------------------------------------------------
Project Capital                                                             
----------------------------------------------------------------------------
  Mining                                                             55.4   
----------------------------------------------------------------------------
  Site Development                                                    3.9   
----------------------------------------------------------------------------
  Process Plant                                                      58.4   
----------------------------------------------------------------------------
  Ancillary Buildings                                                 3.9   
----------------------------------------------------------------------------
  Tailings System                                                     5.7   
----------------------------------------------------------------------------
  Indirect and Owners Cost                                           31.4   
----------------------------------------------------------------------------
  Contingency                                                        19.0   
----------------------------------------------------------------------------
  Total Project Capital                                              177.5  
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Sustaining Capital                                                   41.6   
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Closure Costs (net) - End of LOM                                      4.2   
----------------------------------------------------------------------------
                                                                            
----------------------------------------------------------------------------
Total LOM Capital Cost                                               223.3  
----------------------------------------------------------------------------
Note:                                                                       
----------------------------------------------------------------------------
  1. Costs are in 3Q 2012 $.                                                
----------------------------------------------------------------------------

Operating Cost Estimate

Operating costs to mine and treat at a steady state production rate of 1.1 million tonnes per annum were derived from first principles. The LOM average unit operating costs are summarised in the following table.


----------------------------------------------------------------------------
Item                           $/t ore                      $/oz            
----------------------------------------------------------------------------
Mining                          23.4                         237            
----------------------------------------------------------------------------
Processing                      21.5                         218            
----------------------------------------------------------------------------
G&A                              4.3                         44             
----------------------------------------------------------------------------
Total operating                 49.2                         499            
costs                                                                       
----------------------------------------------------------------------------
Note:                                                                       
 1. Costs are in 3Q 2012 $.                                                 
 2. Operating cash costs exclude costs for freight and refining dore, and   
royalties.                                                                  
----------------------------------------------------------------------------

Environmental & Permitting

Environmental baseline information has been collected over approximately a three year period. This is being used in conjunction with special studies, such as hydrogeology and geotechnical, and DFS design details to produce an EIA which is currently in progress and is expected to be submitted by the end of 2012. The submission of the EIA to the Peruvian government authorities will be the basis for the development permitting process.

Community Relations

MKK has developed excellent relationships with the local community and has a 30 year development and operating permit in place. The community will become a 5% equity participant in MKK upon the commencement of production. A significant portion of the workforce will be local people who will be trained and employed at the operation.

Archaeological clearance has been granted for most of the required plant, tailings and infrastructure locations. Remaining clearance is in progress but no sites of national significance have been identified within the area of planned use.

Project Schedule and Moving Forward

The successful completion of the DFS establishes the basis for moving quickly towards development. The excellent progress on the exploration drive will provide the opportunity for uninterrupted progression toward establishing underground infrastructure and development. The EIA will be completed and submitted in a timely manner. Investigations into project financing will now be accelerated.

The project schedule is predicated upon a rapid move toward development. An engineering company will shortly be appointed to commence detailed design and identify long lead items for placement of early orders. Plant and infrastructure construction is scheduled for completion late in 2014 with first feed to the plant at the beginning of 2015. Canadian National Instrument 43-101 compliant report will be filed within the ensuing required 45 day period.

Competent Persons Statement

The preparation of the technical information contained herein was supervised by Courtney Chamberlain, Executive Chairman, BSc and MSc Metallurgical Engineering, a Fellow of the Australian Institute of Mining and Metallurgy (FAusIMM), who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release. Also by Donald McIver, VP Exploration of the Company, MSc Exploration and Economic Geology, a Fellow of the Australian Institute of Mining and Metallurgy (FAusIMM), as well as the Society of Economic Geologists (FSEG), who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the resource information in this press release.

The preparation of the Probable Mineral Reserve contained herein was supervised by John Hearne, FAusIMM, of Coffey Mining, who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release.

The preparation of the Indicated Mineral Resources contained herein was estimated by Doug Corley, Member of the Australasian Institute of Geoscientists (MAIG), and Registered Professional Geoscientist (RP Geo), of Coffey Mining, who is recognized as a Qualified Person for the purposes of National Instrument 43-101, and who has reviewed and approved the technical information in this press release.

Conference Call

Following the release, Minera IRL plans to host a conference call at 10:00 am Toronto (EDT), 3:00 pm UK (BST), 10:00 am Lima (PET) on November 29, 2012. To participate in the call please dial:


Toll Free (North America): 877-240-9772                                     
Local Toronto and International: 416-340-8527                               
Global: 800-2787-2090                                                       

A live webcast and archive will be available at: http://www.gowebcasting.com/4028

REPLAY:


Dial-in numbers: 905-694-9451 / 800-408-3053/ 800-3366-3052                 
The replay is available till December 6th, 2012                             
Passcode: 5695777                                                           

To view the images associated with this release, please visit the following link: http://media3.marketwire.com/docs/miner11.pdf

Minera IRL Limited is the AIM traded, TSX and BVL listed holding company of precious metals mining and exploration companies focused in Latin America. Minera IRL is led by an experienced senior management team with extensive industry experience, particularly operating in South America. The Group operates the Corihuarmi Gold Mine and the advanced gold projects Ollachea in Peru and Don Nicolas in Argentina. For more information, please visit www.minera-irl.com.

Some of the statements contained in this release are forward-looking statements, such as estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.

While these forward-looking statements, and any assumptions upon which they are based, are made in good faith and reflect our current judgment regarding the direction of our business, actual results will almost always vary, sometimes materially, from any estimates, predictions, projections, assumptions or other future performance suggestions herein. Except as required by applicable law or regulation, Minera IRL Limited does not intend to update any forward-looking statements to conform these statements to actual results.

Quality Assurance and Quality Control Procedures Disclosure

The Company has implemented and maintains a Minera IRL quality assurance/quality control (QA/QC) protocol on the Ollachea Project to ensure best industry practice in sampling and analysis of exploration and resource drill core samples. The insertion of field duplicates, certified standards and blank samples into the sample stream form part of the MIRL procedure (these act as an independent check on contamination, precision and accuracy in the analytical laboratory).

Assay results are reported once rigorous QAQC procedures have been approved.

Independent Audit Programmes

Towards maintaining compliancy with international standards as they pertain to the minerals industry resource evaluation and estimation procedure, MIRL regularly contracts the services of industry experts to conduct detailed audits of established QAQC procedures.

The Toronto Stock Exchange neither approves nor disapproves the information contained in this News Release.

Contacts:
Minera IRL
Trish Kent
Vice President, Corporate Relations
+511 418 1230

Canaccord Genuity Limited
(Nominated Adviser & Broker, London)
Adam Miller
+ 44 (0)20 7523 8350

finnCap (Co-broker, London)
Geoff Nash (Corporate Finance)
Matthew Robinson (Corporate Finance)
Joanna Weaving (Corporate Broking)
+ 44 (0)20 7600 1658

RBC Europe Ltd (Co-broker, London)
Stephen Foss
Martin Eales
+44 (0)20 7653 4000

Buchanan (Financial PR, London)
Bobby Morse
Gordon Poole
Louise Mason
+44 (0)20 7466 5000

Hill+Knowlton Strategies (PR, Toronto)
Rick Harari
+1 416 413 4766

More Stories By Marketwired .

Copyright © 2009 Marketwired. All rights reserved. All the news releases provided by Marketwired are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.

@ThingsExpo Stories
SYS-CON Events announced today that Windstream, a leading provider of advanced network and cloud communications, has been named “Silver Sponsor” of SYS-CON's 16th International Cloud Expo®, which will take place on June 9–11, 2015, at the Javits Center in New York, NY. Windstream (Nasdaq: WIN), a FORTUNE 500 and S&P 500 company, is a leading provider of advanced network communications, including cloud computing and managed services, to businesses nationwide. The company also offers broadband, phone and digital TV services to consumers primarily in rural areas.
The BPM world is going through some evolution or changes where traditional business process management solutions really have nowhere to go in terms of development of the road map. In this demo at 15th Cloud Expo, Kyle Hansen, Director of Professional Services at AgilePoint, shows AgilePoint’s unique approach to dealing with this market circumstance by developing a rapid application composition or development framework.
The Internet of Things is not new. Historically, smart businesses have used its basic concept of leveraging data to drive better decision making and have capitalized on those insights to realize additional revenue opportunities. So, what has changed to make the Internet of Things one of the hottest topics in tech? In his session at @ThingsExpo, Chris Gray, Director, Embedded and Internet of Things, discussed the underlying factors that are driving the economics of intelligent systems. Discover how hardware commoditization, the ubiquitous nature of connectivity, and the emergence of Big Data a...
"BSQUARE is in the business of selling software solutions for smart connected devices. It's obvious that IoT has moved from being a technology to being a fundamental part of business, and in the last 18 months people have said let's figure out how to do it and let's put some focus on it, " explained Dave Wagstaff, VP & Chief Architect, at BSQUARE Corporation, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4-6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
The major cloud platforms defy a simple, side-by-side analysis. Each of the major IaaS public-cloud platforms offers their own unique strengths and functionality. Options for on-site private cloud are diverse as well, and must be designed and deployed while taking existing legacy architecture and infrastructure into account. Then the reality is that most enterprises are embarking on a hybrid cloud strategy and programs. In this Power Panel at 15th Cloud Expo (http://www.CloudComputingExpo.com), moderated by Ashar Baig, Research Director, Cloud, at Gigaom Research, Nate Gordon, Director of T...
SYS-CON Events announced today that IDenticard will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. IDenticard™ is the security division of Brady Corp (NYSE: BRC), a $1.5 billion manufacturer of identification products. We have small-company values with the strength and stability of a major corporation. IDenticard offers local sales, support and service to our customers across the United States and Canada. Our partner network encompasses some 300 of the world's leading systems integrators and security s...

ARMONK, N.Y., Nov. 20, 2014 /PRNewswire/ --  IBM (NYSE: IBM) today announced that it is bringing a greater level of control, security and flexibility to cloud-based application development and delivery with a single-tenant version of Bluemix, IBM's platform-as-a-service. The new platform enables developers to build ap...

“In the past year we've seen a lot of stabilization of WebRTC. You can now use it in production with a far greater degree of certainty. A lot of the real developments in the past year have been in things like the data channel, which will enable a whole new type of application," explained Peter Dunkley, Technical Director at Acision, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
DevOps Summit 2015 New York, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that it is now accepting Keynote Proposals. The widespread success of cloud computing is driving the DevOps revolution in enterprise IT. Now as never before, development teams must communicate and collaborate in a dynamic, 24/7/365 environment. There is no time to wait for long development cycles that produce software that is obsolete at launch. DevOps may be disruptive, but it is essential.
"People are a lot more knowledgeable about APIs now. There are two types of people who work with APIs - IT people who want to use APIs for something internal and the product managers who want to do something outside APIs for people to connect to them," explained Roberto Medrano, Executive Vice President at SOA Software, in this SYS-CON.tv interview at Cloud Expo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
Nigeria has the largest economy in Africa, at more than US$500 billion, and ranks 23rd in the world. A recent re-evaluation of Nigeria's true economic size doubled the previous estimate, and brought it well ahead of South Africa, which is a member (unlike Nigeria) of the G20 club for political as well as economic reasons. Nigeria's economy can be said to be quite diverse from one point of view, but heavily dependent on oil and gas at the same time. Oil and natural gas account for about 15% of Nigera's overall economy, but traditionally represent more than 90% of the country's exports and as...
The Internet of Things is a misnomer. That implies that everything is on the Internet, and that simply should not be - especially for things that are blurring the line between medical devices that stimulate like a pacemaker and quantified self-sensors like a pedometer or pulse tracker. The mesh of things that we manage must be segmented into zones of trust for sensing data, transmitting data, receiving command and control administrative changes, and peer-to-peer mesh messaging. In his session at @ThingsExpo, Ryan Bagnulo, Solution Architect / Software Engineer at SOA Software, focused on desi...
"At our booth we are showing how to provide trust in the Internet of Things. Trust is where everything starts to become secure and trustworthy. Now with the scaling of the Internet of Things it becomes an interesting question – I've heard numbers from 200 billion devices next year up to a trillion in the next 10 to 15 years," explained Johannes Lintzen, Vice President of Sales at Utimaco, in this SYS-CON.tv interview at @ThingsExpo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
"For over 25 years we have been working with a lot of enterprise customers and we have seen how companies create applications. And now that we have moved to cloud computing, mobile, social and the Internet of Things, we see that the market needs a new way of creating applications," stated Jesse Shiah, CEO, President and Co-Founder of AgilePoint Inc., in this SYS-CON.tv interview at 15th Cloud Expo, held Nov 4–6, 2014, at the Santa Clara Convention Center in Santa Clara, CA.
SYS-CON Events announced today that Gridstore™, the leader in hyper-converged infrastructure purpose-built to optimize Microsoft workloads, will exhibit at SYS-CON's 16th International Cloud Expo®, which will take place on June 9-11, 2015, at the Javits Center in New York City, NY. Gridstore™ is the leader in hyper-converged infrastructure purpose-built for Microsoft workloads and designed to accelerate applications in virtualized environments. Gridstore’s hyper-converged infrastructure is the industry’s first all flash version of HyperConverged Appliances that include both compute and storag...
Today’s enterprise is being driven by disruptive competitive and human capital requirements to provide enterprise application access through not only desktops, but also mobile devices. To retrofit existing programs across all these devices using traditional programming methods is very costly and time consuming – often prohibitively so. In his session at @ThingsExpo, Jesse Shiah, CEO, President, and Co-Founder of AgilePoint Inc., discussed how you can create applications that run on all mobile devices as well as laptops and desktops using a visual drag-and-drop application – and eForms-buildi...
We certainly live in interesting technological times. And no more interesting than the current competing IoT standards for connectivity. Various standards bodies, approaches, and ecosystems are vying for mindshare and positioning for a competitive edge. It is clear that when the dust settles, we will have new protocols, evolved protocols, that will change the way we interact with devices and infrastructure. We will also have evolved web protocols, like HTTP/2, that will be changing the very core of our infrastructures. At the same time, we have old approaches made new again like micro-services...
Code Halos - aka "digital fingerprints" - are the key organizing principle to understand a) how dumb things become smart and b) how to monetize this dynamic. In his session at @ThingsExpo, Robert Brown, AVP, Center for the Future of Work at Cognizant Technology Solutions, outlined research, analysis and recommendations from his recently published book on this phenomena on the way leading edge organizations like GE and Disney are unlocking the Internet of Things opportunity and what steps your organization should be taking to position itself for the next platform of digital competition.
The 3rd International Internet of @ThingsExpo, co-located with the 16th International Cloud Expo - to be held June 9-11, 2015, at the Javits Center in New York City, NY - announces that its Call for Papers is now open. The Internet of Things (IoT) is the biggest idea since the creation of the Worldwide Web more than 20 years ago.
As the Internet of Things unfolds, mobile and wearable devices are blurring the line between physical and digital, integrating ever more closely with our interests, our routines, our daily lives. Contextual computing and smart, sensor-equipped spaces bring the potential to walk through a world that recognizes us and responds accordingly. We become continuous transmitters and receivers of data. In his session at @ThingsExpo, Andrew Bolwell, Director of Innovation for HP's Printing and Personal Systems Group, discussed how key attributes of mobile technology – touch input, sensors, social, and ...